(F) Reprint permit | | | 3/16/2000 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 2/10/1997 | | |
|
|
|
Copy of permit for reference to current project under review for installation of one hour occupancy separation room with 1000 gallon diesel fuel, double wall tank for emergency generator backup. Part of BLD97-0110.
|
INSP - Final | 2/1/1996 | 2/1/1996 | 2/1/1996 | | PASS |
|
|
|
|
INSP - Letter of compliance | | | 2/1/1996 | | PASS |
|
|
|
ISSUED #10828 C OF C BY MJW THIS DATE.
|
INSP - Final | 1/30/1996 | 1/30/1996 | 1/30/1996 | | PASS |
Bob Archibald
|
|
|
|
INSP - Final | 1/30/1996 | 1/30/1996 | 1/30/1996 | | PASS |
Carl Westfall
|
|
|
LC ISSUED
|
(F) Reprint permit | | | 10/2/1995 | | |
|
|
|
|
(F) Issue permit | | | 10/2/1995 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 9/28/1995 | | |
|
|
|
|
Permit taken to Permit Desk | 9/28/1995 | | 9/28/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/28/1995 | | |
|
|
|
|
Received Certificate of Value | 9/28/1995 | | 9/27/1995 | | |
|
|
|
|
Routing - ELECTRICAL | 9/5/1995 | | 9/8/1995 | | PASS |
|
|
|
|
Routing - BUILDING | 8/1/1995 | | 9/6/1995 | | FAIL |
|
|
|
UBC plan check started Sept. 5, 1995. Plan review sent to the architect on Sept. 6, 1995. Five items require a response.
|
Plan routing begun/TENANTS | | | 7/31/1995 | | |
|
|
|
Route to Fire Dept. then back to Plan Check.
|
Routing - FIRE | 7/31/1995 | | 7/31/1995 | | PASS |
|
|
|
|
Application received | | | 7/27/1995 | | |
|
|
|
|