Case Summary (BLD) | | | 12/9/2004 | | |
|
|
|
|
INSP - Final | 1/10/1996 | 1/10/1996 | 1/10/1996 | P | PASS |
Carl Dependahl
|
|
|
01/10/96 340 - SUITE 110.
|
INSP - Final | 1/10/1996 | 1/10/1996 | 1/10/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Carpentry | 1/9/1996 | 1/9/1996 | 1/9/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
Permanent Occupancy | | 1/9/1996 | 1/9/1996 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 1/9/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6259 issued 1-9-96 to Rhino Graphics in the Boise Research Center #1.
|
INSP - Final | 12/20/1995 | 12/21/1995 | 12/21/1995 | A | FAIL |
Carl Dependahl
|
|
|
12/20/95 340 - SUITE 110
|
INSP - Final | 12/20/1995 | 12/20/1995 | 12/20/1995 | P | NR |
Carl Dependahl
|
|
|
12/20/95 340 - SUITE 110
|
INSP - Final | 12/13/1995 | 12/13/1995 | 12/13/1995 | P | NR |
Jim Storey
|
|
|
|
INSP - Framing/Rough-in | 11/30/1995 | 11/30/1995 | 11/30/1995 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Ceiling grid | 11/30/1995 | 11/30/1995 | 11/30/1995 | P | FAIL |
Carl Dependahl
|
|
|
11/30/95 340 - SUITE 110
|
INSP - Framing/Rough-in | 10/26/1995 | 10/26/1995 | 11/7/1995 | P | FAIL |
Carl Dependahl
|
|
|
10/26/95 340 -
|
(F) Issue permit | | | 10/24/1995 | | I |
|
|
|
|
Routing - FIRE | 9/27/1995 | | 10/23/1995 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 10/23/1995 | | |
|
|
|
|
Permit taken to Permit Desk | | | 10/23/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/26/1995 | | 9/29/1995 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/26/1995 | | PASS |
|
|
|
FILES
|
Plan Reviewer's activity | | | 9/26/1995 | | PASS |
|
|
|
PLAN REVIEW/ANALYSIS, NO CORRECTIONS NEEDED, PERMIT-PLAN INPUT, SEND TO PW, FIRE.
|
Routing - BUILDING | 9/25/1995 | | 9/26/1995 | | PASS |
|
|
|
OK PER THIS DEPARTMENT AS SOON AS PW, AND FIRE APPROVE
|
Routing - ELECTRICAL | 9/18/1995 | | 9/19/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 9/18/1995 | | 9/18/1995 | | NR |
|
|
|
|
Plan routing begun/TENANTS | 8/25/1995 | | 8/25/1995 | | MYS |
|
|
|
Route to Public Works, Mechanical, Electrical then back to Plan Check. After Plan Check route to Fire Department.
|
Application received | | | 8/24/1995 | | |
|
|
|
|