Letter of compliance | | | 2/24/1999 | | PASS |
|
|
|
Letter of Compliance #14986 issued 2-24-99.
|
INSP - Final | 2/5/1999 | 2/5/1999 | 2/5/1999 | A | PASS |
Carl Dependahl
|
|
|
fees paid per collen; ok per 338
|
Permanent Occupancy | | 2/5/1999 | 2/5/1999 | | DONE |
|
|
|
|
DOC - C/O Approved | | | 2/5/1999 | | PASS |
|
|
|
ok for c/o,elec paid, ok per 338, card to Cathy W.
|
INSP - Final | 5/16/1996 | 5/17/1996 | 5/20/1996 | A | FAIL |
|
|
|
05/17/96 338 - ELEC PERMIT FEES NOT PAID
|
INSP - Framing/Rough-in | 4/12/1996 | 4/15/1996 | 4/15/1996 | A | FAIL |
|
|
|
04/12/96 338 - BLDG. #2 ok to cover bath areas there is a serious joist that a bearing wall has been removed.
|
INSP - Conference | 1/22/1996 | 1/22/1996 | 1/22/1996 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 -
|
Issue PAID IN FULL permit | | | 11/15/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/8/1995 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 11/8/1995 | | PASS |
|
|
|
Based on plans submitted, notes on plans & attached plan review comments - all a part of the approved plan.
|
Permit taken to Permit Desk | | | 11/8/1995 | | PASS |
|
|
|
|
Plans taken to the Permit Desk | | | 11/8/1995 | | PASS |
|
|
|
|
Routing - FIRE | 10/26/1995 | | 11/3/1995 | | PASS |
|
|
|
|
Routing - BUILDING | 8/18/1995 | | 10/25/1995 | | PASS |
|
|
|
Week 0f 08/21 thru 8/25 plan reviewer sick. Started review 08/28/95
|
Received Certificate of Value | | | 10/23/1995 | | |
|
|
|
Received new C.V. do to change in tenant expansion area
|
Meeting | | | 10/23/1995 | | |
|
|
|
Meeting with Paul Clayton & Ron Thurber to review resubmittals and architects review of the plans prior to resubmitting.
|
Plan resubmittals received | | | 10/23/1995 | | PASS |
|
|
|
Plan resubmittal includes a reduction of area from original submittal.
|
Meeting | | | 10/20/1995 | | |
|
|
|
Meeting with Paul Clayton to review plans for resubmittal. Set up meeting on 10/23/95 to include architect Ron Thurber and final plan resubmittals.
|
Plan resubmittals requested | | | 10/4/1995 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 10/3/1995 | | |
|
|
|
|
Received Certificate of Value | | | 9/28/1995 | | |
|
|
|
|
Plan resubmittals received | | | 9/28/1995 | | |
|
|
|
|
Plan resubmittals requested | | | 8/29/1995 | | |
|
|
|
Refer to BLD95-1073 when Rascal's was grouped with all changes to 5200 Fairview, Fairview Square.
|
Routing - PUBLIC WORKS | 6/21/1995 | | 6/23/1995 | | PASS |
|
|
|
Refer to BLD95-1073 & PC419-95
|
Plan routing begun/TENANTS | | | 6/21/1995 | | |
|
|
|
|
Application received | | | 6/20/1995 | | |
|
|
|
Separate application was required for Rascal's tenant improvement so a separate Cert. of Occ. can be issued when complete.
|