Permanent Occupancy | | 4/18/1996 | 4/18/1996 | | DONE |
|
|
|
|
INSP - Final | 4/16/1996 | 4/17/1996 | 4/17/1996 | P | PASS |
Carl Dependahl
|
|
|
04/17/96 340 - SIGNED, CARD TO CONTRACTOR OR OWNER
|
INSP - Final | 4/11/1996 | 4/12/1996 | 4/15/1996 | P | FAIL |
Carl Dependahl
|
|
|
04/12/96 340 - C/N, SEALING & NON ABSORBENT WALLS ETC AT PUB REST RMS OK FOR T/O
|
INSP - Ceiling grid | 3/27/1996 | 3/27/1996 | 3/27/1996 | P | PART |
Carl Dependahl
|
|
|
03/27/96 340 - CALL BILL DAVIS - HE WANTS TO MEET WITH YOU. ###-#### TOLD TO INSTALL SEISMIC PODS & SUBMIT DATA ON GRID
|
INSP - Framing/Rough-in | 1/29/1996 | 1/29/1996 | 1/29/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Energy code compliance | 1/25/1996 | 1/25/1996 | 1/25/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Framing/Rough-in | 1/25/1996 | 1/25/1996 | 1/25/1996 | | PART |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Framing/Rough-in | 1/24/1996 | 1/24/1996 | 1/24/1996 | P | NR |
Carl Dependahl
|
|
|
01/24/96 340 -
|
INSP - Framing/Rough-in | 1/19/1996 | 1/22/1996 | 1/22/1996 | A | PART |
Carl Dependahl
|
|
|
01/19/96 340 -
|
INSP - Framing/Rough-in | 1/17/1996 | 1/17/1996 | 1/17/1996 | P | FAIL |
Carl Dependahl
|
|
|
01/17/96 340 -
|
INSP - Carpentry | 12/4/1995 | 12/5/1995 | 12/5/1995 | A | PART |
Carl Dependahl
|
|
|
12/04/95 340 - CELL ####-####
|
(F) Issue permit | | | 8/24/1995 | | |
|
|
|
|
(F) Reprint permit | | | 8/24/1995 | | |
|
|
|
|
Permit taken to Permit Desk | 8/23/1995 | | 8/23/1995 | | |
|
|
|
|
Routing Off Site - A.C.H.D | 8/23/1995 | | 8/23/1995 | | PASS |
|
|
|
Fees paid 8-23-95. Impact Fee Certificate #95-001165
|
Inspection Record Card- Bld | | | 8/23/1995 | | |
|
|
|
|
Routing - FIRE | 8/22/1995 | | 8/22/1995 | | PASS |
|
|
|
8-22-95 Sent back to Fire for review and change letter, fire sprinkler,s have been removed.
|
Telephone call | 8/22/1995 | | 8/22/1995 | | |
|
|
|
phoned and requested the copy of the ACHD fee receipt
|
Plan Reviewer's Copy of Permit | | | 8/21/1995 | | |
|
|
|
|
Routing - FIRE | 7/29/1995 | | 7/30/1995 | | DONE |
|
|
|
routed to Fire to review the removal of the fire sprinklers 08/22/95
|
Routing Off Site - A.C.H.D | 7/24/1995 | | 7/28/1995 | | PEND |
|
|
|
fee need to be paid
|
Routing - ELECTRICAL | 7/18/1995 | | 7/19/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 7/11/1995 | | 7/18/1995 | | FAIL |
|
|
|
|
Routing - PLUMBING | 7/17/1995 | | 7/18/1995 | | PASS |
|
|
|
|
Routing - PLANNING | 7/10/1995 | | 7/11/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/9/1995 | | 7/10/1995 | | PASS |
|
|
|
|
Application received | | | 6/16/1995 | | PEND |
|
|
|
|
Routing - MECHANICAL | 8/7/1995 | | 8/10/1905 | | PASS |
|
|
|
Routed to mechanical approved 8/10/95
|
Routing - BUILDING | 8/23/1995 | | | | PEND |
|
|
|
|
Routing - BUILDING | 8/22/1995 | | | | PEND |
|
|
|
|
Routing - BUILDING | 8/11/1995 | | | | DONE |
|
|
|
plans at my desk waiting for Architects submittal from correction notice
|