INSP - Conference | 3/26/1996 | 3/26/1996 | 3/26/1996 | | PASS |
|
|
|
/ / 333 -
|
INSP - Final | 12/21/1995 | 12/21/1995 | 12/21/1995 | | PASS |
|
|
|
final ok
|
Permanent Occupancy | | 12/21/1995 | 12/21/1995 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 12/21/1995 | | PASS |
|
|
|
Perm. Occ. Cert. #6250 issued 12-21-95 to Barnes & Noble.
|
INSP - Final | 11/22/1995 | 11/22/1995 | 11/22/1995 | | PASS |
|
|
|
temp ok
|
Issue PAID IN FULL permit | | | 11/22/1995 | | |
|
|
|
|
INSP - Temporary occupancy | | | 11/22/1995 | | PASS |
|
|
|
Temp. Occ. Cert. #3097 issued 11-27-95 to Barnes & Noble Bookstore.
|
INSP - Framing/Rough-in | 10/30/1995 | 10/31/1995 | 10/31/1995 | A | PASS |
|
|
|
10/30/95 333 - front facade ok
|
INSP - Ceiling grid | 10/31/1995 | 10/31/1995 | 10/31/1995 | P | PASS |
|
|
|
10/31/95 333 - CEILING SCLG-OK SUSPENDED CEILING
|
INSP - Ceiling grid | 10/25/1995 | 10/25/1995 | 10/25/1995 | P | PASS |
|
|
|
10/25/95 333 - SCLG-OK SUSPENDED CEILING
|
INSP - Ceiling grid | 10/18/1995 | 10/19/1995 | 10/19/1995 | A | PASS |
|
|
|
10/18/95 333 - SCLG-OK SUSPENDED CEILING
|
INSP - Carpentry | 10/10/1995 | 10/11/1995 | 10/11/1995 | A | PASS |
|
|
|
10/11/95 333 - DRAFT STOPS north west ok
|
INSP - Framing/ Rough-in | 9/21/1995 | 9/22/1995 | 9/22/1995 | A | PASS |
|
|
|
09/22/95 333 - FRAM-OK FRAMING will check draft stops later
|
INSP - Framing/ Rough-in | 9/5/1995 | 9/5/1995 | 9/5/1995 | | PART |
|
|
|
/ / 333 - FRAM-OK FRAMING partial see plan at site
|
INSP - Framing/ Rough-in | 8/31/1995 | 9/1/1995 | 9/1/1995 | A | NR |
Jim Storey
|
|
|
08/31/95 301 -
|
(F) Issue permit | | | 8/18/1995 | | I |
|
|
|
|
Inspection Record Card- Bld | | | 8/17/1995 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 8/16/1995 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 8/16/1995 | | |
|
|
|
|
Permit taken to Permit Desk | | | 8/16/1995 | | PASS |
|
|
|
|
Telephone call | | | 8/16/1995 | | |
|
|
|
To James Terry to let him know that more information was needed but that I would submit plan for permit processing. I also clarified with Mr. Terry how the draft stop locations were marked on the plans and outlined there location with a blue felt tip marker.
|
Plan resubmittals requested | | | 8/16/1995 | | |
|
|
|
To provide further clarifications as noted in letter on file to the structural inspector.
|
Plan Reviewer's Copy of Permit | | | 8/16/1995 | | |
|
|
|
|
Plans taken to the Permit Desk | | | 8/16/1995 | | PASS |
|
|
|
|
Routing - BUILDING | 7/28/1995 | | 8/16/1995 | | PASS |
|
|
|
Started plan review to prepare written pending permit for purpose of routing plans to Fire Dept. and Health Dept. 08/08/95 Received plans back from CDH with approval. 08/09/95 Preliminary review completed. Sent & FAXED copies of review to Michelle Wilson c/o James Terry, CLC Assoc. Inc. with a cover letter explaining actions they need to take before plan review can be completed. 08/14/95 Resubmittals to Plan Check desk for resubbmittal stamp from James Terry, personally delivered. 08/15/95 Put new resubmittal sheets into plans. Began review of resubmittals. 08/16/95 Several questions not answered. Sufficient information supplied to allow processing for issueing of building permit. Sent letter to Michelle Wilson care of James Terry asking for further clarification, to be submitted to the structural inspector prior to work starting in areas of question. Copy of letter in file.
|
Plan resubmittals received | | | 8/15/1995 | | |
|
|
|
|
Plan resubmittals requested | | | 8/9/1995 | | PASS |
|
|
|
Faxed and mailed a copy of my preliminary plan review with a cover letter to Michelle Wilson c/o James Terry Project Manager, CLC Associates, Inc.
|
Routing Off Site - C.D.H | 8/2/1995 | | 8/7/1995 | | PASS |
|
|
|
Approved by Bud Fulleton, CDH, per conditions of review on file at his office.
|
Routing - FIRE | 7/28/1995 | | 7/30/1995 | | PASS |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 7/28/1995 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 7/28/1995 | | |
|
|
|
|
Telephone call | | | 7/27/1995 | | |
|
|
|
Phone call from Gayle Jensen of Van Auker Const. saying Mr. Ron Van Auker has okayed the switching of plan check orer of Hertz Equip and B & N Booksellers. These are both Van Auker projects.
|
Meeting | | | 7/27/1995 | | |
|
|
|
Mtg. with Gayle Jensen of Van Auker Const. & representative from Barnes & Noble Booksellers on status of plan review process. I reviewed the location of the interior remodel plans on our plan review log and indicated that the plan review should start at the beginning of next week - 07/31/95 - and should go failrly quickly if the plans submitted are clean and complete requiring little or no resubmittals from the architect. Mr. Jensen suggested that it may be possible to move the review order up by changing order location of reviews between the Hertz Equip. Co. & Barnes & Noble Booksellers if it was approved by Ron Van Auker. He will call me back latter today if it is okay with Mr. Van Auker.
|
Routing - ELECTRICAL | 6/22/1995 | | 6/28/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 6/21/1995 | | 6/22/1995 | | PASS |
|
|
|
|
Routing - PLUMBING | 6/21/1995 | | 6/22/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/16/1995 | | 6/20/1995 | | PASS |
|
|
|
|
Application received | | | 6/15/1995 | | |
|
|
|
|