Plan Reviewer's activity | | | 7/20/2020 | | DONE |
Jenny Nelson
|
|
|
Spoke with contractor about electrical inspection requirement. No electrical work was shown on plans but a value was put in application. No electrical work was needed for space - removed electrical inspection requirement.
|
Permanent Occupancy | | | 7/20/2020 | | DONE |
|
|
|
|
BLD-Final | 7/16/2020 | 7/16/2020 | 7/16/2020 | A | PASS |
Jim Storey
|
|
|
Please call 30 minutes in advance Phone #: ###-#### Inspection requested via web by Chase Cheverton
|
FIRE-Final Inspection | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, no fire sprinkler modifications, no fire alarm modifications, fire extinguishers are placed with current inspection tags. Final life fire safety inspection is complete, signatures provided on permit sign off card.
Please call 30 minutes in advance Phone #: ###-#### Inspection requested via web by Chase Cheverton
|
Permit Ready to Issue | | | 7/13/2020 | | DONE |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
Print Occupancy Form | | | 7/13/2020 | | DONE |
|
|
|
|
Plan assigned to (J_N) | 7/6/2020 | 7/6/2020 | 7/10/2020 | | DONE |
Jenny Nelson
|
|
|
07/10 plan mod - Nuflare
|
Routing - PLAN CHECK | 7/10/2020 | | 7/10/2020 | | PASS |
Jenny Nelson
|
|
|
|
Route to Impact Fee Review | 7/6/2020 | 7/9/2020 | 7/7/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Plan Modification Accepted | | | 7/6/2020 | | DONE |
|
|
|
We showed a door that does not exist so we need to update the drawings showing no door in that location
|
BLD-Final | 6/30/2020 | 7/2/2020 | 7/2/2020 | A | NR |
Mike Jordan
|
|
|
Please call 30 minutes in advance Phone #: ###-#### Inspection requested via web by Chase Cheverton. Fire/life safety final has failed.
|
FIRE-Final Inspection | 6/30/2020 | 7/1/2020 | 7/1/2020 | P | FAIL |
Troy Cobbley
|
|
|
Resubmit plans showing the non-existant exterior door on the south wall of building, remove the two thumbturn deadbolts, repair exit signs. See city approved plans for corrections clouded in red.
Please call 30 minutes in advance Phone #: ###-#### Inspection requested via web by Chase Cheverton
|
BLD-Framing/Rough-in | 6/16/2020 | 6/17/2020 | 6/17/2020 | A | PASS |
Jim Storey
|
|
|
Please call 30 minutes in advance Phone #: ###-#### Inspection requested via web by Chase Cheverton
|
Print Occupancy Form | | | 6/17/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/15/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/12/2020 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 6/12/2020 | | DONE |
|
|
|
Correcting issue date
|
Plan assigned to (J_N) | 6/3/2020 | 6/3/2020 | 6/11/2020 | | DONE |
Jenny Nelson
|
|
|
1st complete 06/08 L1 NUFLARE ePlan - waiting for hillside
|
1st review completed | | | 6/11/2020 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2020 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 6/11/2020 | | DONE |
|
|
|
MET gwalker@adpboise.com
GC Form
Revised Value
|
Routing PW Grading-Hillside | 6/4/2020 | | 6/10/2020 | | PASS |
Jason C. Taylor
|
|
|
Not a hillside project, no review required. Jason Taylor ###-####
|
Routing - PLAN CHECK | 6/3/2020 | | 6/8/2020 | | PASS |
Jenny Nelson
|
|
|
|
Routing - PUBLIC WORKS | 6/3/2020 | | 6/4/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 6/3/2020 | | 6/3/2020 | | PASS |
Doug Chausow
|
|
|
Corrected address to 2163 E Summersweet Dr
|
Intake Approval | | | 6/2/2020 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 5/20/2020 | | DONE |
|
|
|
Application submitted via PDS Online on May 20 2020 8:46AM
|