Permanent Occupancy | | | 7/22/2020 | | DONE |
|
|
|
|
BLD-Final | 7/20/2020 | 7/21/2020 | 7/21/2020 | P | PASS |
Mike Jordan
|
|
|
call 15 mins for access- Dan *screened* Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 7/20/2020 | 7/21/2020 | 7/21/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
call 15 mins for access- Dan *screened* #: ###-####
|
BLD-Framing/Rough-in | 7/16/2020 | 7/16/2020 | 7/16/2020 | P | PASS |
Mike Jordan
|
|
|
Dan - */Screened*/ *No one at jobsite* Phone #: ###-####. Interior wood framed walls for new changing rooms ok.
|
Telephone call | | | 7/8/2020 | | DONE |
|
|
|
emailed the GC and applicant requesting a form 302
|
Issue PAID IN FULL permit | | | 7/8/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/8/2020 | | DONE |
|
|
|
|
Plan assigned to (JG) | 6/19/2020 | 6/19/2020 | 7/7/2020 | | PASS |
Javier Guzman
|
|
|
07/06 2nd rev L1 Fashion 15 ePlan
|
Routing - PLAN CHECK | 7/1/2020 | | 7/7/2020 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/7/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/7/2020 | | DONE |
|
|
|
met: debbie@eldaps.com
Need
GC Form
|
Route to Impact Fee Review | 6/23/2020 | 6/26/2020 | 6/24/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 6/19/2020 | | 6/23/2020 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 6/23/2020 | | FAIL |
Javier Guzman
|
|
|
|
Intake Approval | | | 6/17/2020 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 6/15/2020 | | FAIL |
Julie Romig
|
|
|
To complete your application, please provide the following:
1. Upload completed 518 checklist, found here:
https://www.cityofboise.org/media/8479/518-minor-ti-submittal-checklist_oct-2019-fillable.pdf
2. Upload drawing sheet as a minimum 36"x24" PDF sheet size. Name file "A1_Floor Plan".
3. Include the following code analysis on drawing sheet:
- VB Construction Type
- M Occupancy
- 48 Occupants
- Fully Fire Sprinklered
4. Identify on plan all new walls.
5. Include wall type construction (ex. 2x4 wood stud wall with 5/8" Type X gypsum board each side).
|
Application received | | | 6/14/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 14 2020 11:29AM
|