Case Summary (BLD) | | | 2/7/2013 | | |
|
|
|
|
Permanent Occupancy | | 10/18/1996 | 10/18/1996 | | DONE |
|
|
|
|
INSP - Occupancy Sign-off | 10/17/1996 | 10/18/1996 | 10/18/1996 | A | PASS |
Joe Tawney
|
|
|
10/18/96 406 - sign off for perm occ
|
INSP - Permanent occupancy | | | 10/18/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6640 issued 10-18-96 to Treasure Valley Hospital.
|
INSP - Final | 9/25/1996 | 9/25/1996 | 9/25/1996 | | PASS |
|
|
|
OK FOR TEMP OCC REINSPECTION REQ
|
INSP - Framing/Rough-in | 8/15/1996 | 8/16/1996 | 8/16/1996 | A | PASS |
|
|
|
08/15/96 338 -
|
INSP - Framing/Rough-in | 8/1/1996 | 8/1/1996 | 8/1/1996 | P | PART |
|
|
|
Reviewed suspended ceiling in corridors #1161 & 1166 lights require wires some misc. penetrations reguire firecaulk also reviewed and approved sheetrock ceiling cover in dietary room, walls @ mechanical room and corridor in this area are not completely firecaulked, will need to reinspect penetrations through ceiling access. 325.
|
INSP - Framing/Rough-in | 6/26/1996 | 6/27/1996 | 6/27/1996 | A | PASS |
|
|
|
06/26/96 338 - lead lining complete
|
INSP - Framing/Rough-in | 6/6/1996 | 6/6/1996 | 6/6/1996 | P | PART |
|
|
|
06/06/96 338 - partial penetration protection assemblies check
|
INSP - Framing/Rough-in | 5/22/1996 | 5/23/1996 | 5/23/1996 | A | PASS |
|
|
|
05/23/96 338 - AM. THURS. made ok ok to cover walls behind the elec plm need to inspect the firecaulk at the penetrations above the ceiling line before ceilings are installed.
|
INSP - Framing/Rough-in | 5/14/1996 | 5/15/1996 | 5/15/1996 | A | PART |
|
|
|
05/14/96 338 - partial made ok
|
INSP - Framing/Rough-in | 4/30/1996 | 5/1/1996 | 5/1/1996 | A | PART |
|
|
|
04/30/96 338 - partial ok to cover
|
INSP - Framing/Rough-in | 4/29/1996 | 4/30/1996 | 4/30/1996 | A | PART |
|
|
|
04/29/96 338 -
|
INSP - Framing/Rough-in | 3/20/1996 | 3/20/1996 | 3/20/1996 | P | PART |
|
|
|
03/20/96 338 - fire proofing inspN
|
INSP - Carpentry | 3/12/1996 | 3/12/1996 | 3/12/1996 | P | PASS |
|
|
|
03/12/96 338 - FIREPROOFING PAR T MADE K
|
INSP - Conference | 2/16/1996 | 2/16/1996 | 2/15/1996 | P | PASS |
|
|
|
02/16/96 338 - MIKE WILL CALL YOU FOR A TIME.
