BLD-Footing | 8/12/2020 | 8/13/2020 | 8/13/2020 | P | DONE |
Tony Young
|
|
|
Screened- pat Phone #: ###-####
|
BLD-Footing | 8/12/2020 | 8/13/2020 | 8/13/2020 | A | PASS |
Tony Young
|
|
|
Chris *screened Phone #: ###-####
|
BLD-Footing | 8/11/2020 | 8/12/2020 | 8/12/2020 | A | NR |
Tony Young
|
|
|
Chris *screened Phone #: ###-####// still waiting for soils approval
|
PubWorks Subgrade Approval | 8/12/2020 | 8/12/2020 | 8/12/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 8/11/2020 | 8/11/2020 | 8/11/2020 | P | PEND |
Tony Young
|
|
|
Chris *screened Phone #: ###-####
|
BLD-Footing | 8/10/2020 | 8/10/2020 | 8/11/2020 | P | NR |
Tony Young
|
|
|
Chris *screened Phone #: ###-####// needs soils approval 1st
|
Issue PAID IN FULL permit | | | 7/30/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/30/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/29/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/29/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/29/2020 | | DONE |
|
|
|
|
Telephone call | | | 7/29/2020 | | DONE |
|
|
|
called applicant to let them know we need a GC form from the GC
|
Plan assigned to (BJM) | 7/1/2020 | 7/1/2020 | 7/28/2020 | | DONE |
Brian McGowan
|
|
|
07/22- 1st Review Complete- 06/23 addition-Hillside- FAILED, Waiting for Hillside Review to finish-
|
Routing - PLAN CHECK | 7/28/2020 | | 7/28/2020 | | PASS |
Brian McGowan
|
|
|
|
Plan Reviewer's activity | | | 7/28/2020 | | DONE |
Brian McGowan
|
|
|
ESC- NO Energy- YES
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2020 | | DONE |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 6/30/2020 | | 7/15/2020 | | PASS |
Troy James
|
|
|
Applicant needs to upload manual j report.
|
1st review completed | | | 7/15/2020 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 6/23/2020 | | 7/8/2020 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor ###-####.
|
Plan Reviewer's activity | | | 7/8/2020 | | DONE |
Brian McGowan
|
|
|
As Per Andy the Contractor needs to list themselves as a Certified ESC Responsible Person when the project permits are ready to be issued.
|
Routing - PLAN CHECK | 6/23/2020 | | 7/2/2020 | | FAIL |
Brian McGowan
|
|
|
|
Routing - Erosion and Sediment | 6/23/2020 | | 6/26/2020 | | PASS |
Andy J. Long
|
|
|
ESC general permit ok, no plan required. Certified RP required
|
Routing - FIRE | 6/23/2020 | 6/23/2020 | 6/24/2020 | | PASS |
Lee G Meredith
|
|
|
New SFH
Sprinklers ae not required. Measuerments appear to be withi allowable limits.
|
Plan assigned to (JAB) Josh | 6/23/2020 | 6/23/2020 | 6/23/2020 | | DEFR |
Josh Bogle
|
|
|
06/23 addition
|
Routing - PLANNING | 6/23/2020 | | 6/23/2020 | | PASS |
Sue Cummings
|
|
|
|
Intake Approval | | | 6/23/2020 | | FAIL |
|
|
|
Applicant must apply for #114 with Planning and Zoning before submitting for Building Permit Application #406.
Please call ###-#### to be directed to a Front Desk Planner for submittal.
|
Telephone call | | | 6/23/2020 | | DONE |
|
|
|
Per Jason Taylor: Project is CAT 1 and does not need P&Z application. Please route to Jason for review of geotech report.
|
Intake Approval | | | 6/23/2020 | | PASS |
|
|
|
|
Intake Approval | | | 6/18/2020 | | FAIL |
|
|
|
Prescreen#1
Corrections below not met: Applicant must apply for #114 with Planning and Zoning before submitting for Building Permit Application #406.
Please call ###-#### to be directed to a Front Desk Planner for submittal.
|
Intake Approval | | | 5/26/2020 | | FAIL |
|
|
|
Project will require a CAT II Hillside application prior to acceptance of the building permit application. Application #114 will need to be filled out and turned in to the Planning & Zoning counter at city hall with the application fee. Once the application has been approved by P&Z please upload the approval letter and then this building permit case can be routed for approval. Jason Taylor ###-####.
|
Application received | | | 5/20/2020 | | DONE |
|
|
|
Application submitted via PDS Online on May 20 2020 10:01AM
|