Permanent Occupancy | | 3/26/1996 | 3/26/1996 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 3/26/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6343 issued 3-26-96 to Comp U.S.A. in the Milwaukee Marketplace.
|
INSP - Final | 3/19/1996 | 3/19/1996 | 3/19/1996 | P | PASS |
|
|
|
03/19/96 338 -
|
INSP - Final | 2/12/1996 | 2/13/1996 | 2/14/1996 | P | NR |
|
|
|
02/13/96 333 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Conference | 2/6/1996 | 2/6/1996 | 2/6/1996 | | PASS |
|
|
|
/ / 333 - sent approval of reaubmittal
|
INSP - Ceiling grid | 1/29/1996 | 1/29/1996 | 1/29/1996 | P | PASS |
|
|
|
01/29/96 333 - SCLG-OK SUSPENDED CEILING
|
INSP - Framing/Rough-in | 1/10/1996 | 1/10/1996 | 1/10/1996 | P | PASS |
|
|
|
01/10/96 333 - FRAM-OK FRAMING front half
|
INSP - Framing/Rough-in | 1/2/1996 | 1/2/1996 | 1/2/1996 | P | PASS |
|
|
|
01/02/96 333 - call Ed ###-#### FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 12/27/1995 | 12/28/1995 | 12/28/1995 | A | PART |
Carl Dependahl
|
|
|
12/28/95 340 -
|
INSP - Framing/Rough-in | 12/21/1995 | 12/22/1995 | 12/26/1995 | A | PASS |
|
|
|
12/21/95 333 - FRAM-OK FRAMING
|
Issue PAID IN FULL permit | | | 11/1/1995 | | I |
|
|
|
|
Inspection Record Card- Bld | | | 10/27/1995 | | P |
|
|
|
|
Permit taken to Permit Desk | 10/27/1995 | | 10/27/1995 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 10/27/1995 | | P |
|
|
|
|
Routing - FIRE | 10/13/1995 | | 10/19/1995 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 10/12/1995 | | PASS |
|
|
|
RESEARCH HISTORY, CREATE HARD-FILE, PLAN REVIEW, PLAN ANALYSIS, CORRECTION LIST, CONFIRM EXIT DOORS, OCCUPANT LOAD, INPUT TO PERMIT-PLAN, FORWARD TO FIRE.
|
Print Pending Permit.LaserJet4 | | | 10/12/1995 | | PASS |
|
|
|
FILES
|
Routing - ELECTRICAL | 10/9/1995 | | 10/10/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 9/27/1995 | | 10/9/1995 | | PASS |
|
|
|
|
Routing - PLUMBING | 9/27/1995 | | 9/29/1995 | | PASS |
|
|
|
CONFERENCE WITH BILL, LEE, AND DICK RESULTED IN DISCOVERY THAT BILL HAD MISCHECK THE "NOT APPROVED" BOX. DESIGNING ENGINEER RESUBMITTED CORRECTED DRAWINGS OCT 26 FOR INCORPORATION INTO PLANS.
|
Routing - PUBLIC WORKS | 9/25/1995 | | 9/27/1995 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 9/25/1995 | | |
|
|
|
Route to Public Works, Plumbing, Mechanical, Electrical and back to Plan Check. After Plan Check route to Fire Department.
|
Application received | | | 9/22/1995 | | |
|
|
|
|
Routing - BUILDING | 10/10/1995 | | | | PEND |
|
|
|
PLUMBING, AND FIRE APPROVAL TO COME.
|
Routing - BUILDING | 10/20/1995 | | | | PEND |
|
|
|
|