Case Summary (BLD) | | | 8/22/2002 | | |
|
|
|
|
Case Summary (BLD) | | | 3/13/2002 | | |
|
|
|
|
Permanent Occupancy | | 9/5/1997 | 9/5/1997 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/5/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6972 issued 9-5-97 to the Jade Village Apts.
|
INSP - Final | 8/28/1997 | 8/28/1997 | 8/28/1997 | | PASS |
|
|
|
/ / 338 - signed the perm col
|
INSP - Final | 8/20/1997 | 8/20/1997 | 8/20/1997 | | NR |
|
|
|
08/20/97 338 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Final | 8/20/1997 | 8/20/1997 | 8/20/1997 | | NR |
|
|
|
08/20/97 338 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Temporary occupancy | | | 9/25/1996 | | PASS |
|
|
|
Temp. Occ. Cert. #3284 issued 9-25-96 to the Jade Village Apts.
|
INSP - Final | 9/23/1996 | 9/24/1996 | 9/23/1996 | A | PART |
|
|
|
09/24/96 338 - OK FOR TEMP OCC SIGNED TEMP LINE ON THE OCC REC CARD
|
INSP - Final | 9/16/1996 | 9/17/1996 | 9/17/1996 | A | PASS |
Joe Tawney
|
|
|
REINSPECTION OK FOR PERM OCC 9/17/96
|
INSP - Final | 9/12/1996 | 9/13/1996 | 9/13/1996 | P | FAIL |
Joe Tawney
|
|
|
REINSPECTION REQ
|
INSP - Final | 9/12/1996 | 9/12/1996 | 9/11/1996 | P | NR |
|
|
|
09/12/96 338 - OTH-OTHER AGENCIES NOT APPROVED c/ left with builder
|
INSP - Framing/Rough-in | 6/4/1996 | 6/4/1996 | 6/4/1996 | | PASS |
|
|
|
/ / 338 - re insp assemblies made ok ok to complete the cover
|
INSP - Framing/Rough-in | 5/17/1996 | 5/17/1996 | 5/17/1996 | | NR |
|
|
|
/ / 338 -
|
INSP - Energy code compliance | 5/10/1996 | 5/10/1996 | 5/10/1996 | | PASS |
|
|
|
/ / 338 - INSL-OK INSULATION-ENERGY CODE
|
INSP - Final | 5/9/1996 | 5/10/1996 | 5/10/1996 | A | CANC |
|
|
|
05/09/96 338 - need 09/44 wrong insp called
|
INSP - Framing/Rough-in | 5/10/1996 | 5/10/1996 | 5/10/1996 | | PASS |
|
|
|
/ / 338 - FRAM-OK FRAMING
|
INSP - Permit holder notice | 12/4/1995 | 12/4/1995 | 12/4/1995 | | PASS |
Jim Storey
|
|
|
/ / 301 -
|
INSP - Carpentry | 11/22/1995 | 11/22/1995 | 11/22/1995 | P | PASS |
Jim Storey
|
|
|
11/22/95 301 - PARTY WALL - TRUSSES
|
INSP - Carpentry | 11/15/1995 | 11/16/1995 | 11/16/1995 | A | CANC |
Jim Storey
|
|
|
11/16/95 301 - PARTY WALL
|
INSP - Wall cover | 11/16/1995 | 11/16/1995 | 11/16/1995 | | PASS |
Jim Storey
|
|
|
/ / 301 -
|
(F) Reprint permit | | | 11/3/1995 | | |
|
|
|
|
INSP - Foundation | 10/25/1995 | 10/25/1995 | 10/25/1995 | P | PASS |
Jim Storey
|
|
|
|
INSP - Footings | 10/19/1995 | 10/19/1995 | 10/19/1995 | P | PASS |
Jim Storey
|
|
|
|
(F) Issue permit | | | 10/5/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/5/1995 | | |
|
|
|
|
Plan Reviewer's activity | | | 10/3/1995 | | PASS |
|
|
|
SEE BLD95-1489 FOR ALL ACTIONS FOR THIS CASE.
|
Permit taken to Permit Desk | 10/3/1995 | | 10/3/1995 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/3/1995 | | PASS |
|
|
|
FILES
|
Application received | | | 1/4/1995 | | PEND |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|