INSP - Permanent occupancy | | | 10/15/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6631 issued 10-14-96 to the LDS Church.
|
Permanent Occupancy | | 10/11/1996 | 10/11/1996 | | DONE |
|
|
|
|
INSP - Final | 10/4/1996 | 10/4/1996 | 10/4/1996 | | PASS |
Joe Tawney
|
|
|
/ / 406 -
|
INSP - Final | 10/4/1996 | 10/4/1996 | 10/4/1996 | | PASS |
Joe Tawney
|
|
|
/ / 406 -
|
INSP - Final | 10/2/1996 | 10/4/1996 | 10/3/1996 | A | PASS |
|
|
|
10/04/96 338 - made ok signed the perm side
|
INSP - Conference | 10/3/1996 | 10/3/1996 | 10/3/1996 | | PASS |
|
|
|
/ / 338 -
|
INSP - Final | 10/3/1996 | 10/3/1996 | 10/3/1996 | | |
|
|
|
|
INSP - Conference | 8/27/1996 | 8/27/1996 | 8/26/1996 | P | PASS |
|
|
|
08/27/96 338 - 0out of time no access
|
INSP - Framing/Rough-in | 7/22/1996 | 7/23/1996 | 7/22/1996 | A | PASS |
|
|
|
07/23/96 338 - ALSO INSPEVTED BY THE ENGINEER OF RECORD
|
INSP - Framing/Rough-in | 7/16/1996 | 7/16/1996 | 7/16/1996 | P | PASS |
|
|
|
07/16/96 338 - USING THERMAL FIBER TO FIRE BLOCK COMBUSTABLE FLOOR FURRI
|
INSP - Framing/Rough-in | 6/26/1996 | 6/26/1996 | 6/26/1996 | P | PASS |
|
|
|
06/26/96 338 - P.M. west end ok to cover
|
INSP - Masonry | 5/30/1996 | 5/30/1996 | 5/30/1996 | | PASS |
|
|
|
/ / 338 - last bond beam made ok r- bar placed
|
INSP - Framing/Rough-in | 5/29/1996 | 5/30/1996 | 5/30/1996 | P | PART |
|
|
|
05/30/96 338 - REINSPECTION partial made ok as other trades pass off
|
INSP - Masonry | 5/30/1996 | 5/30/1996 | 5/30/1996 | | PASS |
|
|
|
/ / 338 - last bond beam made ok r- bar placed
|
INSP - Footings | 5/22/1996 | 5/22/1996 | 5/22/1996 | | PASS |
|
|
|
/ / 338 - west end footings made ok r-bar placed
|
INSP - Framing/Rough-in | 5/21/1996 | 5/22/1996 | 5/22/1996 | A | PASS |
|
|
|
05/22/96 338 - Request for late a.m. inspection. partial frame ceilings
|
INSP - Set-back | 5/22/1996 | 5/22/1996 | 5/21/1996 | | CANC |
|
|
|
this was in error and cannot seem to delete item. Terry.
|
INSP - Framing/Rough-in | 5/7/1996 | 5/7/1996 | 5/7/1996 | | PART |
|
|
|
/ / 338 - STHG-OK ROOF SHEATHING FRAM-OK FRAMING PARTIAL
|
INSP - Conference | 5/1/1996 | 5/1/1996 | 5/1/1996 | P | PASS |
|
|
|
05/01/96 338 -
|
INSP - Masonry | 4/29/1996 | 4/30/1996 | 4/30/1996 | A | PASS |
|
|
|
04/30/96 338 - INSPECTION FOR MASONARY REINFORCING typically poured w/o
|
INSP - Carpentry | 4/17/1996 | 4/18/1996 | 4/18/1996 | A | PASS |
|
|
|
04/18/96 338 - POURING AT 10 A.M.
