INSP - Letter of compliance | | | 12/21/1995 | | PASS |
|
|
|
ISSUED #10543 C OF C BY MJW THIS DATE.
|
INSP - Final | 12/5/1995 | 12/5/1995 | 12/5/1995 | | PASS |
|
|
|
/ / 333 - FNL -OK FINAL OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Partial final | 11/21/1995 | 11/21/1995 | 11/21/1995 | P | PASS |
|
|
|
11/21/95 333 - will sign card for temp in office
|
INSP - Final | 11/16/1995 | 11/17/1995 | 11/17/1995 | A | FAIL |
|
|
|
11/17/95 333 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Masonry | 9/12/1995 | 9/13/1995 | 9/13/1995 | A | PASS |
|
|
|
09/13/95 333 - CFRM-OK CEILING FRAMING last pour
|
INSP - Conference | 9/13/1995 | 9/13/1995 | 9/13/1995 | P | PASS |
|
|
|
09/13/95 333 - DON'T KNOW WHAT KIND OF INSP.?????
|
INSP - Masonry | 9/11/1995 | 9/12/1995 | 9/12/1995 | P | PASS |
|
|
|
09/12/95 333 - MASN-REBAR OK fourth pour
|
INSP - Masonry | 9/8/1995 | 9/11/1995 | 9/11/1995 | A | PASS |
|
|
|
09/11/95 333 - MONDAY 8 AM. & 2:30 PM. MASN-REBAR OK second pour
|
INSP - Masonry | 9/11/1995 | 9/11/1995 | 9/11/1995 | | PASS |
|
|
|
/ / 333 - MASN-REBAR OK third pour
|
INSP - Masonry | 9/11/1995 | 9/11/1995 | 9/11/1995 | | PASS |
|
|
|
/ / 333 - MASN-REBAR OK third pour
|
INSP - Masonry | 9/7/1995 | 9/8/1995 | 9/8/1995 | A | PASS |
|
|
|
09/07/95 333 - first pour front columns MASN-REBAR OK
|
INSP - Framing/ Rough-in | 9/5/1995 | 9/6/1995 | 9/6/1995 | A | PASS |
|
|
|
09/06/95 333 - FRAM-OK FRAMING
|
INSP - Framing/ Rough-in | 9/5/1995 | 9/5/1995 | 9/5/1995 | | PASS |
|
|
|
/ / 333 - FRAM-OK FRAMING partial see plan at site
|
INSP - Footings | 8/31/1995 | 9/1/1995 | 9/1/1995 | A | PASS |
Jim Storey
|
|
|
08/31/95 301 -
|
INSP - Framing/ Rough-in | 8/29/1995 | 8/30/1995 | 8/30/1995 | A | PASS |
Jim Storey
|
|
|
08/29/95 301 -
|
INSP - Framing/ Rough-in | 8/23/1995 | 8/23/1995 | 8/23/1995 | P | NR |
Carl Dependahl
|
|
|
FRAME REINSPECT. 333 area
|
INSP - Footings | 8/17/1995 | 8/18/1995 | 8/21/1995 | A | PASS |
|
|
|
08/18/95 333 - FTG -OK FOOTING
|
INSP - Footings | 8/14/1995 | 8/15/1995 | 8/15/1995 | A | PART |
|
|
|
08/14/95 333 - FRMS-OK FORMS-REBAR first two columns ok
|
INSP - Footings | 8/10/1995 | 8/11/1995 | 8/11/1995 | A | PASS |
|
|
|
08/10/95 333 - FTG -OK FOOTING footing and columns at openings
|
Inspection Record Card- Bld | | | 8/9/1995 | | |
|
|
|
|
Routing - BUILDING | 8/1/1995 | | 8/9/1995 | | PASS |
|
|
|
08/01/95 Finished preliminary plan review, compiled list of corrections and / or clarifications needed with a cover letter and Faxed copies to James Terry, Arch., Gayle Jensen - Contractor, T.C. Bearslee-Barnes & Noble Project Manager , Mailed copy to the above plus Mr. Gorman, Structural Engineer at approx. 2:45 P.M. 08/08/95 Received response from engineer and prepared plans for routing to front desk for permit issuance. 08/09/95 It was discovered that the electrical division had not signed off on plans. Routed for signature. 08/09/95 Upgraded entries and returned to Dave Radford for processing at front desk for permit.
|
Permit taken to Permit Desk | | | 8/9/1995 | | PASS |
|
|
|
Missing Elect. Signature on 08/08/95 - not submitted to front desk.
|
Plans taken to the Permit Desk | | | 8/9/1995 | | PASS |
|
|
|
|
(F) Issue permit | | | 8/9/1995 | | |
|
|
|
|
Routing - ELECTRICAL | 6/5/1995 | | 8/9/1995 | | PASS |
|
|
|
Noted disapproved per NEC230-2 by Pat Lass of Electrical Div. Noted that copies of dissaproval were sent to Priest Engineering, Cary Dunn of Prime Commercial ( Bldg. Owner) & CLC Assoc., Inc. (Architects) by Pat. 08/09/95 Plans signed off as approved by Pat Lass of Electrical Division.
|
Plan Reviewer's Copy of Permit | | | 8/8/1995 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/8/1995 | | PASS |
|
|
|
|
Routing - PLUMBING | 8/1/1995 | | 8/7/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 8/1/1995 | | 8/7/1995 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 8/1/1995 | | |
|
|
|
|
Routing - FIRE | 7/28/1995 | | 7/30/1995 | | PASS |
|
|
|
Routing to Fire Dept. prior to Fire Dept. reviewer vacation for two weeks.
|
Meeting | | | 7/27/1995 | | |
|
|
|
Meeting with representative from Noble Barnes & Noble Booksellers to review status of review. Plan is being reviewed now but will be sent to Fire Dept. for review prior to my completion because of vacation for two weeks of F.D. Plan reviewer to allow permit to be issued during his abscence if all other agency concerns have been addressed.
|
Routing - PLANNING | 6/6/1995 | | 6/9/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/1/1995 | | 6/2/1995 | | PASS |
|
|
|
|
Application received | | | 6/1/1995 | | |
|
|
|
|