Case Summary (BLD) | | | 10/6/2015 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 12/12/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6731 issued 12-11-96 to the Life Care Center; also includes permit #s BLD95-1015, BLD95-1014, BLD95-1013, BLD95-1007.
|
Permanent Occupancy | | 12/11/1996 | 12/11/1996 | | DONE |
|
|
|
|
INSP - Permanent occupancy | 11/26/1996 | 11/26/1996 | 11/26/1996 | | PASS |
Joe Tawney
|
|
|
/ / 406 - OK FOR PERM OCC
|
INSP - Final | 11/20/1996 | 11/20/1996 | 11/20/1996 | | PASS |
|
|
|
OK FOR TEMP OCC FINAL SIGN OFF BY 11/22/96
|
INSP - Temporary occupancy | | | 11/20/1996 | | PASS |
|
|
|
Temp. Occ. Cert. #3317 issued 11-20-96 to the Life Care Center of Treasure Valley; also includes permit BLD95-1007, BLD95-1013, BLD95-1014 & BLD95-1015.
|
INSP - Final | 11/15/1996 | 11/15/1996 | 11/15/1996 | | FAIL |
|
|
|
FAILED SPKLR PROBLEMS
|
INSP - Final | 11/4/1996 | 11/7/1996 | 11/7/1996 | P | NR |
Joe Tawney
|
|
|
11/07/96 406 - FINAL RESCH FOR 11/08/96 AT 8:00 AM
|
INSP - Final | 10/30/1996 | 10/31/1996 | 11/1/1996 | P | FAIL |
|
|
|
11/01/96 338 - not ready all penetrations of the corridor walls below t left open for inspection.
|
INSP - Final | 10/29/1996 | 10/29/1996 | 10/29/1996 | P | NR |
|
|
|
10/29/96 338 -
|
INSP-Sprinkler Rough-in/Hydro | 10/22/1996 | 10/22/1996 | 10/22/1996 | | PASS |
Joe Tawney
|
|
|
OK HYDRO TEST WP #1 WINGS B,C,& D
|
INSP-Sprinkler Rough-in/Hydro | 10/21/1996 | 10/21/1996 | 10/21/1996 | | FAIL |
|
|
|
hydro lost 7 psi in 2 hrs problems with hanger locations
|
INSP-Sprinkler Rough-in/Hydro | 10/16/1996 | 10/18/1996 | 10/18/1996 | A | PASS |
Joe Tawney
|
|
|
10/18/96 406 - TRENT BICE ###-#### OR OFF.###-#### OK HYDRO TEST FOR WPS WING A RESUBMITTAL OF SPKLR PLANS REQUIRED
|
INSP-Sprinkler Rough-in/Hydro | 9/24/1996 | 9/25/1996 | 9/25/1996 | P | NR |
Joe Tawney
|
|
|
ALAN - ###-####. NR WILL RESCHEDULE
|
INSP-Sprinkler Rough-in/Hydro | 9/24/1996 | 9/24/1996 | 9/23/1996 | P | FAIL |
Joe Tawney
|
|
|
AN FERGUSON - ###-####. FAIL BROKEN LINE
|
INSP - Ceiling grid | 8/21/1996 | 8/22/1996 | 8/22/1996 | A | PART |
|
|
|
08/22/96 338 -
|
INSP - Framing/Rough-in | 5/7/1996 | 5/8/1996 | 5/8/1996 | A | PART |
Jim Sly
|
|
|
05/07/96 316 - A.M. C/N All trades R.I. inspections...restrain lateral truss braces, wrap elect.box, draft stop expansion wall.
|
INSP - Carpentry | 5/1/1996 | 5/1/1996 | 5/1/1996 | | PART |
|
|
|
/ / 338 -
|
INSP - Conference | 5/1/1996 | 5/1/1996 | 5/1/1996 | | FAIL |
Jim Storey
|
|
|
/ / 301 - meeting w/eng.
