Case Summary (BLD) | | | 8/17/2015 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 4/23/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6370 issued 4-23-96 to Lindy's Restaurant.
|
INSP - Final | 4/8/1996 | 4/8/1996 | 4/8/1996 | P | PART |
Carl Dependahl
|
|
|
04/08/96 340 - FORMERLY 6290 MEEKER DR NEED VERIFY SIGNATURES ON OCC. CARD, STRUCT OK FOR C/O NEW PERMIT NO.?
|
INSP - Temporary occupancy | | | 4/4/1996 | | PASS |
|
|
|
Temp. Occ. Cert. #3186 issued 4-4-96 to Lindy's Restaurant and Lounge.
|
INSP - Final | 4/3/1996 | 4/3/1996 | 4/3/1996 | P | FAIL |
Carl Dependahl
|
|
|
04/03/96 340 - LATE PM. C/N, OK FOR T/O, CARD TO CONTRACTOR
|
INSP - Carpentry | 3/22/1996 | 3/22/1996 | 3/22/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - GRID OK
|
INSP - Ceiling grid | 3/12/1996 | 3/12/1996 | 3/12/1996 | P | FAIL |
Carl Dependahl
|
|
|
03/12/96 340 -
|
INSP - Conference | 2/13/1996 | 2/13/1996 | 2/13/1996 | | PART |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Framing/Rough-in | 2/12/1996 | 2/12/1996 | 2/12/1996 | P | PART |
Carl Dependahl
|
|
|
02/12/96 340 -
|
INSP - Energy code compliance | 1/31/1996 | 2/1/1996 | 2/1/1996 | A | PART |
Carl Dependahl
|
|
|
02/01/96 340 -
|
INSP - Framing/Rough-in | 2/1/1996 | 2/1/1996 | 2/1/1996 | | PART |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Framing/Rough-in | 1/30/1996 | 1/30/1996 | 1/30/1996 | P | FAIL |
Carl Dependahl
|
|
|
01/30/96 340 - LATE PM.
|
INSP - Framing/Rough-in | 1/23/1996 | 1/23/1996 | 1/23/1996 | P | NR |
Carl Dependahl
|
|
|
01/23/96 340 -
|
INSP - Framing/Rough-in | 1/17/1996 | 1/17/1996 | 1/17/1996 | P | NR |
Carl Dependahl
|
|
|
01/17/96 340 -
|
INSP - Carpentry | 1/4/1996 | 1/4/1996 | 1/4/1996 | P | PART |
Carl Dependahl
|
|
|
01/04/96 340 -
|
INSP - Conference | 12/15/1995 | 12/18/1995 | 12/18/1995 | A | PASS |
Carl Dependahl
|
|
|
12/18/95 340 -
|
INSP - Conference | 12/4/1995 | 12/5/1995 | 12/5/1995 | A | PASS |
Carl Dependahl
|
|
|
12/04/95 340 -
|
INSP - Carpentry | 11/16/1995 | 11/17/1995 | 11/17/1995 | A | PART |
Carl Dependahl
|
|
|
11/17/95 340 -
|
INSP - Foundation | 10/23/1995 | 10/23/1995 | 11/7/1995 | P | PART |
Carl Dependahl
|
|
|
10/23/95 340 -
|
(F) Reprint permit | | | 10/20/1995 | | I |
|
|
|
|
(F) Issue permit | | | 10/6/1995 | | |
|
|
|
|
Routing Off Site - A.C.H.D | 10/6/1995 | | 10/6/1995 | | PAID |
|
|
|
A.C.H.D. IMPACT FEES PAID 10/06/95 - CERT. #95-001428
|
Plan Reviewer's activity | | | 10/6/1995 | | OK |
|
|
|
REVIEWED LAST RESUBMITTED PLAN SHEET DATED 10/06/95 - APPROVED FOR ISSUE AS OF 10/06/95.
|
Permit taken to Permit Desk | | | 10/6/1995 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 10/6/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/6/1995 | | |
|
|
|
|
(F) Reprint permit | | | 10/6/1995 | | |
|
|
|
|
Plan Reviewer's activity | | | 10/5/1995 | | PEND |
|
|
|
REVIEWED RESUBMITTED PLAN SHEETS RECEIVED 09/29/95 - ARCHITECT (DENNIS SUNBERG) WAS CONTACTED BY TELEPHONE FOR ADDITIONAL REVISIONS.
|
Routing - MECHANICAL | 9/19/1995 | | 9/27/1995 | | PASS |
|
|
|
|
(F) Reprint permit | | | 9/26/1995 | | |
|
|
|
|
(F) Issue permit | | | 9/26/1995 | | |
|
|
|
|
Plan Reviewer's activity | | | 9/18/1995 | | PEND |
|
|
|
PRELIMINARY PLAN REVIEW COMPLETED 09/18/95-CORRCTION LIST SENT TO ARCHITECT.
|
Routing - PUBLIC WORKS | 9/5/1995 | | 9/11/1995 | | PASS |
|
|
|
|
Routing - FIRE | 8/23/1995 | | 8/24/1995 | | PASS |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 8/23/1995 | | |
|
|
|
|
Routing - PUBLIC WORKS | 8/22/1995 | | 8/23/1995 | | FAIL |
|
|
|
|
Routing - MECHANICAL | 8/19/1995 | | 8/22/1995 | | FAIL |
|
|
|
|
Routing - PLUMBING | 8/17/1995 | | 8/21/1995 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 8/9/1995 | | 8/17/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/9/1995 | | 8/9/1995 | | FAIL |
|
|
|
|
Routing - PLANNING | 8/2/1995 | | 8/8/1995 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 7/21/1995 | | 8/2/1995 | | PASS |
|
|
|
Contacted Harvey Geis' office 7/21/95 at 10:30 a.m. ###-####. Advised plans ready to go to C.D.H.
|
Routing Off Site - A.C.H.D | 8/1/1995 | | 8/1/1995 | | FAIL |
|
|
|
8-22-95 Fees not paid as of this date.
|
Plan routing begun/NEW & ADDTN | | | 7/21/1995 | | |
|
|
|
Route to CDH, Public Works, Planning, Plumbing, Mechanical and Electrical then back to Plan Check. After Plan Check route to ACHD and Fire Dept.
|
Application received | | | 7/12/1995 | | |
|
|
|
|
Permanent Occupancy | | 4/23/1995 | 4/23/1995 | | DONE |
|
|
|
|
Routing - BUILDING | 8/23/1995 | | | | PEND |
|
|
|
|
Routing - BUILDING | 8/25/1995 | | | | PEND |
|
|
|
|
Routing - BUILDING | 9/27/1995 | | | | PEND |
|
|
|
|