FIRE-Conference | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | DONE |
Troy Cobbley
|
|
|
We went over requirements for a final sign off which were having all doors and hardware installed, all walls installed, fire extinguishers mounted and a sprinkler contractor to verify head spacing when fixtures and walls have been placed.
SCREENED // Jon Phone #: ###-####
|
BLD-Framing/Rough-in | 7/24/2020 | 7/24/2020 | 7/24/2020 | P | PASS |
Brandon Shaw
|
|
|
|
Issue PAID IN FULL permit | | | 6/29/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/29/2020 | | DONE |
|
|
|
|
Plan assigned to (J_N) | 6/5/2020 | 6/5/2020 | 6/26/2020 | | DONE |
Jenny Nelson
|
|
|
1st complete 06/17 L2 Mountain West IRA ePlan
|
Routing - PLAN CHECK | 6/26/2020 | | 6/26/2020 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/26/2020 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 6/26/2020 | | DONE |
|
|
|
MET Mark Wagner
Need GC
Need Revised Values
|
Route to Impact Fee Review | 6/12/2020 | 6/15/2020 | 6/15/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 6/5/2020 | | 6/12/2020 | | FAIL |
Jenny Nelson
|
|
|
|
1st review completed | | | 6/12/2020 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PUBLIC WORKS | 6/5/2020 | | 6/11/2020 | | PASS |
Morgan Webb
|
|
|
NO NEW FEES
|
Routing - Addressing | 6/5/2020 | | 6/8/2020 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 6/4/2020 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 6/3/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 3 2020 4:44PM
|