|
INSP - Carpentry | 4/15/1996 | 4/16/1996 | 4/16/1996 | P | FAIL |
|
|
|
04/15/96 338 - BOND BEAM POURED W/O INSP
|
INSP - Carpentry | 4/12/1996 | 4/15/1996 | 4/15/1996 | A | PASS |
|
|
|
04/12/96 338 - BOND BEAM BLOCK WALL
|
INSP - Carpentry | 4/11/1996 | 4/12/1996 | 4/12/1996 | A | PASS |
|
|
|
04/11/96 338 - poured w/o insp if typical of project will be ok
|
INSP - Carpentry | 4/11/1996 | 4/12/1996 | 4/12/1996 | P | PASS |
|
|
|
04/12/96 338 - BOND BEAM. EARLY P.M. could not wait pwo insp
|
INSP - Carpentry | 4/10/1996 | 4/10/1996 | 4/10/1996 | P | FAIL |
|
|
|
poured bond beam without inspection.
|
INSP - Masonry | 4/8/1996 | 4/9/1996 | 4/9/1996 | P | PASS |
|
|
|
04/09/96 338 - pass r-bar placed
|
INSP - Carpentry | 4/5/1996 | 4/8/1996 | 4/8/1996 | P | PASS |
|
|
|
04/08/96 338 - BOND BEAM, ETC..... misc re bar ok okk to pour this one
|
INSP - Carpentry | 4/5/1996 | 4/8/1996 | 4/8/1996 | A | PASS |
|
|
|
04/05/96 338 - BOND BEAM, ETC.
|
INSP - Carpentry | 4/4/1996 | 4/5/1996 | 4/5/1996 | P | NR |
|
|
|
04/05/96 338 - BOND BEAM INSP. NOT READY TODAY
|
INSP - Masonry | 4/4/1996 | 4/4/1996 | 4/4/1996 | P | PASS |
|
|
|
04/04/96 338 - MASN-REBAR OK
|
INSP - Masonry | 3/29/1996 | 4/1/1996 | 4/1/1996 | A | PASS |
|
|
|
made ok r-b ar placed
|
INSP - Foundation | 3/25/1996 | 3/26/1996 | 3/26/1996 | A | PASS |
|
|
|
03/26/96 338 - REBAR LATE A.M. 12 " footing made ok
|
INSP - Footings | 3/21/1996 | 3/22/1996 | 3/22/1996 | P | PART |
Carl Dependahl
|
|
|
03/22/96 340 - EARLY PM PLEASE BEFORE 3:00 r- bar placed ok to pour par
|
INSP - Conference | 3/8/1996 | 3/11/1996 | 3/19/1996 | A | PASS |
|
|
|
CONF. ON FRAMING DONE BY 333
|
INSP - Framing/Rough-in | 3/15/1996 | 3/18/1996 | 3/18/1996 | A | CANC |
|
|
|
03/18/96 338 - done this am
|
INSP - Masonry | 3/13/1996 | 3/13/1996 | 3/13/1996 | P | PASS |
|
|
|
03/13/96 338 - EARLY PM
|
INSP - Masonry | 3/12/1996 | 3/12/1996 | 3/12/1996 | P | PASS |
|
|
|
03/12/96 338 - REINFORCING EARLY PM POSSIBLE. bond beam ok for the the elev at the gable looks good
|
INSP - Masonry | 3/11/1996 | 3/11/1996 | 3/11/1996 | A | PART |
|
|
|
/ / 333 - south and west wing 1st 4 feet of masonry and foundation at same
|
INSP - Masonry | 3/7/1996 | 3/8/1996 | 3/8/1996 | A | PART |
Wes Worcester
|
|
|
REBAR for masonry cells ok north wall on west side
|
INSP - Footings | 3/7/1996 | 3/7/1996 | 3/7/1996 | P | PART |
Wes Worcester
|
|
|
rebar. WES - PLEASE CALL PERRY. THIS IS SCHEDULED FOR LATE P.M. South portion cover adjusted to minimum. North portion poured prior to my arrival on site. PWI
|
INSP - Foundation | 3/1/1996 | 3/4/1996 | 3/4/1996 | A | PASS |
|
|
|
03/01/96 338 - partial ok
|
