Case Summary (BLD) | | | 10/6/2015 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 12/12/1996 | | PASS |
|
|
|
See comment under permit #BLD95-1001 re: issuance of perm. occ. cert.
|
INSP - Permanent occupancy | 11/26/1996 | 11/26/1996 | 11/26/1996 | | PASS |
Joe Tawney
|
|
|
/ / 406 - OK FOR PERM OCC
|
INSP - Occupancy Sign-off | 11/26/1996 | 11/26/1996 | 11/26/1996 | | PASS |
|
|
|
In compliance w/DR-12-95/Signed Final (Art Yingling)
|
INSP - Final | 11/20/1996 | 11/20/1996 | 11/20/1996 | | PASS |
|
|
|
OK FOR TEMP OCC FINAL SIGN OFF BY 11/22/96
|
INSP - Temporary occupancy | | | 11/20/1996 | | PASS |
|
|
|
|
INSP - Final | 11/15/1996 | 11/15/1996 | 11/15/1996 | | FAIL |
|
|
|
FAILED SPKLR PROBLEMS
|
INSP - Occupancy Sign-off | 11/14/1996 | 11/12/1996 | 11/12/1996 | | NR |
|
|
|
Req. Insp. for Final Occ/ Insp by Art Yingling reveals changes NOT APPROVED - Application for modification of DR-12-95 is required (submit to Martin Santoyo/DR Analyst) (X-Ref: CU-73-94)
|
INSP - Final | 11/1/1996 | 11/8/1996 | 11/8/1996 | A | NR |
Joe Tawney
|
|
|
11/07/96 406 - RESCH FOR 11/08/96 NOT READY
|
INSP - Final | 11/4/1996 | 11/5/1996 | 11/5/1996 | A | NR |
|
|
|
11/05/96 338 -
|
INSP - Final | 10/30/1996 | 10/31/1996 | 11/1/1996 | P | FAIL |
|
|
|
11/01/96 338 -
|
INSP - Final | 10/29/1996 | 10/29/1996 | 10/29/1996 | P | NR |
|
|
|
10/29/96 338 - NR
|
INSP - Framing/Rough-in | 6/10/1996 | 6/11/1996 | 6/11/1996 | P | PART |
|
|
|
06/11/96 338 - partial made ok spoke with the sprink people on the fire will usa metacaulk 950 on the metal and 835 and 880 on the plastic
|
INSP - Framing/Rough-in | 6/3/1996 | 6/4/1996 | 6/4/1996 | A | NR |
Jim Storey
|
|
|
06/03/96 301 - TRANSPHERED TO PERRY VIA PHONE.
|
INSP - Carpentry | 5/1/1996 | 5/1/1996 | 5/1/1996 | | PART |
|
|
|
/ / 338 -
|
INSP - Conference | 5/1/1996 | 5/1/1996 | 5/1/1996 | | FAIL |
Jim Storey
|
|
|
/ / 301 - meet w/heart truss eng.
|
INSP - Carpentry | 5/1/1996 | 5/1/1996 | 5/1/1996 | | PART |
|
|
|
/ / 338 -
|
INSP - Framing/Rough-in | 4/26/1996 | 4/29/1996 | 4/29/1996 | P | CANC |
|
|
|
ON LIDS...NOT HERE SENT TO JIM STOREY
|
INSP - Framing/Rough-in | 4/29/1996 | 4/29/1996 | 4/29/1996 | | FAIL |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 4/24/1996 | 4/24/1996 | 4/24/1996 | P | PART |
|
|
|
04/24/96 338 - NAILING first layer on the ceiling drywall ok for the 2n
|
INSP - Framing/Rough-in | 4/19/1996 | 4/22/1996 | 4/22/1996 | A | PART |
|
|
|
04/19/96 338 - SHEET ROCK..MAILINGok in the d wing partial
|
INSP - Framing/Rough-in | 4/18/1996 | 4/18/1996 | 4/18/1996 | P | PART |
|
|
|
04/18/96 338 - PM
|
INSP - Roof | 4/12/1996 | 4/12/1996 | 4/12/1996 | P | PASS |
|
|
|
04/12/96 338 - ROOF NAILING ok to cover the roof deck
|
INSP - Framing/Rough-in | 4/12/1996 | 4/12/1996 | 4/11/1996 | A | FAIL |
|
|
|
see cn from perry
|
INSP - Carpentry | 4/10/1996 | 4/11/1996 | 4/11/1996 | A | FAIL |
|
|
|
04/10/96 338 - NAILING ROOF not ready c/n issued
|
Routing Off Site - A.C.H.D | 3/18/1996 | | 3/20/1996 | | PEND |
|
|
|
|
Routing Off Site - C.D.H | 3/11/1996 | | 3/18/1996 | | PASS |
|
|
|
CALLED GENE WALKER ###-####. 3/7/96 DAR
|
INSP - Framing/Rough-in | 3/11/1996 | 3/12/1996 | 3/12/1996 | A | PART |
Jim Storey
|
|
|
03/11/96 301 - FRAME REINSPECT
|
Routing - PLUMBING | 3/8/1996 | | 3/11/1996 | | PASS |
|
|
|
|
Routing - MECHANICAL | 3/5/1996 | | 3/8/1996 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 3/5/1996 | | PEND |
|
|
|
CORRECTION LIST WITH RESUBMITTAL REQUEST SENT TO ARCHITECT 03/05/96 (ALEX TUDOR).
|
Routing - PUBLIC WORKS | 2/16/1996 | | 2/20/1996 | | PASS |
|
|
|
|
Routing - PLANNING | 2/1/1996 | | 2/15/1996 | | PASS |
|
|
|
THIS IS A MAJOR RESUBMITTAL ADDING APPROXIMATELY 3000 SQ. F. TO THE PROJECT. DAR X-ref: DR-12-95,CU-73-94. CU approved by RC. DR approved by MS.
|
INSP - Footings | 12/1/1995 | 12/1/1995 | 12/1/1995 | P | PART |
Carl Dependahl
|
|
|
12/01/95 340 - SPECIAL INSPECTOR ON JOB. KIM WANTED TO KNOW WHEN THEY WERE POURING.
|
INSP - Foundation | 11/20/1995 | 11/21/1995 | 11/21/1995 | A | PASS |
|
|
|
11/21/95 333 - STEM WALLS
|
INSP - Foundation | 11/20/1995 | 11/21/1995 | 11/21/1995 | A | PASS |
|
|
|
11/21/95 333 - STEM WALLS
|
INSP - Foundation | 11/20/1995 | 11/20/1995 | 11/20/1995 | P | PASS |
|
|
|
11/20/95 333 - FDN -OK FOUNDATION first half
|
INSP - Footings | 11/16/1995 | 11/17/1995 | 11/20/1995 | P | PASS |
|
|
|
11/17/95 333 - PM LATE FTG -OK FOOTING balance ok
|
(F) Issue permit | | | 10/12/1995 | | |
|
|
|
|
(F) Reprint permit | | | 10/12/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/6/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/6/1995 | | |
|
|
|
|
Application received | | | | | |
|
|
|
|
Routing - BUILDING | 2/15/1996 | | | | PEND |
|
|
|
|
Routing - BUILDING | 2/21/1996 | | | | PEND |
|
|
|
|