Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberBLD95-00788
StatusFinaled
Name BLUE CROSS OF IDAHO
Site Address 1501 S FEDERAL WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
This building is not fire sprinkled. To remodel portions of the 4th floor of an existing office building. Work is to include 2 new interior doors and approximately 64 lineal feet of interior noncombustible wall all per approved drawings and plancheck notes on file. Selective demolition of interior nonbearing walls is covered under this permit. A separate electrical permit is required. This permit is not to establish a Certificate of Occupancy for the building. There are exiting deficiencies on the 1st floor that are relevant to the safe exiting from this floor. PC-322-95 CJW
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final5/30/19965/30/19965/30/1996 PASS
DetailsJim Storey
/ / 301 - FNL -OK FINAL
CHANGE STATUS TO (D)  5/30/1996 PASS
lc #10968
INSP - Letter of compliance  5/30/1996 PASS
lc # 10968
INSP - Final4/26/19964/26/19964/26/1996PPASS
DetailsJim Storey
04/26/96 301 - FNL -OK FINAL routed for sign offs
INSP - Framing/Rough-in11/15/199511/15/199511/15/1995PPASS
Details
11/15/95 338 -
INSP - Conference10/4/199510/4/199510/4/1995 PASS
Details
/ / 338 - UPDATE
(F) Issue permit  9/28/1995
Inspection Record Card- Bld  9/25/1995
Inspection Record Card- Bld  9/25/1995
Permit taken to Permit Desk8/8/1995 9/22/1995
Inspection Record Card- Bld  9/22/1995
Plan Reviewer's Copy of Permit  9/22/1995
Inspection Record Card- Bld  9/22/1995
Received Certificate of Value9/22/1995 9/22/1995
Waiting for Cert. of Value8/8/1995 6/6/1995
Telephone call8/8/1995 6/6/1995
On or about June 6, 1995, the applicant was called and told that the drawings had completed routing. He was told that we needed a Cert. of Value and the Contractor's name. As of Aug. 8, 1995 this has not been provided.
Routing - FIRE5/25/1995 6/5/1995 PASS
Plan routing begun/TENANTS8/8/1995 5/25/1995
Routing - BUILDING5/22/1995 5/25/1995 PASS
UBC plan check was started May 24, 1995. Drawings were approved and routed to the Fire Department May 25, 1995. The drawings were returned to Carl J. Westfall on June 5, 1995 after the Fire Department's review. As of Aug. 8, 1995 the permit has not been picked up.
Application received  5/22/1995