INSP - Footings | 3/1/1996 | 3/4/1996 | 3/4/1996 | A | PASS |
|
|
|
03/01/96 338 - partial
|
INSP - Footings | 2/28/1996 | 2/29/1996 | 2/29/1996 | A | PASS |
|
|
|
REBAR LATE AM
|
INSP - Foundation | 2/23/1996 | 2/26/1996 | 2/26/1996 | A | PASS |
|
|
|
02/23/96 338 - WALL REINFORCING FDN -OK FOUNDATION
|
INSP - Foundation | 2/21/1996 | 2/22/1996 | 2/22/1996 | A | PASS |
|
|
|
02/21/96 338 - REBAR BETWEEN 11 & 12 A.M. PARTIAL FOOTING OK
|
Issue PAID IN FULL permit | | | 1/9/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/8/1996 | | |
|
|
|
|
Plan Received by (JCM) | 8/28/1995 | | 1/5/1996 | | PASS |
John Menard
|
|
|
01/05/96 11:31:30 JCM - this action updated by action script from <<>> in Case No. BLD96-0016 01/05/96 13:48:37 JCM - this action updated by action script from <<>> in Case No. BLD95-1208
|
Permit taken to Permit Desk | | | 1/5/1996 | | PASS |
|
|
|
PERMIT READY FOR ISSUE - JCM
|
Routing - FIRE | 1/3/1996 | | 1/5/1996 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 12/13/1995 | | PEND |
|
|
|
PLAN RESUBMITTALS WERE REVIEWED AND A DETERMINATION WAS MADE THAT NOT ALL REQUESTED INFORMATION HAD BEEN SUBMITTED. A LETTER WAS SENT TO SCOTT WENDELL, ARCHITECT, REQUESTING SUBMITTAL OF ALL PREVIOUSLY REQUESTED INFORMATION.
|
Routing - FIRE | 10/6/1995 | | 12/12/1995 | | FAIL |
|
|
|
|
Plan Reviewer's activity | | | 10/6/1995 | | PEND |
|
|
|
REVIEW ON RESUBMITTED PLANS RECEIVED 09/25/95. LEETER SENT TO ARCHITECT FOR ADDITIONAL REVISIONS AND INFORMATION 10/06/95.
|
Routing - PUBLIC WORKS | 9/12/1995 | | 9/15/1995 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 8/28/1995 | | PEND |
|
|
|
PRELIMINARY PLAN REVIEW COMPLETED 09/11/95 CORRECTION LIST SENT TO ARCHITECT.
|
Routing - FIRE | 8/15/1995 | | 8/21/1995 | | FAIL |
|
|
|
|
Routing Off Site - A.C.H.D | 8/14/1995 | | 8/16/1995 | | PASS |
|
|
|
IMPACT FEES PAID-08/15/95-CERT. #95-01112.
|
Received Certificate of Value | | | 8/15/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 7/28/1995 | | 7/31/1995 | | PASS |
|
|
|
|
Routing - PLUMBING | 7/19/1995 | | 7/28/1995 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 7/14/1995 | | 7/19/1995 | | PASS |
|
|
|
|
Routing - PLANNING | 7/13/1995 | | 7/14/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/11/1995 | | 7/13/1995 | | FAIL |
|
|
|
DRAINAGE PLAN REQUIRED.
|
Routing - FIRE | 7/11/1995 | | 7/13/1995 | | FAIL |
|
|
|
|
Application received | | | 6/20/1995 | | PEND |
|
|
|
|
Routing - BUILDING | 9/28/1995 | | | | PEND |
|
|
|
|
Routing - BUILDING | 9/18/1995 | | | | PEND |
|
|
|
|
Routing - BUILDING | 12/12/1995 | | | | PEND |
|
|
|
|
Routing - BUILDING | 1/5/1996 | | | | PEND |
|
|
|
|