INSP - Final | 4/1/1996 | 4/1/1996 | 4/1/1996 | | PASS |
|
|
|
|
INSP - Letter of compliance | | | 4/1/1996 | | PASS |
|
|
|
ISSUED #0944 C OF C BY MJW THIS DATE.
|
(F) Reprint permit | | | 3/20/1996 | | |
|
|
|
|
INSP - Final | 3/19/1996 | 3/19/1996 | 3/19/1996 | P | PART |
|
|
|
03/19/96 338 -
|
INSP - Final | 2/12/1996 | 2/13/1996 | 2/14/1996 | P | FAIL |
|
|
|
02/13/96 333 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Framing/Rough-in | 1/2/1996 | 1/2/1996 | 1/2/1996 | P | PASS |
|
|
|
01/02/96 333 - call Ed ###-#### FRAM-OK FRAMING REAR HALF
|
INSP - Framing/Rough-in | 12/27/1995 | 12/28/1995 | 12/28/1995 | A | PART |
Carl Dependahl
|
|
|
12/28/95 340 -
|
INSP - Foundation | 11/9/1995 | 11/13/1995 | 11/14/1995 | A | PASS |
|
|
|
11/14/95 333 - CONCRETE REBAR FDN -OK FOUNDATION
|
INSP - Footings | 10/24/1995 | 10/24/1995 | 10/24/1995 | P | PART |
Wes Worcester
|
|
|
10/24/95 342 - poured, did not see special inspectors log
|
INSP - Foundation | 10/24/1995 | 10/24/1995 | 10/24/1995 | P | PART |
Wes Worcester
|
|
|
10/24/95 342 - SPECIAL INSPECTORS ON JOB , did not see log
|
INSP - Footings | 10/20/1995 | 10/20/1995 | 10/20/1995 | | PASS |
|
|
|
|
INSP - Foundation | 10/20/1995 | 10/20/1995 | 10/20/1995 | | PASS |
|
|
|
|
INSP - Footings | 10/17/1995 | 10/18/1995 | 10/18/1995 | A | PASS |
|
|
|
10/18/95 333 - THEY HAVE SPECIAL INSPECTORS ON JOB.
|
(F) Issue permit | | | 9/8/1995 | | |
|
|
|
|
(F) Reprint permit | | | 9/8/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/30/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/30/1995 | | |
|
|
|
|
Routing - PLANNING | 6/9/1995 | | 8/29/1995 | | PASS |
|
|
|
DR IS APPROVED CU HAS NOT BEEN APPROVED 8/18/95 NEW PLANS HAVE BEEN SUBMITTED NEW APPROVALS REQUIRED
|
Permit taken to Permit Desk | 8/29/1995 | | 8/29/1995 | | |
|
|
|
|
Routing - BUILDING | 8/29/1995 | | 8/29/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/24/1995 | | 8/29/1995 | | PASS |
|
|
|
Resubmittal
|
Plan Reviewer's Copy of Permit | | | 8/29/1995 | | |
|
|
|
|
Routing - PUBLIC WORKS | 6/4/1995 | | 8/25/1995 | | PASS |
|
|
|
NEW PLANS HAVE BEEN SUBMITTED NEW APPROVALS REQUIRED
|
Routing - PLANNING | 8/21/1995 | | 8/23/1995 | | PASS |
|
|
|
Resubmittal
|
Routing Off Site - A.C.H.D | 7/18/1995 | | 7/18/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 6/21/1995 | | 6/22/1995 | | PASS |
|
|
|
|
Routing - PLUMBING | 6/20/1995 | | 6/21/1995 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 6/14/1995 | | 6/15/1995 | | PASS |
|
|
|
|
Routing - FIRE | 6/14/1995 | | 6/14/1995 | | PASS |
|
|
|
|
Application received | | | 5/16/1995 | | PEND |
|
|
|
|