BLD-Foundation | 8/6/2020 | 8/6/2020 | 8/7/2020 | P | PASS |
Tony Young
|
|
|
Jared *screened* Phone #: ###-####
|
BLD-Foundation | 8/5/2020 | 8/6/2020 | 8/6/2020 | A | DEFR |
Tony Young
|
|
|
Jared *screened* Phone #: ###-####// per concrete guy.. after lunch
|
BLD-Footing | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | PART |
Tony Young
|
|
|
Jerrod - */Screened*/ Phone #: ###-####// pending special inspection report,, also has helical piers// needs rebar clearance
|
PubWorks Subgrade Approval | 8/5/2020 | 8/5/2020 | 8/5/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 7/22/2020 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 6/9/2020 | 6/9/2020 | 7/22/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing PW Grading-Hillside | 7/10/2020 | | 7/22/2020 | | FAIL |
Judith Amador
|
|
|
"fail" per eplan
|
Routing - PLAN CHECK | 7/22/2020 | | 7/22/2020 | | PASS |
Debbie Sanine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/22/2020 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 7/22/2020 | | DONE |
|
|
|
met
|
Issue PAID IN FULL permit | | | 7/22/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/22/2020 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 7/21/2020 | | 7/21/2020 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor ###-####.
|
Routing - PLAN CHECK | 7/10/2020 | | 7/10/2020 | | FAIL |
Debbie Sanine
|
|
|
|
1st review completed | | | 6/24/2020 | | FAIL |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 6/9/2020 | | 6/24/2020 | | FAIL |
Debbie Sanine
|
|
|
|
Routing - FIRE | 6/9/2020 | 6/9/2020 | 6/18/2020 | | PASS |
Lee G Meredith
|
|
|
New SFH
Sprinklers are not required. All measurements are within required limits. No review comments provided.
|
Routing - Erosion and Sediment | 6/9/2020 | | 6/18/2020 | | PASS |
Michael Zawacki
|
|
|
Foothills home, site prep inspection required.
|
Routing PW Grading-Hillside | 6/9/2020 | | 6/18/2020 | | FAIL |
Jason C. Taylor
|
|
|
Please have geotechnical engoineer review the latest grading and drainage plan and write a site suitibilty letter approving the grading based off thier geotechnical report. Upload the site suitability letter to the case files for our review. Jason Taylor ###-####
|
Route to Impact Fee Review | 6/9/2020 | 6/12/2020 | 6/10/2020 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 6/9/2020 | | 6/10/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/9/2020 | | 6/9/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - MECHANICAL | 6/9/2020 | | 6/9/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/9/2020 | | 6/9/2020 | | PASS |
Jeff Lowe
|
|
|
per Public Works, no Cat II required.
|
Intake Approval | | | 6/9/2020 | | PASS |
|
|
|
|
Intake Approval | | | 6/8/2020 | | FAIL |
|
|
|
Grading plans have two files, please re upload them as seprate files and please re upload the erosion plan in landscape format.
|
Application received | | | 6/2/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 2 2020 11:56AM
|