Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberBLD95-00907
StatusFinaled
Name TREASURE VALLEY HOSPITAL
Site Address 8800 W EMERALD ST
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct the structural shell of 28,828 sq. ft. and then finish the interior areas, except the Physical Therapy Suite, for use as Treasure Valley Hospital per the approved plans. To comply with requirements for a fully fire sprinklered, Type II-FR, noncombustible, fire-resistive building. To create operating rooms, patient rooms and support areas as shown on the plans. Contact person is Marv Meyers, Russell Corp. @ 323-0777. Separate elect., mech. & plumbing permits are required. DR-20-94, CU-6-94 PC320-94 drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  2/7/2013  
Permanent Occupancy 10/18/199610/18/1996 DONE
Details
INSP - Occupancy Sign-off10/17/199610/18/199610/18/1996APASS
DetailsJoe Tawney
10/18/96 406 - sign off for perm occ
INSP - Permanent occupancy  10/18/1996 PASS
Perm. Occ. Cert. #6640 issued 10-18-96 to Treasure Valley Hospital.
INSP - Final9/25/19969/25/19969/25/1996 PASS
OK FOR TEMP OCC REINSPECTION REQ
INSP - Framing/Rough-in8/15/19968/16/19968/16/1996APASS
Details
08/15/96 338 -
INSP - Framing/Rough-in8/1/19968/1/19968/1/1996PPART
Details
Reviewed suspended ceiling in corridors #1161 & 1166 lights require wires some misc. penetrations reguire firecaulk also reviewed and approved sheetrock ceiling cover in dietary room, walls @ mechanical room and corridor in this area are not completely firecaulked, will need to reinspect penetrations through ceiling access. 325.
INSP - Framing/Rough-in6/26/19966/27/19966/27/1996APASS
Details
06/26/96 338 - lead lining complete
INSP - Framing/Rough-in6/6/19966/6/19966/6/1996PPART
Details
06/06/96 338 - partial penetration protection assemblies check
INSP - Framing/Rough-in5/22/19965/23/19965/23/1996APASS
Details
05/23/96 338 - AM. THURS. made ok ok to cover walls behind the elec plm need to inspect the firecaulk at the penetrations above the ceiling line before ceilings are installed.
INSP - Framing/Rough-in5/14/19965/15/19965/15/1996APART
Details
05/14/96 338 - partial made ok
INSP - Framing/Rough-in4/30/19965/1/19965/1/1996APART
Details
04/30/96 338 - partial ok to cover
INSP - Framing/Rough-in4/29/19964/30/19964/30/1996APART
Details
04/29/96 338 -
INSP - Framing/Rough-in3/20/19963/20/19963/20/1996PPART
Details
03/20/96 338 - fire proofing inspN
INSP - Carpentry3/12/19963/12/19963/12/1996PPASS
Details
03/12/96 338 - FIREPROOFING PAR T MADE K
INSP - Conference2/16/19962/16/19962/15/1996PPASS
Details
02/16/96 338 - MIKE WILL CALL YOU FOR A TIME.
INSP - Flatwork2/7/19962/7/19962/7/1996PPASS
Details
02/07/96 333 - slab FRMS-OK FORMS-REBAR
INSP - Roof1/26/19961/29/19961/29/1996APASS
Details
01/29/96 333 - framing of roof ok pending special inspection reports
INSP - Carpentry1/9/19961/10/19961/10/1996APASS
Details
01/09/96 333 - MTC ALREADY INSPECTED - FLOOR POUR (ROOF) POURING THURSDA FRMS-OK FORMS-REBAR for roof floor future expansion
INSP - Footings11/22/199511/22/199511/22/1995PPART
DetailsCarl Dependahl
11/22/95 340 - REBAR ALSO
INSP - Footings11/20/199511/21/199511/21/1995PPASS
Details
11/21/95 333 - REBAR FTG -OK FOOTING
INSP - Carpentry11/20/199511/20/199511/20/1995PPASS
Details
11/20/95 333 - rebar FTG -OK FOOTING grade beams
INSP - Foundation11/17/199511/17/199511/20/1995PPASS
Details
11/17/95 333 - REBAR & CONCRETE FDN -OK FOUNDATION
INSP - Foundation11/16/199511/16/199511/16/1995PPASS
Details
11/16/95 333 - FTG -OK FOOTING
INSP - Foundation11/1/199511/2/199511/2/1995APASS
Details
11/01/95 333 - FTG -OK FOOTING
Inspection Record Card- Bld  10/24/1995 I
Inspection Record Card- Bld  10/24/1995 I
Plan Reviewer's Copy of Permit  10/20/1995 PASS
Plan Reviewer's Copy of Permit  10/20/1995 PASS
Plans taken to the Permit Desk  10/20/1995 PASS
Permit taken to Permit Desk  10/20/1995 PASS
Additional plans submitted  10/20/1995 PASS
New owners group removed 8 room units from this project phase and made additional changes in areas of finish to reduce the initial cost of construction. Room addition shown as future phase. Reviewed with Gordon Goldsmith of Fire Dept., Tempra Wilson of Planning & Zoning & Bob Garrison, Plan Check Div. Manager. Updated office copy of plans & structural specs and approved set for contractor to install in his approved plan. Permit has allready been issued for this project and work is in progress. Copy of change request letter & P&Z acceptance E-Mail given to inspector, Kim Maurer. Permit has been rewritten to reflect changes and taken to front desk for reissue. No changes in fee schedule do to time involved to re plan check and reissue per mtg. with Bob Garrison, Marv Meyers, Dan Stuart & Wayne Carr of Healthsouth Corp.
