Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD95-01520
StatusFinaled
Name RASCAL'S
Site Address 5200 W FAIRVIEW AVE
Project NameFAIRVIEW SQUARE
Customer Number 
ePlanReviewNo
Description
To remodel the NW 1/4 of Bldg. Unit #2 to create a 1687 s.f. Game Room Area & a 210 s.f. Office to add to the existing "Seating/Dance Floor Area" of Rascals plus miscelaneous accessory support areas. New total area for Rascals of 7036 s.f. To remodel the rest rooms to comply with A.D.A. A new Certificate of Occupancy is required for this Tenant when project is completed & approved. This building is fully fire sprinklered. Separate Elec., Mech., & Plumbing permits are required. PC649-95 DRS PROJECT $25,000 ELEC $4,200 PLMB $8,500 MEC $4,200 CMB $12,700 FIRE SPRINK $1,000 INITIAL CERTIFICATE OF VALUE ON FILE LAS 11/8/95
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  2/24/1999 PASS
Letter of Compliance #14986 issued 2-24-99.
INSP - Final2/5/19992/5/19992/5/1999APASS
DetailsCarl Dependahl
fees paid per collen; ok per 338
Permanent Occupancy 2/5/19992/5/1999 DONE
Details
DOC - C/O Approved  2/5/1999 PASS
ok for c/o,elec paid, ok per 338, card to Cathy W.
INSP - Final5/16/19965/17/19965/20/1996AFAIL
Details
05/17/96 338 - ELEC PERMIT FEES NOT PAID
INSP - Framing/Rough-in4/12/19964/15/19964/15/1996AFAIL
Details
04/12/96 338 - BLDG. #2 ok to cover bath areas there is a serious joist that a bearing wall has been removed.
INSP - Conference1/22/19961/22/19961/22/1996 FAIL
DetailsCarl Dependahl
/ / 340 -
Issue PAID IN FULL permit  11/15/1995
Inspection Record Card- Bld  11/8/1995
Plan Reviewer's Copy of Permit  11/8/1995 PASS
Based on plans submitted, notes on plans & attached plan review comments - all a part of the approved plan.
Permit taken to Permit Desk  11/8/1995 PASS
Plans taken to the Permit Desk  11/8/1995 PASS
Routing - FIRE10/26/1995 11/3/1995 PASS
Routing - BUILDING8/18/1995 10/25/1995 PASS
Week 0f 08/21 thru 8/25 plan reviewer sick. Started review 08/28/95
Received Certificate of Value  10/23/1995
Received new C.V. do to change in tenant expansion area
Meeting  10/23/1995
Meeting with Paul Clayton & Ron Thurber to review resubmittals and architects review of the plans prior to resubmitting.
Plan resubmittals received  10/23/1995 PASS
Plan resubmittal includes a reduction of area from original submittal.
Meeting  10/20/1995
Meeting with Paul Clayton to review plans for resubmittal. Set up meeting on 10/23/95 to include architect Ron Thurber and final plan resubmittals.
Plan resubmittals requested  10/4/1995
Plan Reviewer's Copy of Permit  10/3/1995
Received Certificate of Value  9/28/1995
Plan resubmittals received  9/28/1995
Plan resubmittals requested  8/29/1995
Refer to BLD95-1073 when Rascal's was grouped with all changes to 5200 Fairview, Fairview Square.
Routing - PUBLIC WORKS6/21/1995 6/23/1995 PASS
Refer to BLD95-1073 & PC419-95
Plan routing begun/TENANTS  6/21/1995
Application received  6/20/1995
Separate application was required for Rascal's tenant improvement so a separate Cert. of Occ. can be issued when complete.