BLD-Final | 8/3/2020 | 8/4/2020 | 8/4/2020 | A | PASS |
Mike Jordan
|
|
|
Screened- Ron Phone #: ###-####
|
DOC - Permit Finaled | 8/4/2020 | 8/4/2020 | 8/4/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 7/22/2020 | 7/23/2020 | 7/23/2020 | A | PASS |
Brandon Shaw
|
|
|
SCREENED // Ron Phone #: ###-####
|
BLD-Foundation | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | PASS |
Mike Jordan
|
|
|
Ron *screened* Phone #: ###-####
|
Permit Ready to Issue | | | 6/23/2020 | | DONE |
|
|
|
met
|
Issue PAID IN FULL permit | | | 6/23/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/23/2020 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 6/5/2020 | 6/5/2020 | 6/22/2020 | | PASS |
Josh Bogle
|
|
|
06/10 carport, ePlan
|
Routing - PLAN CHECK | 6/5/2020 | | 6/22/2020 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 6/22/2020 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/22/2020 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Application received | | | 6/5/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 5 2020 1:36PM
|
Plans ACCEPTED BY PLAN TECH | | | 6/5/2020 | | DONE |
|
|
|
|
Intake Approval | | | 6/5/2020 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/5/2020 | | DONE |
|
|
|
|
Routing - PLANNING | 6/5/2020 | | 6/5/2020 | | FAIL |
Sue Cummings
|
|
|
Called customer requested CVT to be drawn on the site plan
|
Routing - PLANNING | 6/5/2020 | | 6/5/2020 | | PASS |
Sue Cummings
|
|
|
Customer provied new site plan showing CVT O.K. now
|