BLD-Footing | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | PASS |
Mike Jordan
|
|
|
Jason - */Screened*/ Phone #: ###-####
|
Inspection Record Card- Bld | | | 7/1/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/30/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/30/2020 | | DONE |
|
|
|
|
Telephone call | | | 6/29/2020 | | DONE |
|
|
|
Email to GC to let them know ESC fees still need to be paid
|
Route to Impact Fee Review | 6/23/2020 | 6/26/2020 | 6/24/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 6/18/2020 | 6/18/2020 | 6/23/2020 | | PASS |
Joe Bruce
|
|
|
Foundation only has been reviewed.
|
Routing - Design Review | 6/22/2020 | | 6/23/2020 | | PASS |
KayCee Babb
|
|
|
Per DRH19-00475. Foundation Only.
|
Routing PW Street Lights | 6/22/2020 | | 6/23/2020 | | PASS |
Tom Marshall
|
|
|
|
1st review completed | | | 6/23/2020 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/23/2020 | | DONE |
Michael Hanson
|
|
|
|
Routing PW Solid Waste | 6/23/2020 | | 6/23/2020 | | PASS |
Evan Carpenter
|
|
|
Approved for commercial cart service.
|
Routing PW Drainage | 6/23/2020 | | 6/23/2020 | | PASS |
Brian Murphy
|
|
|
LESS 1000 SQ FEET
|
Permit Ready to Issue | | | 6/23/2020 | | DONE |
|
|
|
met: rdtalboy@gmail.com
NEED
REVISED VALUE
MET
GC FORM
RP
|
Plan assigned to (M_H) | 6/16/2020 | | 6/23/2020 | | DONE |
Michael Hanson
|
|
|
Foundation Only Personnel Plus
|
Routing - PLAN CHECK | 6/18/2020 | | 6/22/2020 | | PASS |
Michael Hanson
|
|
|
|
Routing - PLANNING | 6/18/2020 | | 6/22/2020 | | PASS |
Ethan Mansfield
|
|
|
|
Routing - PUBLIC WORKS | 6/18/2020 | | 6/22/2020 | | PASS |
Morgan Webb
|
|
|
NO ASSESSMENT DUE, FIXTURE CHARGES ON BUILD OUT PERMIT
|
Routing PW Sewer Design | 6/22/2020 | | 6/22/2020 | | PASS |
DeAnn Brown
|
|
|
|
Routing Off Site - STRUCTURAL | 6/18/2020 | | 6/22/2020 | | PASS |
Michael Hanson
|
|
|
Approved by AHJ under main permit BLD20-01285.
|
Routing - Erosion and Sediment | 6/19/2020 | | 6/19/2020 | | PASS |
Michael Zawacki
|
|
|
Site will be inspected under ESC20-00556
|
Routing - Addressing | 6/18/2020 | | 6/18/2020 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 6/16/2020 | | PASS |
Jenny Nelson
|
|
|
|
Intake Approval | | | 6/15/2020 | | FAIL |
Jenny Nelson
|
|
|
To complete your application please provide the following:
• Provide a completed 502 checklist (Incomplete submittals will not be accepted)
• The checklist is not complete unless all information is filled out, all appropriate boxes are checked and all plan page numbers are listed.
• Provide items that are requested from the checklist that apply to the project. Checklist can be found at https://www.cityofboise.org/departments/planning-and-development-services/building/building-permits/?category=all&search=all
|
Intake Approval | | | 6/15/2020 | | FAIL |
Jenny Nelson
|
|
|
To complete your application please provide the following:
1. Please provide, civil site plans, architectural site plan (if all same information is shown on civil plans this isn't needed), MEP plans if foundation is affected by any of that work.
2. Please upload all associated small documents - #304 form, planning approval letter etc...
|
Application received | | | 6/5/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 5 2020 12:06PM
|
BLD-Foundation | 8/13/2020 | 8/14/2020 | | A | |
Mike Jordan
|
|
|
Screened- Jason- foundation wall Phone #: ###-####
|