Permanent Occupancy | | 4/3/1996 | 4/3/1996 | | DONE |
|
|
|
|
INSP - Final | 4/3/1996 | 4/3/1996 | 4/3/1996 | P | PASS |
Carl Dependahl
|
|
|
04/03/96 340 - FOR CERT. OCC. c/o ok, card signed...to cathy w.
|
INSP - Permanent occupancy | | | 4/3/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6353 issued 4-3-96 to Primary Health Medical Clinic.
|
INSP - Temporary occupancy | | | 3/19/1996 | | PASS |
|
|
|
Temp. Occ. Cert. #3170 issued 3-19-96 to Primary Health Medical Clinic.
|
INSP - Final | 3/18/1996 | 3/18/1996 | 3/18/1996 | P | FAIL |
Carl Dependahl
|
|
|
03/18/96 340 -
|
INSP - Final | 3/12/1996 | 3/13/1996 | 3/13/1996 | A | NR |
Carl Dependahl
|
|
|
03/12/96 340 -
|
INSP - Carpentry | 2/22/1996 | 2/22/1996 | 2/22/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Ceiling grid | 2/21/1996 | 2/21/1996 | 2/21/1996 | P | PART |
Carl Dependahl
|
|
|
02/21/96 340 -
|
INSP - Ceiling grid | 2/13/1996 | 2/14/1996 | 2/14/1996 | P | PASS |
Carl Dependahl
|
|
|
02/14/96 340 -
|
INSP - Framing/Rough-in | 2/14/1996 | 2/14/1996 | 2/14/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Carpentry | 2/2/1996 | 2/2/1996 | 2/2/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Set-back | 2/1/1996 | 2/1/1996 | 2/1/1996 | | PART |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Energy code compliance | 1/31/1996 | 1/31/1996 | 1/31/1996 | P | PART |
Carl Dependahl
|
|
|
01/31/96 340 -
|
INSP - Carpentry | 1/30/1996 | 1/30/1996 | 1/30/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
(F) Reprint permit | | | 1/26/1996 | | |
|
|
|
|
INSP - Framing/Rough-in | 1/22/1996 | 1/23/1996 | 1/23/1996 | A | PART |
Carl Dependahl
|
|
|
01/23/96 340 -
|
INSP - Carpentry | 1/22/1996 | 1/22/1996 | 1/22/1996 | | PART |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Carpentry | 1/12/1996 | 1/16/1996 | 1/16/1996 | A | PART |
Carl Dependahl
|
|
|
01/16/96 340 -
|
INSP - Framing/Rough-in | 1/12/1996 | 1/12/1996 | 1/12/1996 | P | FAIL |
Carl Dependahl
|
|
|
01/12/96 340 -
|
INSP - Wall cover | 1/11/1996 | 1/11/1996 | 1/11/1996 | P | NR |
Carl Dependahl
|
|
|
01/11/96 340 - SHEETROCK
|
INSP - Conference | 1/9/1996 | 1/9/1996 | 1/9/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
(F) Reprint permit | | | 1/9/1996 | | |
|
|
|
|
INSP - Conference | 1/8/1996 | 1/8/1996 | 1/8/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Footings | 12/21/1995 | 12/21/1995 | 12/21/1995 | P | PART |
Carl Dependahl
|
|
|
12/21/95 340 -
|
INSP - Footings | 11/27/1995 | 11/27/1995 | 11/27/1995 | P | PASS |
Jim Sly
|
|
|
Jim Sly Inspected for Carl.
|
INSP - Footings | 11/27/1995 | 11/27/1995 | 11/27/1995 | | PART |
Carl Dependahl
|
|
|
11/26/95 340 -
|
INSP - Footings | 11/21/1995 | 11/22/1995 | 11/22/1995 | A | PASS |
Carl Dependahl
|
|
|
11/21/95 340 -
|
(F) Reprint permit | | | 11/21/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/15/1995 | | |
|
|
|
|
Permit taken to Permit Desk | | | 11/15/1995 | | PASS |
|
|
|
THERE IS A DOUBLE PLAN REVIEW FEE CHARGED ON THIS PERMIT FOR SUBMITTAL AND COMPLETED PLAN REVIEW UNDER THE 1994 UBC AND THE 1991 UBC.
|
Issue PAID IN FULL permit | | | 11/15/1995 | | I |
|
|
|
|
Plan resubmittals received | | | 11/15/1995 | | PASS |
|
|
|
PLAN RESUBMITTALS RECEIVED AND APPROVED.
|
Inspection Record Card- Bld | | | 11/15/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/15/1995 | | |
|
|
|
|
Plan resubmittals requested | | | 11/14/1995 | | FAIL |
|
|
|
CALL STEVE TROUT REQUESTED ADDITIONAL REVISIONS.
|
Plan resubmittals received | | | 11/9/1995 | | PEND |
|
|
|
|
Routing Off Site - A.C.H.D | 11/1/1995 | | 11/1/1995 | | PASS |
|
|
|
A.C.H.D. IMPACT FEES PAID 11/01/95, CERTIFICATE #95-001558
|
Routing - PUBLIC WORKS | 10/26/1995 | | 10/30/1995 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 10/24/1995 | | 10/25/1995 | | FAIL |
|
|
|
Contacted Steve Trout for A.C.H.D. pickup at ###-####. Fees not paid as of 10-25-95
|
Plan resubmittals received | | | 10/24/1995 | | NA |
|
|
|
THE RESUBMITTED PLANS WERE REVIEWED AND ADDITIONAL CORRECTION ITEMS REQUESTED. LETTER SENT TO THE ARCHITECT 10/24/95.
|
Routing - PUBLIC WORKS | 9/28/1995 | | 10/10/1995 | | FAIL |
|
|
|
|
Routing - FIRE | 9/25/1995 | | 9/27/1995 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/21/1995 | | PEND |
|
|
|
PRELIMINARY PLAN REVIEW SENT TO THE ARCHITECT FOR CORRECTIONS ON 09/22/95.
|
Routing - BUILDING | 9/19/1995 | | 9/21/1995 | | PEND |
|
|
|
PRELIMINARY PLAN REVIEW COMPLETED, WAITING FOR ARCHTECT'S RESPONSE.
|
Routing - ELECTRICAL | 8/21/1995 | | 8/22/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 8/14/1995 | | 8/21/1995 | | PASS |
|
|
|
|
Routing - PLUMBING | 8/9/1995 | | 8/14/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/31/1995 | | 8/8/1995 | | FAIL |
|
|
|
NEEDS ENGINEERS STAMPED PLANS
|
Routing - PLANNING | 7/28/1995 | | 7/31/1995 | | PASS |
|
|
|
|
Application received | | | 7/27/1995 | | PEND |
|
|
|
|
Routing - BUILDING | 10/31/1995 | | | | PEND |
|
|
|
|