INSP - Foundation | 11/13/1995 | 11/14/1995 | 11/14/1996 | A | PASS |
Jim Sly
|
|
|
|
INSP - Letter of compliance | | | 10/3/1996 | | PASS |
|
|
|
ISSUED 11545 C OF C BY MJW 7/26/96. ISSUED IN ERROR BUT IS FINALED NOW AS PER WES W.
|
INSP - Final | 10/2/1996 | 10/2/1996 | 10/2/1996 | | PASS |
|
|
|
|
INSP - Final | 10/2/1996 | 10/2/1996 | 10/2/1996 | | PASS |
|
|
|
|
INSP - Letter of compliance | | | 10/2/1996 | | PASS |
|
|
|
ISSUED #11545 C OF C BY MJW 7/26/96. (THIS WAS ISSUED IN ERROR BUT WAS NEVER RECALLED SO IT STANDS FOR FINAL LETTER.MJW
|
INSP - Final | 7/25/1996 | 7/26/1996 | 7/26/1996 | A | CANC |
Alan Hauser
|
|
|
07/26/96 350 - TO BE DONE BY #342
|
INSP - Final | 7/22/1996 | 7/23/1996 | 7/23/1996 | P | NR |
Wes Worcester
|
|
|
PLEASE CALL ###-#### HE WILL MEET YOU still needs signatures of fire, achd, public wks, elect.....
|
Inspection Record Card- Bld | | | 7/22/1996 | | |
|
|
|
|
ISSUE OCCUPANCY FORM | | | 7/22/1996 | | |
|
|
|
|
INSP - Framing/Rough-in | 3/13/1996 | 3/13/1996 | 3/13/1996 | P | PASS |
Wes Worcester
|
|
|
firewall? finishing firecaulking and trusses were as per Architect
|
INSP - Framing/Rough-in | 3/6/1996 | 3/7/1996 | 3/7/1996 | A | PART |
Wes Worcester
|
|
|
10:30 A.M. APPOINTMENT ok to insulate, need truss eng of truss mod at West hip by Valley truss
|
INSP - Conference | 2/23/1996 | 2/23/1996 | 2/23/1996 | P | PART |
Wes Worcester
|
|
|
discussed correct firewall assembly as per plan
|
INSP - Carpentry | 2/23/1996 | 2/23/1996 | 2/23/1996 | P | FAIL |
Wes Worcester
|
|
|
incorrect firewall assembly
|
INSP - Foundation | 11/17/1995 | 11/17/1995 | 11/17/1995 | | PASS |
Jim Sly
|
|
|
|
INSP - Foundation | 11/9/1995 | 11/9/1995 | 11/9/1995 | | PASS |
Jim Sly
|
|
|
|
INSP - Footings | 11/8/1995 | 11/9/1995 | 11/9/1995 | A | PASS |
Jim Sly
|
|
|
|
Issue PAID IN FULL permit | | | 11/3/1995 | | I |
|
|
|
|
(F) Reprint permit | | | 11/3/1995 | | |
|
|
|
|
Plans taken to the Permit Desk | | | 10/31/1995 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 10/31/1995 | | P |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/31/1995 | | PASS |
|
|
|
|
Routing - FIRE | 10/16/1995 | | 10/27/1995 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 10/16/1995 | | PASS |
|
|
|
RECIEVED REVISED DRAWINGS DATED 10/12/95
|
Received Certificate of Value | | | 10/13/1995 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 9/29/1995 | | 10/4/1995 | | PEND |
|
|
|
|
Routing Off Site - A.C.H.D | 9/28/1995 | | 9/28/1995 | | PASS |
|
|
|
fees paid, crt. #95-01375
|
Routing Off Site - A.C.H.D | 8/9/1995 | | 9/1/1995 | | FAIL |
|
|
|
Fees not paid as of 9-1-95.
|
Plan Reviewer's activity | | | 9/1/1995 | | |
|
|
|
|
Routing - ELECTRICAL | 8/8/1995 | | 8/8/1995 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 7/21/1995 | | 8/7/1995 | | PASS |
|
|
|
|
Routing - PLUMBING | 7/28/1995 | | 8/7/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 7/28/1995 | | 8/7/1995 | | PASS |
|
|
|
|
Routing - PLANNING | 7/19/1995 | | 7/21/1995 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 7/19/1995 | | |
|
|
|
Route to Public Works, Planning, Plumbing, Mechanical and Electrical then back to Plan Check. After Plan Check route to A.C.H.D. and Fire Department.
|
Application received | | | 7/14/1995 | | |
|
|
|
|
Routing - BUILDING | 9/1/1995 | | | | PEND |
|
|
|
|
Routing - BUILDING | 10/5/1995 | | | | PEND |
|
|
|
To plan check, waiting for roof redesign - to close to the property line.
|
Routing - BUILDING | 10/30/1995 | | | | PEND |
|
|
|
|