BLD-Wall cover | 8/12/2020 | 8/13/2020 | 8/13/2020 | P | PASS |
Mike Jordan
|
|
|
Call Tim 30 minutes prior for access Phone #: ###-#### Inspection requested via web by Timothy Gammill. Shear blocking installed. insulation not completed. Will need to call in energy code inspection when insulation is installed.
|
BLD-Framing/Rough-in | 8/11/2020 | 8/12/2020 | 8/12/2020 | A | PART |
Mike Jordan
|
|
|
Call Tim 30 minutes prior for access Phone #: ###-#### Inspection requested via web by Timothy Gammill. complete airseal, and install shear blocking.
|
BLD-Foundation | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | PASS |
Mike Jordan
|
|
|
virtual inspection // Greg Phone #: ###-####
|
BLD-Foundation | 7/13/2020 | 7/13/2020 | 7/13/2020 | P | CANC |
Mike Jordan
|
|
|
Grege *screened* Phone #: ###-####
|
BLD-Footing | 7/8/2020 | 7/9/2020 | 7/9/2020 | A | PART |
Mike Jordan
|
|
|
SCREENED late morning Jon Phone #: ###-####. No approved plans on site. Ok to place footing at contractors own risk. Will neeed to schedule a foundation inspection for concrete stemwall, have approved plans and paperwork on site to verify rear setback.
|
Inspection Record Card- Bld | | | 7/8/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/7/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/6/2020 | | DONE |
|
|
|
met
|
Plan assigned to (JAB) Josh | 6/19/2020 | 6/19/2020 | 7/2/2020 | | PASS |
Josh Bogle
|
|
|
06/25 addition, ePlan - 1st done
|
Plan Reviewer's activity | | | 7/2/2020 | | DONE |
Josh Bogle
|
|
|
returned resubmittal per applicant request
|
Routing - PLAN CHECK | 7/2/2020 | | 7/2/2020 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2020 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy yes
|
Routing - PLAN CHECK | 6/19/2020 | | 7/1/2020 | | FAIL |
Josh Bogle
|
|
|
plan lacked required details
|
1st review completed | | | 7/1/2020 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLANNING | 6/19/2020 | | 6/19/2020 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/19/2020 | | DONE |
|
|
|
|
Intake Approval | | | 6/19/2020 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/19/2020 | | DONE |
|
|
|
|
Intake Approval | | | 6/18/2020 | | FAIL |
|
|
|
Plans are still showing as being uploaded in the wrong orientation
|
Application received | | | 6/17/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 17 2020 1:48PM
|
Intake Approval | | | 6/17/2020 | | FAIL |
|
|
|
Plans must be uploaded in the correct orientation. (landscape vs horizontal)
|