Permit Information
Permit NumberBLD20-01812
StatusIssued
Name VISSER BUILDING CO
Site Address 501 S ASH ST
Project NameAsh St - Push & Pour
Customer Number 
ePlanReviewYes
Description
**PROJECT MANAGEMENT - Angie Brosious (ASH STREET PUSH & POUR) Permit for the first-time tenant build out of a 469 sq ft commercial space in the multi-family mixed-use building, Ash St Townhomes, constructed under BLD17-04464. Note: site work and envelope including exterior lighting was approved with the shell permit. Work to include: interior concrete slab; non-bearing interior walls; electrical power and interior lighting; mechanical equipment; plumbing for restroom and sink; and interior finishes in compliance with Chapter 8 of the 2015 IBC. Approval is contingent upon adhering to the approved plans on file. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JAR**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference7/31/20207/31/20207/31/2020PDONE
DetailsDave Hannah
please call ahead David - */Screened*/ Phone #: ###-####
Issue PAID IN FULL permit  7/31/2020 DONE
Print Occupancy Form  7/31/2020 DONE
Plan assigned to (JAR)6/10/20206/17/20207/13/2020 DONE
DetailsJulie Romig
1st Rev Comp - L3 Ash St Push & Pour
Routing - PLAN CHECK7/8/2020 7/13/2020 PASS
DetailsJulie Romig
PLANS/APPL TAKEN TO FRONT DESK  7/13/2020 DONE
Permit Ready to Issue  7/13/2020 DONE
ALL MET- Need GC
Need Revised Values
Routing PW Environmental7/8/2020 7/9/2020 PASS
DetailsZach Conde
PER ZACH: Passed on ePlan with this comment: “Approved with grease abatement as shown.” Please pass on Tidemark
Routing - FIRE6/10/20206/17/20207/8/2020 PASS
DetailsErika Akin
Attached comments to case
1st review completed  7/8/2020 FAIL
DetailsJulie Romig
Routing - PLAN CHECK6/17/2020 7/6/2020 FAIL
DetailsJulie Romig
Routing PW Solid Waste6/22/2020 6/26/2020 PASS
DetailsEvan Carpenter
Routing PW Flood Plain6/22/2020 6/23/2020 PASS
DetailsJason C. Taylor
Project is outside Special Flood Hazard Area, no floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
Routing PW Street Lights6/22/2020 6/23/2020 PASS
DetailsTom Marshall
Routing PW Sewer Design6/22/2020 6/22/2020 PASS
DetailsDeAnn Brown
Routing PW Drainage6/22/2020 6/22/2020 PASS
DetailsBrian Murphy
LESS THAN 1000 SQUARE FEET
Routing - PUBLIC WORKS6/17/2020 6/22/2020 PASS
DetailsMorgan Webb
ADDITIONAL FIXTURE FEES WILL BE DUE WITH TI
Routing - Addressing6/17/2020 6/18/2020 PASS
DetailsDoug Chausow
Routing - MECHANICAL6/17/2020 6/18/2020 PASS
DetailsTroy James
Routing - PLUMBING6/17/2020 6/17/2020 PASS
DetailsDan Ediger
Per Plans and the ISPC
Routing - PLANNING6/17/2020 6/17/2020 PASS
DetailsNicolette Womack
As per CUP17-00017. Exterior changes require DR review.
Intake Approval  6/10/2020 PASS
DetailsJulie Romig
Application received  6/2/2020 DONE
Application submitted via PDS Online on Jun 2 2020 11:12AM
Route to Impact Fee Review7/8/20207/11/2020   
Review requested for Commercial Permit
Routing PW Environmental6/22/2020   FAIL
Suitable and adequate grease abatement for coffee shop waste. Contact Zach Conde with Boise City Pretreatment for questions. zconde@cityofboise.org. ###-####.