|
INSP - Flatwork | 2/7/1996 | 2/7/1996 | 2/7/1996 | P | PASS |
|
|
|
02/07/96 333 - slab FRMS-OK FORMS-REBAR
|
INSP - Roof | 1/26/1996 | 1/29/1996 | 1/29/1996 | A | PASS |
|
|
|
01/29/96 333 - framing of roof ok pending special inspection reports
|
INSP - Carpentry | 1/9/1996 | 1/10/1996 | 1/10/1996 | A | PASS |
|
|
|
01/09/96 333 - MTC ALREADY INSPECTED - FLOOR POUR (ROOF) POURING THURSDA FRMS-OK FORMS-REBAR for roof floor future expansion
|
INSP - Footings | 11/22/1995 | 11/22/1995 | 11/22/1995 | P | PART |
Carl Dependahl
|
|
|
11/22/95 340 - REBAR ALSO
|
INSP - Footings | 11/20/1995 | 11/21/1995 | 11/21/1995 | P | PASS |
|
|
|
11/21/95 333 - REBAR FTG -OK FOOTING
|
INSP - Carpentry | 11/20/1995 | 11/20/1995 | 11/20/1995 | P | PASS |
|
|
|
11/20/95 333 - rebar FTG -OK FOOTING grade beams
|
INSP - Foundation | 11/17/1995 | 11/17/1995 | 11/20/1995 | P | PASS |
|
|
|
11/17/95 333 - REBAR & CONCRETE FDN -OK FOUNDATION
|
INSP - Foundation | 11/16/1995 | 11/16/1995 | 11/16/1995 | P | PASS |
|
|
|
11/16/95 333 - FTG -OK FOOTING
|
INSP - Foundation | 11/1/1995 | 11/2/1995 | 11/2/1995 | A | PASS |
|
|
|
11/01/95 333 - FTG -OK FOOTING
|
Inspection Record Card- Bld | | | 10/24/1995 | | I |
|
|
|
|
Inspection Record Card- Bld | | | 10/24/1995 | | I |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 10/20/1995 | | PASS |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 10/20/1995 | | PASS |
|
|
|
|
Plans taken to the Permit Desk | | | 10/20/1995 | | PASS |
|
|
|
|
Permit taken to Permit Desk | | | 10/20/1995 | | PASS |
|
|
|
|
Additional plans submitted | | | 10/20/1995 | | PASS |
|
|
|
New owners group removed 8 room units from this project phase and made additional changes in areas of finish to reduce the initial cost of construction. Room addition shown as future phase. Reviewed with Gordon Goldsmith of Fire Dept., Tempra Wilson of Planning & Zoning & Bob Garrison, Plan Check Div. Manager. Updated office copy of plans & structural specs and approved set for contractor to install in his approved plan. Permit has allready been issued for this project and work is in progress. Copy of change request letter & P&Z acceptance E-Mail given to inspector, Kim Maurer. Permit has been rewritten to reflect changes and taken to front desk for reissue. No changes in fee schedule do to time involved to re plan check and reissue per mtg. with Bob Garrison, Marv Meyers, Dan Stuart & Wayne Carr of Healthsouth Corp.
|
INSP - Footings | 10/19/1995 | 10/19/1995 | 10/19/1995 | | PASS |
|
|
|
/ / 333 - FTG -OK FOOTING
|
INSP - Footings | 10/16/1995 | 10/17/1995 | 10/17/1995 | A | PART |
|
|
|
10/17/95 338 - REBAR THEY ARE USING SPECIAL INSPECTORS. POURED W/O INSP
|
Meeting | | | 10/11/1995 | | |
|
|
|
Mtg with Marv Meyers, Russell Corp to review plans and receive two copies of structural design, calcs and comment letter from Greg Leishman of Stapley Engineering.
|
Meeting | | | 9/26/1995 | | |
|
|
|
Meeting to review plans for proposed changes for Treasure Valley Hospital. Present at meeting were Wayne Carr, TVH Design; Marv Meyers, Russell Corp.; Bob Garrison, Plan Check Div. Manager & Dan Stuart, Plans Examiner. Reviewed letter to be submitted to each agency involved with the original plan review, describing the changes proposed & a Marv Meyers was to obtain approval of changes from Tempra Wilson of P&Z. Other agency requests for fee alterations (Public Works & ACHD) will bwe handled separately by Marv Meyers. Need new structural design and calcs for relocation of footings and end wall.
|
(F) Issue permit | | | 9/1/1995 | | |
|
|
|
|
(F) Reprint permit | | | 9/1/1995 | | |
|
|
|
|
Routing - BUILDING | 6/25/1994 | | 8/29/1995 | | PASS |
|
|
|
Interior finish reviewed, a preliminary plan review was completed with a copy of items needing to be resumitted sent to Curtis Chong, architect, for his response. Plans were routed to other agencies while waiting for response.
|
Plan Reviewer's Copy of Permit | | | 8/29/1995 | | PASS |
|
|
|
|
Permit taken to Permit Desk | | | 8/29/1995 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/29/1995 | | I |
|
|
|
|
Plans taken to the Permit Desk | | | 8/29/1995 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/29/1995 | | I |
|
|
|
|
Meeting | | | 8/28/1995 | | |
|
|
|
Meeting with Marv Meyers to review resubmittals.
