BLD-Energy code compliance | 6/16/2020 | 6/16/2020 | 6/16/2020 | P | PASS |
Tell Riley
|
|
|
Screened- Derek Phone #: ###-####//ok when insulation added to rim board area and at the plumbing chase on exterior wall--will take photos of this completed//close cell foam with value of roughly R21 installed//
|
BLD-Framing/Rough-in | 6/12/2020 | 6/12/2020 | 6/12/2020 | P | PASS |
Tell Riley
|
|
|
screened // Derek Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/11/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/11/2020 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 5/19/2020 | 5/19/2020 | 6/10/2020 | | PASS |
Josh Bogle
|
|
|
05/25 remodel, ePlan - 1st done
|
Routing - PLAN CHECK | 6/10/2020 | | 6/10/2020 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/2020 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 6/10/2020 | | |
|
|
|
|
Routing - PLAN CHECK | 5/19/2020 | | 6/9/2020 | | FAIL |
Josh Bogle
|
|
|
see notes in ePlan
|
1st review completed | | | 6/9/2020 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLANNING | 5/19/2020 | | 5/20/2020 | | PASS |
Sue Cummings
|
|
|
|
Application received | | | 5/19/2020 | | DONE |
|
|
|
Application submitted via PDS Online on May 19 2020 8:26AM
|
Intake Approval | | | 5/19/2020 | | FAIL |
|
|
|
Prescreen comments #1
1. Please include site plan of entire parcel for exterior work.
|
Plans ACCEPTED BY PLAN TECH | | | 5/19/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/19/2020 | | DONE |
|
|
|
|