(F) Reprint permit | | | 2/23/1996 | | |
|
|
|
|
INSP - Final | 2/1/1996 | 2/1/1996 | 2/1/1996 | | PASS |
|
|
|
|
INSP - Final | 1/30/1996 | 1/30/1996 | 1/30/1996 | | PASS |
Bob Archibald
|
|
|
LC ISSUED BY MOLLY.
|
INSP - Framing/Rough-in | 11/7/1995 | 11/7/1995 | 11/7/1995 | | FAIL |
Bob Archibald
|
|
|
NOT READY.
|
INSP - Framing/Rough-in | 10/31/1995 | 10/31/1995 | 10/31/1995 | | FAIL |
Bob Archibald
|
|
|
CN issued.
|
INSP - Conference | 8/8/1995 | 8/8/1995 | 8/8/1995 | A | PASS |
Bob Archibald
|
|
|
conference on ventilation requirements. requested resubmittals to mechanical division.
|
(F) Issue permit | | | 8/8/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/4/1995 | | |
|
|
|
|
Waiting for Cert. of Value | 8/2/1995 | | 8/2/1995 | | |
|
|
|
|
Telephone call | 8/2/1995 | | 8/2/1995 | | |
|
|
|
Called Neil Hosford. Left a message that I (Carl) need to talk to him about problems with his resubmittal.
|
Plan resubmittals received | 8/2/1995 | | 7/26/1995 | | |
|
|
|
|
Routing - FIRE | 7/17/1995 | | 7/24/1995 | | OK |
|
|
|
|
Plan resubmittals requested | 8/2/1995 | | 7/17/1995 | | |
|
|
|
|
Plan routing begun/TENANTS | 8/2/1995 | | 7/17/1995 | | |
|
|
|
Routing resumed after UBC plan check
|
Routing - BUILDING | 6/14/1995 | | 7/17/1995 | | |
|
|
|
Drawings waiting for UBC plan review. UBC plan review started 7-14-95. Copy of plan review sent to the Architect 7-17-95. Four items required a response.
|
Routing - ELECTRICAL | 6/13/1995 | | 6/14/1995 | | OK |
|
|
|
|
Routing - PUBLIC WORKS | 6/9/1995 | | 6/13/1995 | | OK |
|
|
|
|
Plan routing begun/TENANTS | 8/2/1995 | | 6/9/1995 | | |
|
|
|
Routing prior to UBC plan review
|
Application received | | | 6/8/1995 | | |
|
|
|
|
INSP - Letter of compliance | | | 2/1/1991 | | PASS |
|
|
|
ISSUED #10827 C OF C BY MJW THIS DATE.
|
Permit taken to Permit Desk | 8/2/1995 | | | | |
|
|
|
|