INSP - Final | 4/19/1999 | 4/19/1999 | 4/19/1999 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - FINALLY!!!!
|
Permanent occupancy | | | 4/19/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7746 issued 4-19-99 to Quizno's Classic Subs.
|
Permanent Occupancy | | 4/18/1999 | 4/18/1999 | | DONE |
|
|
|
|
INSP-Final Inspection | 4/16/1999 | 4/16/1999 | 4/16/1999 | P | PASS |
Rick Jackson
|
|
|
occ approved
|
INSP - Final | 8/10/1998 | 8/10/1998 | 8/10/1998 | P | FAIL |
Carl Dependahl
|
|
|
conf w/ Scott Steed; need htg, fire, & struct finals for c/o...keep c/n
|
INSP - Final | 8/7/1998 | 8/7/1998 | 8/7/1998 | A | NR |
Carl Dependahl
|
|
|
call back from owner re c/n...will get w/ cont & obtain final asap
|
INSP - Final | 8/5/1998 | 8/5/1998 | 8/5/1998 | A | FAIL |
Carl Dependahl
|
|
|
issued c/n to obtain c/o...not requested insp, cleaning up old c/o cards.
|
INSP - Temporary occupancy | 9/25/1995 | 9/25/1995 | 9/25/1995 | | PASS |
|
|
|
Temp. Occ. Cert. #3049 issued 9-25-95 to Quizno's in the Albertson's Marketplace, Bldg. C.
|
INSP - Carpentry | 8/30/1995 | 8/30/1995 | 8/30/1995 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Framing/ Rough-in | 8/30/1995 | 8/30/1995 | 8/30/1995 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Carpentry | 8/30/1995 | 8/30/1995 | 8/30/1995 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Framing/ Rough-in | 8/30/1995 | 8/30/1995 | 8/30/1995 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Ceiling grid | 8/23/1995 | 8/23/1995 | 8/23/1995 | P | PASS |
Carl Dependahl
|
|
|
GRID REINSPECTION.
|
INSP - Ceiling grid | 8/22/1995 | 8/22/1995 | 8/22/1995 | P | NR |
Wes Worcester
|
|
|
08/22/95 342 - Carl's ???
|
INSP - Framing/ Rough-in | 8/9/1995 | 8/9/1995 | 8/9/1995 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Framing/ Rough-in | 8/9/1995 | 8/9/1995 | 8/9/1995 | P | PART |
Carl Dependahl
|
|
|
08/09/95 340 - FRAME REINSPECT.
|
(F) Issue permit | | | 7/27/1995 | | I |
|
|
|
|
Inspection Record Card- Bld | | | 7/26/1995 | | |
|
|
|
|
Plan resubmittals received | | | 7/26/1995 | | 7/25 |
|
|
|
received a-2,a-3 resubmittals for review and addtn to plans.
|
Permit taken to Permit Desk | | | 7/26/1995 | | FINL |
|
|
|
ready to issue
|
Plan resubmittals requested | | | 7/21/1995 | | PEND |
|
|
|
FAX TO ARCHITECT CORRECTION LIST FOR RESUBMITTAL REQUESTS
|
Print Pending Permit.......... | | | 7/21/1995 | | PEND |
|
|
|
COPY FOR FILES AND PLANS
|
Plan resubmittals received | | | 7/18/1995 | | PEND |
|
|
|
REVISED ELECTRICAL SHEETS RECEIVED
|
Plan routing begun/TENANTS | | | 6/23/1995 | | PEND |
|
|
|
SENDING TO CDH, PW, PLUMBING, ELEC, MECH, BLD, FIRE
|
Application received | | | 6/22/1995 | | PEND |
|
|
|
RECEIVED FOR REVIEW AND CIRCULATION
|
Application received | | | | | |
|
|
|
|