BLD-Energy code compliance | 8/12/2020 | 8/12/2020 | 8/12/2020 | P | PART |
Tony Young
|
|
|
screened // Joe Phone #: ###-####,, north exterior walls on 3rd and 4th ok,, finished puddy pads on interior walls.. ok to sound insulate pending trades
|
BLD-Framing/Rough-in | 8/10/2020 | 8/10/2020 | 8/10/2020 | P | PART |
Dave Hannah
|
|
|
screened // Joe Phone #: ###-#### ok to insulate the ext walls on 3rd and fouth floor steel stud walls
|
Issue PAID IN FULL permit | | | 8/3/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/3/2020 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/23/2020 | 6/26/2020 | 6/24/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 6/24/2020 | | DONE |
|
|
|
ISSUE WITH BLD19-04433
all met: ACHD
met: GC FORM
met: REVISED VALUE
|
Plan assigned to (JAR) | 6/15/2020 | 6/23/2020 | 6/23/2020 | | DONE |
Julie Romig
|
|
|
|
Routing - FIRE | 6/23/2020 | 6/23/2020 | 6/23/2020 | | PASS |
Erika Akin
|
|
|
Reviewed under BLD19-04433. Attached comments to case.
|
Routing PW Drainage | 6/23/2020 | | 6/23/2020 | | PASS |
Jason C. Taylor
|
|
|
Reviewed under BLD19-04433. Approved under GRD19-00067 JCT.
|
Routing PW Street Lights | 6/23/2020 | | 6/23/2020 | | PASS |
Tom Marshall
|
|
|
Reviewed under BLD19-04433
|
Routing PW Sewer Design | 6/23/2020 | | 6/23/2020 | | PASS |
DeAnn Brown
|
|
|
Reviewed under BLD19-04433
|
Routing PW Flood Plain | 6/23/2020 | | 6/23/2020 | | PASS |
Jason C. Taylor
|
|
|
Reviewed under BLD19-04433. A portion of the subject property is within the regulatory floodplain. This project must comply with the Boise Floodplain Ordinance (B.C.C. 11-08). If you have any questions, please call Jason Taylor at ###-####.
Upload Elevation Certificates. Elevation Certificate elevations need prior to occupancy. Jason Taylor ###-####.
|
Routing PW Solid Waste | 6/23/2020 | | 6/23/2020 | | PASS |
Evan Carpenter
|
|
|
Reviewed under BLD19-04433
|
Routing PW Environmental | 6/23/2020 | | 6/23/2020 | | PASS |
Zach Conde
|
|
|
Reviewed under BLD19-04433. PER ZACH: Passed on ePlan with this comment: "Approved for retail shell only. Any restaurant/food service tenants will need suitable and adequate grease abatement. Tenants will need to get approval from Pretreatment." Please pass on Tidemark.
|
1st review completed | | | 6/23/2020 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/23/2020 | | DONE |
|
|
|
|
Routing - Design Review | 6/23/2020 | | 6/23/2020 | | PASS |
Josh Wilson
|
|
|
Reviewed under BLD19-04433
|
Routing - PLAN CHECK | 6/23/2020 | | 6/23/2020 | | PASS |
Julie Romig
|
|
|
Reviewed under BLD19-04433
|
Routing - MECHANICAL | 6/23/2020 | | 6/23/2020 | | PASS |
Troy James
|
|
|
Reviewed under BLD19-04433
|
Routing - PLUMBING | 6/23/2020 | | 6/23/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC. Reviewed under BLD19-04433
|
Routing - PLANNING | 6/23/2020 | | 6/23/2020 | | PASS |
Cody Riddle
|
|
|
Reviewed under BLD19-04433. Reviewed for DRH, and compliance with DA by JWilson.
|
Routing - Addressing | 6/23/2020 | | 6/23/2020 | | PASS |
Doug Chausow
|
|
|
Reviewed under BLD19-04433
|
Routing - PUBLIC WORKS | 6/23/2020 | | 6/23/2020 | | PASS |
Morgan Webb
|
|
|
Reviewed under BLD19-04433
|
Application received | | | 6/15/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 15 2020 7:51AM
|
Intake Approval | | | 6/15/2020 | | PASS |
Julie Romig
|
|
|
|