Permanent Occupancy | | 1/11/1996 | 1/11/1996 | | DONE |
|
|
|
|
Permanent Occupancy | | 1/11/1996 | 1/11/1996 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 1/11/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6263 issued 1-11-96 to Discount Carpet & Flooring.
|
INSP - Final | 1/4/1996 | 1/4/1996 | 1/4/1996 | | FAIL |
Jim Sly
|
|
|
Not ready....needs Fire Dept. to sign off.
|
INSP - Carpentry | 12/22/1995 | 12/22/1995 | 12/22/1995 | | PASS |
Jim Sly
|
|
|
Met with Tim the contractor and we looked at construction of building after he uncovered wall. Told Tim to get with architect and come up with configuration for 1 hr wall.
|
INSP - Conference | 12/12/1995 | 12/13/1995 | 12/13/1995 | A | PASS |
Jim Sly
|
|
|
|
Issue PAID IN FULL permit | | | 12/12/1995 | | I |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 12/11/1995 | | PASS |
|
|
|
FILES
|
Print Pending Permit.LaserJet4 | | | 12/11/1995 | | |
|
|
|
|
Routing - BUILDING | 10/25/1995 | | 12/11/1995 | | PASS |
|
|
|
OK TO ISSUE
|
Permit taken to Permit Desk | | | 12/11/1995 | | PASS |
|
|
|
OK TO ISSUE
|
Inspection Record Card- Bld | | | 12/11/1995 | | |
|
|
|
|
Plan Reviewer's activity | | | 12/11/1995 | | PASS |
|
|
|
REVIEW RESUBMITTAL, MARK-UP PLANS, ASSEMBLE, FINAL INPUT TO PERMIT PLAN, ISSUE.
|
Plan resubmittals received | 12/11/1995 | | 12/8/1995 | | PASS |
|
|
|
|
Received Certificate of Value | 12/11/1995 | | 12/8/1995 | | |
|
|
|
|
Plan resubmittals requested | 11/29/1995 | | 11/29/1995 | | |
|
|
|
|
Plan Reviewer's activity | | | 11/29/1995 | | PEND |
|
|
|
RECEIVED RESUBMITTALS INCLUDING MEZZININE FLOOR STRUCTURAL ASSEMBLY. CALCULATIONS REVIELED THIS FLOOR IS 126.8% OVER STRESSED. ISSUE CORRECTION NOTICE TO ARCHITECT FOR CORRECTIVE ACTION.
|
Plan resubmittals received | 11/29/1995 | | 11/28/1995 | | |
|
|
|
|
Routing - FIRE | 10/16/1995 | | 10/25/1995 | | PASS |
|
|
|
|
Routing - BUILDING | 10/6/1995 | | 10/16/1995 | | PEND |
|
|
|
TO FIRE
|
Waiting for Cert. of Value | 10/16/1995 | | 10/16/1995 | | |
|
|
|
|
Plan Reviewer's activity | | | 10/16/1995 | | PEND |
|
|
|
PLAN REVIEW, HISTORY CHECK, PLAN-ANALYSIS, CORRECTION LIST-FAXED TO ARCH AND MANAGER, PERMIT-PLAN INPUT, FOWARD TO FIRE.
|
Plan resubmittals requested | 10/16/1995 | | 10/16/1995 | | |
|
|
|
|
Routing - PLANNING | 10/5/1995 | | 10/6/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/26/1995 | | 10/5/1995 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 9/26/1995 | | |
|
|
|
Route to Public Works and Planning then back to Plan Check. After Plan Check route to Fire Department.
|
Application received | | | 9/25/1995 | | |
|
|
|
|