BLD-Footing | 8/10/2020 | 8/10/2020 | 8/10/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 8/5/2020 | 8/6/2020 | 8/6/2020 | P | CANC |
Brandon Shaw
|
|
|
Chris *screened* Phone #: ###-####
|
PubWorks Subgrade Approval | 8/6/2020 | 8/6/2020 | 8/6/2020 | | DONE |
Jason C. Taylor
|
|
|
* FOOTINGS ONLY NO COLUMNS***A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 7/27/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/27/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/27/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 7/24/2020 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 7/1/2020 | 7/1/2020 | 7/24/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLANNING | 7/24/2020 | | 7/24/2020 | | PASS |
David Moser
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2020 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 7/24/2020 | | DONE |
|
|
|
ALL MET-
NEED-
GC FORM (sent email to owner doneil@grboise.com)
|
1st review completed | | | 7/16/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 7/1/2020 | | 7/16/2020 | | PASS |
Debbie Sanine
|
|
|
|
Routing PW Grading-Hillside | 7/1/2020 | | 7/14/2020 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor ###-####.
|
Routing - PLANNING | 7/1/2020 | | 7/8/2020 | | FAIL |
David Moser
|
|
|
The house is built over a 18 foot storm drainage easement across the back of the parcel which is recorded on the final plat
|
Routing - MECHANICAL | 7/1/2020 | | 7/6/2020 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 7/1/2020 | | 7/6/2020 | | PASS |
Andy J. Long
|
|
|
ESC site plan and narrative submitted. ESC site preparation inspection is required before excavation and after BMP installation
|
Route to Impact Fee Review | 7/1/2020 | 7/4/2020 | 7/2/2020 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 7/1/2020 | 7/1/2020 | 7/1/2020 | | PASS |
Lee G Meredith
|
|
|
New SFH
Sprinklers are not required. All measurements are within limits. No review comments.
|
Intake Approval | | | 7/1/2020 | | PASS |
|
|
|
|
Routing - Addressing | 7/1/2020 | | 7/1/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/1/2020 | | 7/1/2020 | | PASS |
Candy A. Nichols
|
|
|
NO OCCUPANCY UNTUIL SEWER LIFT STATION COMPLETED
|
Intake Approval | | | 6/23/2020 | | FAIL |
|
|
|
1. Need Geotech Report
2. Manual J
3. Site Specific Fire Flow at Hydrants Letter from local water provider.
4. Erosion Narrative
5. Please fill out a 404 application (not 402) and checklist upload it into the documents folder.
|
Telephone call | | | 6/19/2020 | | DONE |
|
|
|
Applicant requested all documents and drawings be deleted and returned to him for upload task.
|
Telephone call | | | 6/19/2020 | | DONE |
|
|
|
Called Dalton to let him know he needs a 404 application and checklist. Had already gone to hillside, so he will email me those applications and I will upload.
|
Application received | | | 6/15/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 15 2020 12:23PM
|