INSP - Wall cover | 6/5/1996 | 6/6/1996 | 6/6/1996 | P | PASS |
Wes Worcester
|
|
|
06/06/96 342 - FIREWALL INSPECTION
|
INSP - Framing/Rough-in | 5/8/1996 | 5/8/1996 | 5/2/1996 | P | PART |
Wes Worcester
|
|
|
05/08/96 342 - DOUBLE SHEET ROCK ON CEILING not an approved assy, ie 1x furr downs, referring back to architect as w corrections on resubmittals
|
INSP - Conference | 5/7/1996 | 5/7/1996 | 5/1/1996 | P | PART |
Wes Worcester
|
|
|
05/07/96 342 - 3:30 TUES. P.M.
|
Issue PAID IN FULL permit | | | 11/9/1995 | | I |
|
|
|
II
|
Routing - BUILDING | 9/12/1995 | | 10/31/1995 | | PASS |
|
|
|
Drawings were Carl's desk awaiting a response from the architect since 9-12-95. An acceptable resubmittal came in on 10-25-95. The drawings were approved 10-31-95.
|
Inspection Record Card- Bld | | | 10/31/1995 | | P |
|
|
|
|
Permit taken to Permit Desk | 10/31/1995 | | 10/31/1995 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 10/31/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/31/1995 | | P |
|
|
|
|
Plan resubmittals received | 10/31/1995 | | 10/25/1995 | | |
|
|
|
|
Routing - BUILDING | 8/16/1995 | | 9/12/1995 | | FAIL |
|
|
|
UBC plan check was started Sept. 11, 1995. Report was sent to the architect on Sept 12, 1995. Four items require a response.
|
Routing - MECHANICAL | 8/7/1995 | | 8/16/1995 | | PASS |
|
|
|
|
Routing - PLANNING | 8/4/1995 | | 8/7/1995 | | PASS |
|
|
|
|
Plan routing begun/MISC | | | 8/4/1995 | | |
|
|
|
Route to Planning and Mechanical then back to Plan Check. After Plan Check route to Fire Department.
|
Application received | | | 8/1/1995 | | |
|
|
|
|