|
INSP - Framing/Rough-in | 4/18/1996 | 4/18/1996 | 4/18/1996 | P | PART |
|
|
|
04/18/96 338 - PM
|
INSP - Framing/Rough-in | 4/12/1996 | 4/12/1996 | 4/11/1996 | A | FAIL |
|
|
|
see cn from perry
|
INSP - Wall cover | 4/10/1996 | 4/11/1996 | 4/11/1996 | A | FAIL |
|
|
|
04/10/96 338 - UPPER AREA not ready need to get ready and recall
|
(F) Reprint permit | | | 4/3/1996 | | |
|
|
|
|
INSP - Conference | 3/21/1996 | 3/21/1996 | 3/21/1996 | | PASS |
|
|
|
/ / 338 - called and talked to the super that there will be no inspect resubmitted plans are approved and new or amended plans are taken care o
|
INSP - Framing/Rough-in | 3/20/1996 | 3/21/1996 | 3/21/1996 | A | FAIL |
|
|
|
03/21/96 338 - ROOF FOR A WING no approved plans on the jobsite
|
INSP - Carpentry | 3/6/1996 | 3/7/1996 | 3/12/1996 | A | FAIL |
|
|
|
03/07/96 338 - ROOF NAILING
|
INSP - Wall cover | 2/27/1996 | 2/28/1996 | 2/28/1996 | A | PASS |
|
|
|
02/27/96 338 - NAILING INSPECTION. NOT READY
|
INSP - Footings | 11/6/1995 | 11/6/1995 | 11/6/1995 | P | FAIL |
Jim Storey
|
|
|
11/06/95 301 - POURING AT 10 AM TODAY.......
|
INSP - Footings | 11/6/1995 | 11/6/1995 | 11/6/1995 | | PASS |
|
|
|
/ / 333 - FTG -OK FOOTING
|
(F) Reprint permit | | | 10/12/1995 | | |
|
|
|
|
(F) Issue permit | | | 10/12/1995 | | I |
|
|
|
|
Permit taken to Permit Desk | | | 10/6/1995 | | OK |
|
|
|
|
Inspection Record Card- Bld | | | 10/6/1995 | | |
|
|
|
|
Routing Off Site - A.C.H.D | 10/6/1995 | | 10/6/1995 | | PAID |
|
|
|
A.C.H.D. IMPACT FEES PAID 10/06/95 - CERT. #95-001424
|
Plan Reviewer's activity | | | 10/6/1995 | | OK |
|
|
|
PERMIT READY FOR ISSUE AS OF 10/06/95 P.M..
|
Plan Reviewer's activity | | | 9/26/1995 | | OK |
|
|
|
FINAL REVISIONS FROM ARCHITECT RECEIVED 09/26/95-PERMIT READY FOR ISSUE.
|
Routing - FIRE | 8/29/1995 | | 9/5/1995 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/29/1995 | | |
|
|
|
|
Routing - PUBLIC WORKS | 8/25/1995 | | 8/28/1995 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 8/24/1995 | | NA |
|
|
|
PRELIMINARY PLAN REVIEW WAS COMPLETED AND A COPY OF THE CORRECTION LIST WAS FAXED TO ARCHITECT'S OFFICE EARLY P.M..
|
Routing Off Site - A.C.H.D | 7/10/1995 | | 8/9/1995 | | PEND |
|
|
|
A.C.H.D. IMPACT FEES HAVE NOT PAID AS OF 08/25/95
|
Routing - MECHANICAL | 7/3/1995 | | 7/7/1995 | | OK |
|
|
|
|
Routing - FIRE | 6/30/1995 | | 7/3/1995 | | NA |
|
|
|
|
Routing Off Site - C.D.H | 6/5/1995 | | 6/16/1995 | | OK |
|
|
|
|
Routing - PLUMBING | 5/25/1995 | | 6/2/1995 | | OK |
|
|
|
|
Routing - MECHANICAL | 5/22/1995 | | 5/25/1995 | | NA |
|
|
|
|
Routing - ELECTRICAL | 5/18/1995 | | 5/22/1995 | | OK |
|
|
|
|
Plan Reviewer's activity | | | 5/19/1995 | | NA |
|
|
|
REVISED PLANS WERE RECEIVED ON MAY 19, 1995.
|
Routing - PLANNING | 5/16/1995 | | 5/18/1995 | | OK |
|
|
|
|
Routing - PUBLIC WORKS | 5/9/1995 | | 5/16/1995 | | NA |
|
|
|
|
Plan Reviewer's activity | | | 5/8/1995 | | NA |
|
|
|
SENT THE ARCHITECT, ALEX TUDOR, A LETTER INDICATING THE MAJOR PROBLEMS WITH THE PLANS AND ASKED FOR REVISED PLANS.
|
Application received | | | 5/1/1995 | | PEND |
|
|
|
|
Routing - BUILDING | 9/5/1995 | | | | PEND |
|
|
|
|