INSP - Letter of compliance | | | 6/6/1996 | | PASS |
|
|
|
ISSUED #11364 C OF C BY 333.
|
INSP - Final | 6/5/1996 | 6/5/1996 | 6/5/1996 | | PASS |
|
|
|
|
INSP - Framing/Rough-in | 4/16/1996 | 4/17/1996 | 4/17/1996 | A | PASS |
|
|
|
ok
|
INSP - Ceiling grid | 3/6/1996 | 3/6/1996 | 3/6/1996 | | PART |
Bob Archibald
|
|
|
CEILING GRID OK, CN ISSUED FOR CORRIDOR CORRECTIONS,
|
INSP - Framing/Rough-in | 2/14/1996 | 2/14/1996 | 2/14/1996 | | PART |
Bob Archibald
|
|
|
cn issued.
|
INSP - Footings | 10/19/1995 | 10/19/1995 | 10/19/1995 | | PASS |
Bob Archibald
|
|
|
Special inspector on site.
|
INSP - Footings | 10/11/1995 | 10/11/1995 | 10/11/1995 | | PASS |
Bob Archibald
|
|
|
Pre-con on special inspection requirements. Special inspector on site.
|
(F) Issue permit | | | 9/27/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/27/1995 | | I |
|
|
|
|
Plans taken to the Permit Desk | | | 9/27/1995 | | PASS |
|
|
|
|
Permit taken to Permit Desk | | | 9/27/1995 | | PASS |
|
|
|
|
Routing - FIRE | 9/19/1995 | | 9/26/1995 | | PASS |
|
|
|
|
Plan Reviewer's activity | 9/19/1995 | | 9/19/1995 | | PASS |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 9/19/1995 | | |
|
|
|
|
Routing Off Site - A.C.H.D | 8/1/1995 | | 8/5/1995 | | PASS |
|
|
|
NO FEES REQUIRED FOR THIS ADDITION
|
Routing - MECHANICAL | 7/17/1995 | | 7/18/1995 | | PASS |
|
|
|
|
Routing - PLUMBING | 7/16/1995 | | 7/17/1995 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 7/12/1995 | | 7/13/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/11/1995 | | 7/12/1995 | | PASS |
|
|
|
|
Routing - PLANNING | 7/4/1995 | | 7/5/1995 | | PASS |
|
|
|
|
Application received | | | 6/30/1995 | | PEND |
|
|
|
|