CHANGE STATUS TO (D) | | | 3/27/1996 | | DONE |
|
|
|
|
INSP - Final | 10/12/1995 | 10/12/1995 | 10/12/1995 | P | CANC |
|
|
|
10/12/95 333 -
|
INSP - Final | 10/11/1995 | 10/12/1995 | 10/12/1995 | P | PASS |
|
|
|
10/12/95 333 - LATE PM. FNL -OK FINAL
|
INSP - Letter of compliance | 10/12/1995 | 10/12/1995 | 10/12/1995 | | PASS |
|
|
|
/ / 333 - letter #10171 given to contractor
|
INSP - Framing/ Rough-in | 9/5/1995 | 9/6/1995 | 9/5/1995 | A | |
Jim Sly
|
|
|
|
INSP - Framing/ Rough-in | 9/5/1995 | 9/5/1995 | 9/5/1995 | P | |
Jim Sly
|
|
|
|
INSP - Conference | 8/31/1995 | 8/31/1995 | 8/31/1995 | P | FAIL |
Jim Sly
|
|
|
CONF.W/CONTRACTOR. REPOSTED C/N. C/N STILL IN EFFECT.
|
INSP - Framing/ Rough-in | 8/31/1995 | 8/31/1995 | 8/31/1995 | P | FAIL |
Jim Sly
|
|
|
ISSUED C/N ON FRAME. OK TO INSULATE. WILL CHECK C/N AT ENERGY INSPECTION.
|
INSP - Framing/ Rough-in | 8/30/1995 | 8/30/1995 | 8/30/1995 | P | FAIL |
Jim Sly
|
|
|
NOT READY. NEEDS PLUMBING & HTG.
|
INSP - Footings | 7/19/1995 | 7/20/1995 | 8/7/1995 | A | CANC |
Jim Sly
|
|
|
canc 305
|
INSP - Footings | 7/19/1995 | 7/20/1995 | 8/7/1995 | A | CANC |
Jim Sly
|
|
|
canc 305
|
(F) Issue permit | | | 7/31/1995 | | I |
|
|
|
|
Inspection Record Card- Bld | | | 7/26/1995 | | |
|
|
|
|
Print Pending Permit.......... | | | 7/26/1995 | | |
|
|
|
|
Permit taken to Permit Desk | | | 7/26/1995 | | |
|
|
|
|
Plan resubmittals requested | | | 7/25/1995 | | |
|
|
|
|
Plan resubmittals received | | | 7/25/1995 | | |
|
|
|
|
Telephone call | | | 7/25/1995 | | |
|
|
|
|
INSP - Foundation | 7/21/1995 | 7/21/1995 | 7/21/1995 | P | PASS |
Jim Sly
|
|
|
|
Telephone call | | | 7/21/1995 | | |
|
|
|
|
INSP - Footings | 7/20/1995 | 7/20/1995 | 7/20/1995 | P | PASS |
Jim Sly
|
|
|
|
Telephone call | | | 7/20/1995 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 7/18/1995 | | P |
|
|
|
|
Dwelling recd. by Plan Check | | | 7/11/1995 | | |
|
|
|
|
Application received | | | 7/5/1995 | | |
|
|
|
|