CHANGE STATUS TO (D) | | | 4/2/1996 | | DONE |
|
|
|
|
INSP - Conference | 1/25/1996 | 1/25/1996 | 1/25/1996 | | PASS |
George Slane
|
|
|
/ / 38 - UPDATE
|
INSP - Footings | 11/1/1995 | 11/2/1995 | 11/2/1995 | A | PASS |
|
|
|
11/01/95 333 - LATER AM...... FTG -OK FOOTING
|
INSP - Final | 10/31/1995 | 10/31/1995 | 10/31/1995 | | PASS |
|
|
|
|
INSP - Letter of compliance | 10/31/1995 | 10/31/1995 | 10/31/1995 | | PASS |
|
|
|
ISSUED #95-0808 C OF C BY PAT ELLIS AS PER KIM THIS DATE.
|
INSP - Letter of compliance | 10/31/1995 | 10/31/1995 | 10/31/1995 | | PASS |
|
|
|
ISSUED #95-0808 C OF C BY PAT ELLIS AS PER KIM THIS DATE.
|
INSP - Final | 10/27/1995 | 10/27/1995 | 10/27/1995 | P | PASS |
|
|
|
10/27/95 333 - FNL -OK FINAL
|
INSP - Energy code compliance | 9/29/1995 | 9/29/1995 | 9/29/1995 | P | PASS |
|
|
|
09/29/95 333 - INSL-OK INSULATION-ENERGY CODE
|
INSP - Framing/Rough-in | 9/27/1995 | 9/27/1995 | 9/27/1995 | P | PASS |
|
|
|
FRAME REINSPECT.
|
INSP - Framing/Rough-in | 9/25/1995 | 9/25/1995 | 9/25/1995 | P | FAIL |
|
|
|
09/25/95 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Foundation | 8/28/1995 | 8/28/1995 | 8/28/1995 | | PASS |
|
|
|
/ / 333 - FDN -OK FOUNDATION
|
INSP - Footings | 8/28/1995 | 8/28/1995 | 8/28/1995 | P | PASS |
|
|
|
08/28/95 333 - FTG -OK FOOTING
|
(F) Issue permit | | | 8/22/1995 | | |
|
|
|
|
Permit taken to Permit Desk | | | 8/21/1995 | | |
|
|
|
|
Print Pending Permit.......... | | | 8/21/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/21/1995 | | |
|
|
|
|
Dwelling recd. by Plan Check | | | 8/3/1995 | | |
|
|
|
|
Application received | | | 7/31/1995 | | |
|
|
|
|