BLD-Wall cover | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | PASS |
Tell Riley
|
|
|
screened // Justin Phone #: ###-####//per the contractor--plumbing will be completed when cabinets are installed//other trades have passed//will need code compliant smoke and smoke/co combos installed for final//other areas ok//
|
BLD-Wall cover | 7/30/2020 | 7/31/2020 | 7/31/2020 | A | PART |
Tell Riley
|
|
|
Justin *screened* Phone #: ###-####//need plans onsite//wire in smoke detectors in bedrooms//ok to insulate walls//will check plans at energy//
|
BLD-Wall cover | 7/28/2020 | 7/28/2020 | 7/28/2020 | P | CANC |
Tell Riley
|
|
|
Justin *screened* Phone #: ###-####//electrical failed will need to reschedule//
|
BLD-Wall cover | 7/27/2020 | 7/27/2020 | 7/27/2020 | P | NR |
Tell Riley
|
|
|
call for access - screened // Justin Phone #: ###-####//need plumbing permit, need electrical rough in inspection//
|
Permit Ready to Issue | | | 7/1/2020 | | DONE |
|
|
|
met
|
Issue PAID IN FULL permit | | | 7/1/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/1/2020 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 6/30/2020 | 6/30/2020 | 6/30/2020 | | PASS |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 6/30/2020 | | 6/30/2020 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 6/30/2020 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/2020 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Plans ACCEPTED BY PLAN TECH | | | 6/30/2020 | | DONE |
|
|
|
|
Intake Approval | | | 6/30/2020 | | PASS |
|
|
|
Per Josh we are pushign this thorugh so he can do an appointment with the applicant
|
Application received | | | 6/29/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 29 2020 12:51PM
|
Intake Approval | | | 6/29/2020 | | FAIL |
|
|
|
Please show ALL walls (and call out rooms) for the before and after floor plan
|