INSP - Permanent occupancy | | | 2/13/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6298 issued 2-13-96 to Storey Chiropractic Clinic.
|
INSP - Final | 2/12/1996 | 2/12/1996 | 2/12/1996 | P | PART |
Wes Worcester
|
|
|
FINAL REINSPECT
|
Permanent Occupancy | | 2/12/1996 | 2/12/1996 | | DONE |
|
|
|
|
INSP - Temporary occupancy | | | 12/20/1995 | | PASS |
|
|
|
Temp. Occ. Cert. #3111 issued 12-20-95 to Storey Chiropractic Clinic.
|
INSP - Final | 12/13/1995 | 12/13/1995 | 12/13/1995 | P | FAIL |
Jim Sly
|
|
|
Correction notice: sign off by P/Z and handrails not in compliance.
|
INSP - Final | 12/8/1995 | 12/8/1995 | 12/8/1995 | P | NR |
Carl Dependahl
|
|
|
12/08/95 340 - THEY SAID TO SEND THIS TO YOU AS YOU HAD BEEN THERE ORIGINALLY.... THAT MUST HAVE BEEN WHAT WES WAS TALKING ABOUT WHEN HE CALLED YOU.
|
INSP - Final | 12/8/1995 | 12/8/1995 | 12/8/1995 | | NR |
Wes Worcester
|
|
|
/ / 342 -
|
Inspection Record Card- Bld | | | 12/8/1995 | | I |
|
|
|
|
INSP - Framing/Rough-in | 11/2/1995 | 11/2/1995 | 11/7/1995 | P | PART |
Carl Dependahl
|
|
|
11/02/95 340 -
|
INSP - Framing/Rough-in | 11/1/1995 | 11/1/1995 | 11/7/1995 | P | PART |
Carl Dependahl
|
|
|
11/01/95 340 - REINSPECTION
|
INSP - Framing/Rough-in | 10/16/1995 | 10/16/1995 | 11/7/1995 | P | FAIL |
Carl Dependahl
|
|
|
10/16/95 340 -
|
INSP - Framing/Rough-in | 10/31/1995 | 10/31/1995 | 11/6/1995 | P | NR |
Wes Worcester
|
|
|
10/31/95 342 - reinspection
|
INSP - Conference | 10/9/1995 | 10/9/1995 | 10/9/1995 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
(F) Issue permit | | | 8/11/1995 | | I |
|
|
|
|
Permit taken to Permit Desk | 8/7/1995 | | 8/11/1995 | | PASS |
|
|
|
|
(F) Issue NO FEE RECEIVED prmt | | | 8/11/1995 | | |
|
|
|
|
Received Certificate of Value | | | 8/11/1995 | | PASS |
|
|
|
Received approximately 11:15 AM. DAR
|
Inspection Record Card- Bld | | | 8/11/1995 | | |
|
|
|
|
Routing - ELECTRICAL | 8/9/1995 | | 8/10/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/9/1995 | | 8/9/1995 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 8/7/1995 | | 8/8/1995 | | FAIL |
|
|
|
|
Routing - MECHANICAL | 7/31/1995 | | 8/7/1995 | | OK |
|
|
|
|
Waiting for Cert. of Value | | | 8/7/1995 | | HOLD |
|
|
|
A new cert. of value is required. It must reflect the cost minus the footing and foundation permit issued eariler.
|
Routing - BUILDING | 8/7/1995 | | 8/7/1995 | | OK |
|
|
|
UBC plan check completed after resubmittal was reviewed.
|
Plan Reviewer's Copy of Permit | | | 8/7/1995 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | 8/7/1995 | | 8/7/1995 | | |
|
|
|
Plan routing resumed after UBC plan check review of resubmittal.
|
Plan resubmittals received | 8/7/1995 | | 8/2/1995 | | OK |
|
|
|
Resubmittals received on Aug. 2, 1995. They were reviewed Aug. 7, 1995 and approved.
|
Routing - PLUMBING | 7/31/1995 | | 8/1/1995 | | OK |
|
|
|
|
Routing - FIRE | 7/28/1995 | | 7/29/1995 | | OK |
|
|
|
|
Routing - PLANNING | 7/20/1995 | | 7/21/1995 | | OK |
|
|
|
|
Plan resubmittals requested | | | 7/20/1995 | | HOLD |
|
|
|
Plan Check sent to the Architect. Eight items require a response.
|
Routing - BUILDING | 7/18/1995 | | 7/20/1995 | | |
|
|
|
UBC plan review completed. Waiting for resubmittal from Architect.
|
Plan routing begun/NEW & ADDTN | 8/7/1995 | | 7/20/1995 | | |
|
|
|
Plan routing resumed July 20, 1995 after UBC plan check.
|
Routing - PLUMBING | 7/13/1995 | | 7/17/1995 | | |
|
|
|
Pulled out of Plumbing 7-17-95 to start UBC Plan Review. Needs approval by Plumbing.
|
Routing - ELECTRICAL | 7/11/1995 | | 7/13/1995 | | HOLD |
|
|
|
Rejected first time.
|
Routing - PUBLIC WORKS | 6/29/1995 | | 7/11/1995 | | HOLD |
|
|
|
Rejected the first time.
|
Routing Off Site - A.C.H.D | 6/7/1995 | | 6/28/1995 | | OK |
|
|
|
S. C. Rich Approved drawings per CU-27-94/modified on 06-09-95. Angie Cecil required no impact fees 06-27-95.
|
Plan routing begun/NEW & ADDTN | | | 6/7/1995 | | |
|
|
|
|
Application received | | | 6/5/1995 | | |
|
|
|
|