Information based on query as of Wednesday, July 3, 2024.
Permit Information
Permit NumberBLD95-00584
StatusFinaled
Name WHITE CLOUD AUTO TRANSPORT
Site Address 6438 S SUPPLY WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
WHITE CLOUD AUTO TRANSPORT * TO CONSTRUCT A NEW 6200 SQ.FT. H-4 VEHICLE REPAIR GARAGE. THE BUILDING IS A SINGLE STORY TYPE V NONRATED, MANUFACTURED METAL BUILDING. THE BUILDING IS SPLIT INTO THREE AREAS, 920 SQ.FT IS ADMINISTRATIVE OFFICE SPACE, WITH LIGHT WEIGHT STORAGE ABOVE IN A MEZZANINE, 2200 SQ.FT. IS OUTSIDE COVER REPAIR AREA, THE REMAINING 3080 SQ.FT. FOR VECHILE MAINTENANCE AND REPAIR. TOTAL PAVED AREA IS 58746 SQ.FT. THE INSTALLATION OF THE FIRE SPRINKLER SYSTEM IS REQUIRED BY UBC SECTION 3802(f). ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED REQUIREMENT LIST, AND THE 1991 EDITION OF THE UBC. MP (95-384) DR-61-95
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 9/30/19969/30/1996 DONE
Details
INSP - Final9/30/19969/30/19969/30/1996 PASS
DetailsJim Storey
/ / 301 - FNL -OK FINAL
INSP - Final9/30/19969/30/19969/30/1996 PASS
Details
/ / 405 - reinspect for sprinkler corrections. items corrected.
INSP - Permanent occupancy  9/30/1996 PASS
Perm. Occ. Cert. #6600 issued 9-30-96 to White Cloud Auto Transport.
INSP - Final9/27/19969/28/19969/27/1996A
Details
WAITING ON ALARMS
INSP - Final9/24/19969/24/19969/24/1996 PART
Details
/ / 405 - temp occ ok'd pending sprinkler system issues, c/n issued
INSP - Final9/24/19969/24/19969/24/1996PNH
Details
09/24/96 405 - CORRECTIONS MADE no one there
INSP - Final9/19/19969/19/19969/19/1996 FAIL
Details
/ / 405 - c/n issued....building occupied
INSP - Final9/19/19969/19/19969/19/1996 FAIL
Details
/ / 405 - c/n issued....building occupied
INSP - Final9/17/19969/18/19969/18/1996PCANC
Details
transfered to #301
INSP - Final9/18/19969/18/19969/18/1996PPART
DetailsJim Storey
09/18/96 301 - OTH-OTHER AGENCIES NOT APPROVED pending signoff ok for perm occ.
INSP - Partial final4/5/19964/8/19964/8/1996AFAIL
DetailsJim Storey
04/05/96 301 - CALL EVERETT - ###-#### FOR A TIME. CORR-CORREC-CALL FOR REINSP WHEN COMPLETED OFFICE EXIT DOORS HARDWARE AN SIGNAGE. ADDERSS NUMBERS,ADA UNDER SINK PROTECTION,ADA CURB AC
INSP - Framing/Rough-in2/16/19962/16/19962/16/1996PPASS
DetailsJim Storey
02/16/96 301 -
INSP - Framing/Rough-in2/14/19962/15/19962/15/1996AFAIL
DetailsJim Storey
02/14/96 301 -
INSP - Framing/Rough-in2/13/19962/14/19962/14/1996ACANC
DetailsJim Storey
02/14/96 301 -
(F) Reprint permit  2/5/1996
INSP - Foundation11/9/199511/9/199511/9/1995 PASS
DetailsJim Storey
/ / 301 -
INSP - Foundation11/7/199511/8/199511/8/1995AFAIL
DetailsJim Storey
11/07/95 301 -
INSP - Footings11/3/199511/6/199511/6/1995APASS
DetailsJim Storey
11/03/95 301 -
Routing Off Site - A.C.H.D10/19/1995 10/19/1995 PASS
FEES PAID
Permit taken to Permit Desk  10/19/1995 PASS
Plan Reviewer's activity10/19/1995 10/19/1995 PASS
Plan Reviewer's Copy of Permit  10/19/1995 PASS
(F) Issue permit  10/19/1995 I
Inspection Record Card- Bld  10/19/1995 I
(F) Reprint permit  10/19/1995
Inspection Record Card- Bld  10/19/1995 I
Plan Reviewer's Copy of Permit  9/25/1995
Routing - FIRE9/20/1995 9/22/1995 PASS
Routing - ELECTRICAL8/19/1995 9/20/1995 PASS
Plan Reviewer's activity9/8/1995 9/8/1995 FAIL
Called and left message. Need infor to determine occupancy group and other additional information. plans behind my desk.
Plan Reviewer's activity9/7/1995 9/7/1995 FAIL
sent submittal letter asking for additional information as to the occupancy group.
Routing Off Site - A.C.H.D8/7/1995 8/15/1995 PASS
Impact Fee Certificate #95-001484 paid and copy received 10-19-95
Routing - PUBLIC WORKS7/26/1995 8/7/1995 PASS
Plan routing begun/NEW & ADDTN  7/26/1995
Route to Public Works, Planning, Plumbing, Mechanical and Electrical then to Plan Check. After Plan Check route to ACHD and Fire Department.
Routing - PLANNING7/14/1995 7/21/1995 PASS
Routing - MECHANICAL7/11/1995 7/14/1995 PASS
Routing - PLUMBING7/5/1995 7/11/1995 PASS
Routing - ELECTRICAL7/3/1995 7/5/1995 PASS
Application received  6/8/1995
Routing - BUILDING9/25/1995   PEND
Routing - BUILDING9/22/1995   PEND