Letter of compliance | | | 8/31/1999 | | PASS |
|
|
|
Letter of Compliance #17901 issued 8-31-99.
|
INSP - Final | 8/24/1999 | 8/25/1999 | 8/25/1999 | A | PASS |
Alan Hauser
|
|
|
08/25/99 350 - dennis- ###-#### fn occ insp
|
INSP-Final Inspection | 8/20/1999 | 8/20/1999 | 8/20/1999 | | PASS |
Joe Tawney
|
|
|
08/20/99 406 - OK FOR CERT OF COMPLETION
|
INSP - Final | 8/20/1999 | 8/20/1999 | 8/20/1999 | P | NR |
Jim Sly
|
|
|
08/20/99 316 - NR
|
INSP - Final | 8/10/1999 | 8/10/1999 | 8/10/1999 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - REINSP FAIL 1 HR SPKLR ROOM
|
Code Occupancy Approval | | | 8/5/1999 | | PASS |
|
|
|
Meets compliance.
|
Print Occupancy Form | | | 7/30/1999 | | |
|
|
|
|
Print Occupancy Form | | | 7/21/1999 | | |
|
|
|
|
INSP - Temporary occupancy | 12/23/1997 | 12/23/1997 | 12/23/1997 | P | FAIL |
Jim Sly
|
|
|
12/23/97 316 - C/N....No approved plans or occupancy request form on sit
|
INSP - Final | 11/25/1997 | 11/28/1997 | 11/28/1997 | A | NR |
Tom Arcoraci
|
|
|
11/28/97 408 - SHELL AND CORE/ CALL RICO AT ###-####
|
INSP-Final Inspection | 11/25/1997 | 11/26/1997 | 11/26/1997 | P | NR |
Joe Tawney
|
|
|
11/26/97 406 - SHELL AND CORE/ READY AFTER 2:00 ANY QUESTIONS- RICO-867- NOT READY NO PLANS ON SITE
|
INSP - Final | 11/4/1997 | 11/5/1997 | 11/5/1997 | A | FAIL |
Joe Tawney
|
|
|
SHELL FAIL
|
Print Occupancy Form | | | 11/4/1997 | | |
|
|
|
|
Print Occupancy Form | | | 11/4/1997 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/4/1997 | | PASS |
|
|
|
|
Print Occupancy Form | | | 11/4/1997 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 10/10/1997 | 10/13/1997 | 10/13/1997 | A | PART |
Joe Tawney
|
|
|
10/13/97 406 - OK ON ROUGH IN AND HYDRO TEST
|
INSP-Sprinkler Rough-in/Hydro | 9/18/1997 | 9/22/1997 | 9/22/1997 | P | NR |
Joe Tawney
|
|
|
09/22/97 406 - WILL BE READY ARROUND 1 P.M. JOE I DIDN'T KNOW IF THIS W NOT.PE NOT READY NO PLANS ON SITE WATER NOT TURNED ON
|
Inspection Record Card- Bld | | | 8/26/1997 | | |
|
|
|
|
INSP-Conference | 8/15/1997 | 8/15/1997 | 8/15/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - PRE FINAL CONFERENCE SPKLR SYSTEM CURB STRIPING 1 HR SPKLR R
|
INSP - Final | 8/14/1997 | 8/15/1997 | 8/15/1997 | A | FAIL |
Jim Sly
|
|
|
08/14/97 316 - C/N...Need special insp reports, stamped approval from en
|
INSP-Final Inspection | 8/14/1997 | 8/15/1997 | 8/15/1997 | A | FAIL |
Jim Sly
|
|
|
08/14/97 316 - C/N...Need Special insp reports, engineers stamped approv
|
INSP - Flatwork | 9/17/1996 | 9/18/1996 | 9/18/1996 | P | PASS |
Jim Sly
|
|
|
09/17/96 316 - SLAB - SPEC. INSPECTORS ON JOB. SLAB AND REINFORCEMENT PENDING SPECIAL INSPECTORS OK. 1 E. SECTION..1 W. SECTION OF NORTH BLDG.
|
INSP - Footings | 9/10/1996 | 9/11/1996 | 9/11/1996 | P | PASS |
Jim Sly
|
|
|
09/10/96 316 - OK..pending special inspection OK'd.
|
(F) Issue permit | | | 9/1/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/1/1995 | | |
|
|
|
|
Permit taken to Permit Desk | | | 9/1/1995 | | PASS |
|
|
|
|
(F) Reprint permit | | | 9/1/1995 | | |
|
|
|
|
Routing Off Site - A.C.H.D | 8/11/1995 | | 8/30/1995 | | PASS |
|
|
|
Paid ACHD fees Cert. # 95-001225 dated 08/30/95
|
Routing - PUBLIC WORKS | 5/17/1995 | | 5/30/1995 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 4/4/1995 | | 4/5/1995 | | PEND |
|
|
|
|
Routing - FIRE | 4/5/1995 | | 4/5/1995 | | PASS |
|
|
|
|
Routing - BUILDING | 2/8/1995 | | 3/1/1995 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 2/8/1995 | | PEND |
|
|
|
|
Application received | | | 2/8/1995 | | PEND |
|
|
|
|