CHANGE STATUS TO (D) | | | 4/2/1996 | | DONE |
|
|
|
|
INSP - Letter of compliance | 12/29/1995 | 12/29/1995 | 12/29/1995 | | PASS |
|
|
|
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED # 10410
|
INSP - Letter of compliance | 12/29/1995 | 12/29/1995 | 12/29/1995 | | PASS |
|
|
|
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED # 10410
|
INSP - Final | 12/29/1995 | 12/29/1995 | 12/29/1995 | | PASS |
|
|
|
/ / 338 -
|
INSP - Framing/Rough-in | 11/3/1995 | 11/6/1995 | 11/6/1995 | A | PASS |
|
|
|
11/06/95 338 - REINSPECTION ingineering picked up for this project ok to cover sticker already place
|
INSP - Framing/Rough-in | 11/1/1995 | 11/1/1995 | 11/2/1995 | P | PASS |
|
|
|
11/01/95 333 - REINSPECTION FRAM-OK FRAMING
|
INSP - Framing/ Rough-in | 10/27/1995 | 10/27/1995 | 10/27/1995 | | PASS |
|
|
|
/ / 338 -
|
INSP - Energy code compliance | 10/27/1995 | 10/27/1995 | 10/27/1995 | P | PASS |
|
|
|
10/27/95 338 -
|
INSP - Framing/Rough-in | 10/25/1995 | 10/25/1995 | 10/25/1995 | P | FAIL |
|
|
|
/ / 338 -
|
INSP - Conference | 9/13/1995 | 9/13/1995 | 9/13/1995 | | PASS |
|
|
|
/ / 338 - UPDATE WP
|
INSP - Conference | 9/13/1995 | 9/13/1995 | 9/13/1995 | | PASS |
|
|
|
/ / 338 - UPDATE WP
|
(F) Issue permit | | | 9/5/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/31/1995 | | I |
|
|
|
|
Permit taken to Permit Desk | | | 8/30/1995 | | |
|
|
|
|
Print Pending Permit.......... | | | 8/30/1995 | | |
|
|
|
|
INSP - Footings | 8/28/1995 | 8/28/1995 | 8/28/1995 | P | NR |
Carl Dependahl
|
|
|
EARLY START????
|
INSP - Footings | 8/28/1995 | 8/29/1995 | 8/25/1995 | A | NR |
|
|
|
08/28/95 338 - FROM CARL T. EARLY START EAR-EARLY START POURED WITHOUT INSPECTION NO APPROVED PLANS ON SITE OR P PLAN WILL INSPECT AT THE FRAME
|
Plan Reviewer's Copy of Permit | | | 8/18/1995 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 8/18/1995 | | |
|
|
|
|
Dwelling recd. by Plan Check | | | 8/11/1995 | | |
|
|
|
|
Application received | | | 8/7/1995 | | |
|
|
|
|