BLD-Energy code compliance | 8/7/2020 | 8/7/2020 | 8/7/2020 | P | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-#### Inspection requested via web by Todd Twedt
|
BLD-Framing/Rough-in | 8/6/2020 | 8/6/2020 | 8/6/2020 | P | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-#### Inspection requested via web by Todd Twedt
|
BLD-Wall Bracing | 7/24/2020 | 7/24/2020 | 7/24/2020 | P | PART |
Brandon Shaw
|
|
|
Address to be readily visable from the street... 1st floor only...
|
BLD-Foundation | 6/17/2020 | 6/18/2020 | 6/18/2020 | P | PASS |
Jim Storey
|
|
|
Dane *screened* Phone #: ###-####
|
BLD-Footing | 6/16/2020 | 6/17/2020 | 6/17/2020 | P | PASS |
Jim Storey
|
|
|
Dane *screened* Phone #: ###-####
|
BLD-Footing | 6/15/2020 | 6/16/2020 | 6/16/2020 | P | CANC |
Jim Storey
|
|
|
Screened-Dane Phone #: ###-####
|
OVERRIDE | | | 6/8/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 5/18/2020 | 5/18/2020 | 6/8/2020 | | DONE |
Rob Patrick
|
|
|
1st Review Complete 06/03 Failed: 05/29 sfd L1 ePlan
|
Issue PAID IN FULL permit | | | 6/8/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/8/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/8/2020 | | 6/8/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/8/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 6/8/2020 | | DONE |
|
|
|
met
|
1st review completed | | | 6/3/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - PLAN CHECK | 5/18/2020 | | 6/3/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - MECHANICAL | 5/18/2020 | | 5/20/2020 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 5/18/2020 | 5/21/2020 | 5/19/2020 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 5/18/2020 | | 5/19/2020 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 5/18/2020 | | 5/19/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/18/2020 | | 5/19/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Application received | | | 5/18/2020 | | DONE |
|
|
|
Application submitted via PDS Online on May 18 2020 9:43AM
|
Plans ACCEPTED BY PLAN TECH | | | 5/18/2020 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/18/2020 | | DONE |
|
|
|
|
Intake Approval | | | 5/18/2020 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/18/2020 | | DONE |
|
|
|
|