Case Summary (BLD) | | | 2/6/2003 | | |
|
|
|
|
Case Summary (BLD) | | | 1/14/2003 | | |
|
|
|
|
DOC - Permit Finaled | 1/24/2001 | 1/24/2001 | 1/24/2001 | P | PASS |
Russ Owen
|
|
|
Added by Inspector: 407 On 1/24/2001 2:37:28 PM
|
INSP - Letter of compliance | 9/17/1997 | | 9/17/1997 | | PASS |
|
|
|
Letter of Compliance #12955 issued 9-17-97.
|
Temporary occupancy | | | 9/5/1997 | | PASS |
|
|
|
Temp. Occ. Cert. #3463 issued 9-5-97 to Westpark Corp. Campus, Bldg. C. Note - this will ultimately be issued an L.C. when signed off.
|
INSP - Final | 9/4/1997 | 9/4/1997 | 9/4/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP FOR FINAL OK FOR CERT OF COMPL
|
INSP - Final | 9/3/1997 | 9/4/1997 | 9/4/1997 | P | PART |
|
|
|
09/04/97 338 - OK FOR THE TEMP
|
Routing for occupancy | 9/3/1997 | 9/3/1997 | 9/3/1997 | | PASS |
|
|
|
Inspected by Scott Brown - meets compliance
|
INSP-Final Inspection | 9/2/1997 | 9/3/1997 | 9/3/1997 | A | FAIL |
Joe Tawney
|
|
|
09/03/97 406 - REINSP FOR FINAL FAIL BLDG ADDRESS
|
INSP - Final | 9/2/1997 | 9/3/1997 | 9/3/1997 | P | NR |
|
|
|
09/03/97 338 - CANCELLED BY CTR OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Final | 8/29/1997 | 8/29/1997 | 8/29/1997 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - FINAL ON SHELL FAIL ADDRESS STRIPE & LETTER CURB PROTECT GA
|
INSP - Framing/Rough-in | 7/24/1997 | 7/25/1997 | 7/25/1997 | A | PASS |
|
|
|
07/25/97 338 -
|
INSP - Footings | 6/6/1997 | 6/6/1997 | 6/6/1997 | P | PASS |
|
|
|
06/06/97 338 - poured w/o insp ok with sp insp blessing
|
INSP - Footings | 6/5/1997 | 6/5/1997 | 6/5/1997 | P | PASS |
|
|
|
06/05/97 338 - POURING AT 1:30 made ok with sp insp approval
|
INSP - Footings | 6/3/1997 | 6/4/1997 | 6/4/1997 | P | PASS |
|
|
|
06/04/97 338 - OKWITH SP INSP APPROVAL
|
INSP - Masonry | 6/3/1997 | 6/3/1997 | 6/3/1997 | P | PASS |
|
|
|
06/03/97 338 - made ok with sp insp approval.
|
INSP - Footings | 5/29/1997 | 5/30/1997 | 5/30/1997 | A | PASS |
|
|
|
05/30/97 338 - POURING MONDAY AT 7 11 PANELS.
|
INSP - Wall cover | 5/21/1997 | 5/22/1997 | 5/22/1997 | A | PASS |
|
|
|
05/22/97 338 - WALL REBAR WALL TILT-UP
|
INSP - Foundation | 5/13/1997 | 5/14/1997 | 5/13/1997 | P | PASS |
|
|
|
05/14/97 338 - tilt up slabs for the old falash project
|
INSP - Conference | 5/12/1997 | 5/13/1997 | 5/13/1997 | A | PASS |
|
|
|
05/13/97 338 - the work is startinng forms are being placed as i inspect placed
|
CHANGE STATUS TO (I) | | | 4/25/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/23/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/23/1997 | | |
|
|
|
|
INSP - Conference | 3/6/1997 | 3/10/1997 | 3/9/1997 | A | PASS |
|
|
|
03/10/97 338 - made ok project will continue in early may
|
INSP - Conference | 9/24/1996 | 9/25/1996 | 9/24/1996 | P | PASS |
|
|
|
09/25/96 338 - made ok const in progress
|
Office Staff conference/action | | | 7/16/1996 | | PASS |
|
|
|
PERMIT TO REMAIN IN FORCE. SOME GROUND WORK DONE.AS PER GEORGE SLANE.
|
Issue FEE-DUE permit | | | 9/29/1995 | | |
|
|
|
|
(F) Issue permit | | | 9/29/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/29/1995 | | |
|
|
|
|
Plan Reviewer's activity | | | 9/29/1995 | | PEND |
|
|
|
WESTPARK CORPORATE CAMPUS SHELL BUILDING #C IS APPROVED FOR ISSUE AFTER RECEIPT OF COPY OF A.C.H.D. IMPACT FEE CERTIFICATE.
|
(F) Reprint permit | | | 9/29/1995 | | |
|
|
|
|
Application received | | | | | |
|
|
|
|