|
Additional plans submitted | | | 8/25/1995 | | PASS |
|
|
|
|
Received Certificate of Value | | | 8/25/1995 | | PASS |
|
|
|
Dave Radford reviewed C of V and quetion on changes to sewer fee's since plans first submitted and Dave updated totals for project.
|
Waiting for Cert. of Value | | | 8/17/1995 | | |
|
|
|
Called Marv Meyers of Russell Corp. to request a Cert. of Value - these were not required for the original submittals - only the application with costs filled in.
|
Telephone call | | | 8/16/1995 | | |
|
|
|
Call from Bob Owens, Boulder Associates Architects, to review required items on rolling steel fire door installation and use of the Papco Insullation product for required clearances per Sec. 2002(d) UMC, 1991 ed. per the NER Report-332 for use around kitchen hood exhaust ducts. I explained that I need specific details calling out the structural materials and connection to be used to support the rolling grill when used in a framed wall. ie; tube steel, lateral bracing, length, cover, etc. and I FAXED him a copy of the NER-332 for his reference.
|
Routing - PLUMBING | 7/14/1994 | | 8/1/1995 | | PASS |
|
|
|
08/09/94 Plan rejected by Lee Rice, Plumbing Div. at returned for routing. 07/31/95 Plans recirculated to Plumbing Div. and approved by Lee Rice on 08/01/95
|
Plan resubmittals requested | | | 7/31/1995 | | |
|
|
|
Copy of outstanding items needing responce and approval before processing plans for a permit, were FAXED to Marv Meyers of Russell Corp.
|
Routing - FIRE | 7/24/1995 | | 7/26/1995 | | PASS |
|
|
|
|
Telephone call | | | 7/19/1995 | | |
|
|
|
Call from Marv Meyers asking that I send him a copy of any outstanding items needing answered by the architect that would delay the issuance of a permit.
|
Plan resubmittals received | | | 6/9/1995 | | |
|
|
|
Received response to 09/01/94 letter when it was decided that the project would be continued.
|
Routing - MECHANICAL | 7/14/1994 | | 1/8/1995 | | PASS |
|
|
|
08/09/94 Plan was rejected by mech. division, Lee Rice and returned for routing. 08/31/95 Plan was recirculated to Mech. for review - plan approved by Lee Rice 08/01/95
|
Plan resubmittals requested | | | 9/1/1994 | | |
|
|
|
Listed items not sufficiently addressed in the 08/24/94 response
|
Plan resubmittals received | | | 8/24/1994 | | |
|
|
|
Incomplete resubmittals. Faxed and Mailed list of unanswered questions on 09/01/94
|
Routing - ELECTRICAL | 7/14/1994 | | 7/26/1994 | | PASS |
|
|
|
Approved by Jack Frank of Elec. Div.
|
Plan resubmittals requested | | | 7/19/1994 | | |
|
|
|
|
Routing - PLANNING | 7/12/1994 | | 7/13/1994 | | PASS |
|
|
|
By Tempra Wilson DR-20-94
|
Routing - PLANNING | 7/11/1994 | | 7/12/1994 | | PASS |
|
|
|
Approved by SRS CU-06-94
|
Routing - PUBLIC WORKS | 7/7/1994 | | 7/8/1994 | | PASS |
|
|
|
|
Routing - BUILDING | 6/17/1994 | | 6/24/1994 | | PASS |
|
|
|
Bob Garrison performed the review of the structural sheel for the Treasure Valley Hospital then forwarded it to Dan Stuart for the Tenant Improvement/Interior Finish.
|
Plan routing begun/NEW & ADDTN | | | 6/16/1994 | | |
|
|
|
|
Application received | | | 6/16/1994 | | |
|
|
|
|
Routing Off Site - A.C.H.D | 6/15/1994 | | 6/16/1994 | | |
|
|
|
|
Routing Off Site - C.D.H | 6/16/1994 | | 6/16/1994 | | |
|
|
|
|