INSP - Footings10/19/199510/19/199510/19/1995 PASS
Details
/ / 333 - FTG -OK FOOTING
INSP - Footings10/16/199510/17/199510/17/1995APART
Details
10/17/95 338 - REBAR THEY ARE USING SPECIAL INSPECTORS. POURED W/O INSP
Meeting  10/11/1995
Mtg with Marv Meyers, Russell Corp to review plans and receive two copies of structural design, calcs and comment letter from Greg Leishman of Stapley Engineering.
Meeting  9/26/1995
Meeting to review plans for proposed changes for Treasure Valley Hospital. Present at meeting were Wayne Carr, TVH Design; Marv Meyers, Russell Corp.; Bob Garrison, Plan Check Div. Manager & Dan Stuart, Plans Examiner. Reviewed letter to be submitted to each agency involved with the original plan review, describing the changes proposed & a Marv Meyers was to obtain approval of changes from Tempra Wilson of P&Z. Other agency requests for fee alterations (Public Works & ACHD) will bwe handled separately by Marv Meyers. Need new structural design and calcs for relocation of footings and end wall.
(F) Issue permit  9/1/1995
(F) Reprint permit  9/1/1995
Routing - BUILDING6/25/1994 8/29/1995 PASS
Interior finish reviewed, a preliminary plan review was completed with a copy of items needing to be resumitted sent to Curtis Chong, architect, for his response. Plans were routed to other agencies while waiting for response.
Plan Reviewer's Copy of Permit  8/29/1995 PASS
Permit taken to Permit Desk  8/29/1995 PASS
Inspection Record Card- Bld  8/29/1995 I
Plans taken to the Permit Desk  8/29/1995 PASS
Inspection Record Card- Bld  8/29/1995 I
Meeting  8/28/1995
Meeting with Marv Meyers to review resubmittals.
Additional plans submitted  8/25/1995 PASS
Received Certificate of Value  8/25/1995 PASS
Dave Radford reviewed C of V and quetion on changes to sewer fee's since plans first submitted and Dave updated totals for project.
Waiting for Cert. of Value  8/17/1995
Called Marv Meyers of Russell Corp. to request a Cert. of Value - these were not required for the original submittals - only the application with costs filled in.
Telephone call  8/16/1995
Call from Bob Owens, Boulder Associates Architects, to review required items on rolling steel fire door installation and use of the Papco Insullation product for required clearances per Sec. 2002(d) UMC, 1991 ed. per the NER Report-332 for use around kitchen hood exhaust ducts. I explained that I need specific details calling out the structural materials and connection to be used to support the rolling grill when used in a framed wall. ie; tube steel, lateral bracing, length, cover, etc. and I FAXED him a copy of the NER-332 for his reference.
Routing - PLUMBING7/14/1994 8/1/1995 PASS
08/09/94 Plan rejected by Lee Rice, Plumbing Div. at returned for routing. 07/31/95 Plans recirculated to Plumbing Div. and approved by Lee Rice on 08/01/95
Plan resubmittals requested  7/31/1995
Copy of outstanding items needing responce and approval before processing plans for a permit, were FAXED to Marv Meyers of Russell Corp.
Routing - FIRE7/24/1995 7/26/1995 PASS
Telephone call  7/19/1995
Call from Marv Meyers asking that I send him a copy of any outstanding items needing answered by the architect that would delay the issuance of a permit.
Plan resubmittals received  6/9/1995
Received response to 09/01/94 letter when it was decided that the project would be continued.
Routing - MECHANICAL7/14/1994 1/8/1995 PASS
08/09/94 Plan was rejected by mech. division, Lee Rice and returned for routing. 08/31/95 Plan was recirculated to Mech. for review - plan approved by Lee Rice 08/01/95
Plan resubmittals requested  9/1/1994
Listed items not sufficiently addressed in the 08/24/94 response
Plan resubmittals received  8/24/1994
Incomplete resubmittals. Faxed and Mailed list of unanswered questions on 09/01/94
Routing - ELECTRICAL7/14/1994 7/26/1994 PASS
Approved by Jack Frank of Elec. Div.
Plan resubmittals requested  7/19/1994
Routing - PLANNING7/12/1994 7/13/1994 PASS
By Tempra Wilson DR-20-94
Routing - PLANNING7/11/1994 7/12/1994 PASS
Approved by SRS CU-06-94
Routing - PUBLIC WORKS7/7/1994 7/8/1994 PASS
Routing - BUILDING6/17/1994 6/24/1994 PASS
Bob Garrison performed the review of the structural sheel for the Treasure Valley Hospital then forwarded it to Dan Stuart for the Tenant Improvement/Interior Finish.
Plan routing begun/NEW & ADDTN  6/16/1994
Application received  6/16/1994
Routing Off Site - A.C.H.D6/15/1994 6/16/1994
Routing Off Site - C.D.H6/16/1994 6/16/1994