Information based on query as of Wednesday, July 3, 2024.
Permit Information
Permit NumberBLD95-00850
StatusFinaled
Name WENSEL CONSTRUCTION INC
Site Address 800 E CITATION CT
Project NameCITATION BUS. CNTR.
Customer Number 
ePlanReviewNo
Description
To finish a 3,464 sq.ft. tenant space for offices of Wensel Construction by building approximatly 2800lf of interior partition wall and a new 1-hr tenant demising wall to the roof deck, installing a new suspended ceiling, providing new exterior wall window openings on the west wall per revised Engineering design, new floor covering, wall finish, cabinets, counters and finishes per approved plans and attached requirement list. Special Inspections by a Qualified Special Inspector is required for all Masonry Revisions Pertaining to this project. A Mechanical, Plumbing, and Electrical Permit is required for this project. A Certificate of Occupancy must be obtained prior to occupying this space. Plan Check # 541-95. PRP INITIAL CERTIFICATE OF VALUE ON FILE. ELEC. 6,000 PLG. 3,500 MECH. 8,000 COMBINED PL/ME 11,500
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Inspection Record Card- Bld  6/10/1996
INSP - Permanent occupancy  4/17/1996 PASS
Perm. Occ. Cert. #6365 issued 4-17-96 to Wensel Construction (offices).
INSP - Final4/16/19964/16/19964/16/1996PPART
DetailsJim Storey
04/16/96 301 - FNL -OK FINAL pending plumbing sign off.
Permanent Occupancy 4/16/19964/16/1996 DONE
Details
INSP - Final1/3/19961/4/19961/4/1996APASS
DetailsJim Storey
01/03/96 301 -
INSP - Temporary occupancy  1/4/1996 PASS
Temp. Occ. Cert. #3119 issued 1-4-96 to Wensel Construction for their new offices.
INSP - Letter of compliance12/29/19951/2/19961/2/1996ANR
DetailsJim Storey
12/29/95 301 -
INSP - Letter of compliance12/29/19951/2/19961/2/1996ANR
DetailsJim Storey
12/29/95 301 -
INSP - Final12/29/19951/2/19961/2/1996 NR
DetailsJim Storey
12/29/95 301 -
INSP - Letter of compliance12/28/199512/28/199512/28/1995PNR
DetailsJim Storey
INSP - Final12/28/199512/28/199512/28/1995PFAIL
DetailsJim Storey
INSP - Letter of compliance12/28/199512/28/199512/28/1995PNR
DetailsJim Storey
INSP - Final12/28/199512/28/199512/28/1995 FAIL
DetailsJim Sly
Not Ready.... Will call for inspection for Tues. Jan 2nd.
INSP - Ceiling grid12/18/199512/18/199512/18/1995PPART
DetailsJim Storey
12/18/95 301 - CEILING GRID & FIREWALL
INSP - Footings10/18/199510/18/199510/18/1995PPASS
DetailsJim Storey
REBAR
INSP - Footings10/17/199510/17/199510/17/1995PPASS
Details
covered w/special inspection
(F) Issue permit  9/27/1995
(F) Reprint permit  9/27/1995
Plan Reviewer's activity  9/21/1995 PASS
did preliminary plan review, prepared letter to arch and contractor, need several items before I can proceed. Forwarding to Planning for DR conformance Question. 09/21/95-Plan Analysis, permit-plan in-put, correction list forwarded to arch and Contractor, issue.
Inspection Record Card- Bld  9/21/1995
Print Pending Permit.LaserJet4  9/21/1995 PASS
ALL OK--ISSUE
Permit taken to Permit Desk  9/21/1995 PASS
ISSUE
Routing - PLANNING8/28/1995 8/28/1995 PASS
conformance with DR 42-95 in question OK PER SCOTT.
Routing - ELECTRICAL8/25/1995 8/28/1995 PASS
Routing - MECHANICAL8/24/1995 8/25/1995 PASS
Routing - PLUMBING8/17/1995 8/24/1995 PASS
Routing - PUBLIC WORKS8/14/1995 8/16/1995 PASS
Plan routing begun/TENANTS  8/14/1995
Route to Public Works, Mechanical, Electrical then back to Plan Check. After Plan Check route to Fire Department.
Application received  8/11/1995 DAR