Case Summary (BLD) | | | 6/29/2004 | | |
|
|
|
|
(F) Reprint permit | | | 12/2/1999 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 1/15/1997 | | |
|
|
|
|
INSP - Permanent occupancy | | | 1/15/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6764 issued 1-14-97 to the Courtyard by Marriott Hotel - also includes permits BLD95-1555, BLD95-1556 and BLD96-0236.
|
Permanent Occupancy | | 1/14/1997 | 1/14/1997 | | DONE |
|
|
|
|
INSP - Final | 1/14/1997 | | 1/14/1997 | | PASS |
|
|
|
|
INSP - Occupancy Sign-off | 1/13/1997 | 1/13/1997 | 1/13/1997 | | PASS |
|
|
|
Insp - Art Yingling - Meets compliance w/CU-21-95/DR-15-95 - Final Occ. Signed - Approved to release Bond.
|
INSP - Occupancy Sign-off | 11/15/1996 | 11/15/1996 | 11/15/1996 | | FAIL |
|
|
|
Issues of meeting DR cond. #1b, #1e (add'l shrubs and moving a tree). Providing specific approved shrubs. Cond. #1c - ground cover for NW Pad/pedestrian walkway, stiping drives and issue of Off-Premise Adv. Sign
|
INSP - Temporary occupancy | | | 10/14/1996 | | PASS |
|
|
|
Temp. Occ. #3296 issued 10-14-96 to the Marriott Hotel for pool & spa area.
|
INSP - Temporary occupancy | | | 10/14/1996 | | PASS |
|
|
|
Temp. Occ. Cert. #3295 issued 10-14-96 to the Marriott Hotel for Bldg. Sec. 1.
|
INSP - Final | 10/11/1996 | 10/11/1996 | 10/11/1996 | A | PART |
Wes Worcester
|
|
|
|
INSP - Conference | 10/11/1996 | 10/11/1996 | 10/11/1996 | A | PASS |
Wes Worcester
|
|
|
installing hardware and caulking penetrations
|
INSP - Final | 10/11/1996 | 10/11/1996 | 10/11/1996 | | PASS |
|
|
|
temp occ approved, c/n issued
|
INSP - Temporary occupancy | 10/10/1996 | 10/10/1996 | 10/10/1996 | | PASS |
|
|
|
Insp for temp. by Art Y./Required bonding for landscaping & sprinkler system/Bond posted for $79,123.00 on 10/10/96 temporary occupancy signed.
|
INSP - Conference | 10/4/1996 | 10/4/1996 | 10/4/1996 | | PASS |
|
|
|
/ / 405 - advised on elevator shaft requirements
|
INSP - Conference | 10/4/1996 | 10/4/1996 | 10/4/1996 | | PASS |
|
|
|
/ / 405 - advised on elevator shaft requirements
|
INSP - Fire Dept. Request | 8/20/1996 | 8/20/1996 | 8/20/1996 | | PASS |
|
|
|
/ / 405 - hydrant flush witnessed, ok
|
INSP - Conference | 8/20/1996 | 8/20/1996 | 8/20/1996 | | PART |
|
|
|
/ / 405 - conference with Jim (supt) scheduled to temp final office ar reviewed list of issues critical to office occ
|
INSP - Carpentry | 8/13/1996 | 8/14/1996 | 8/14/1996 | P | PART |
Wes Worcester
|
|
|
FIRE CAULK HALLWAY three floors each side corridors all ok area A still not done
|
INSP - Conference | 5/1/1996 | 5/1/1996 | 5/1/1996 | | PART |
Wes Worcester
|
|
|
/ / 342 -
|
INSP - Framing/Rough-in | 3/21/1996 | 3/21/1996 | 3/21/1996 | P | NR |
Wes Worcester
|
|
|
partial r/i
|
(F) Reprint permit | | | 11/30/1995 | | |
|
|
|
|
Plan resubmittals received | | | 11/29/1995 | | OK |
|
|
|
INFORMATION AND DETAILS THAT WERE REQUESTED 11/17/95 HAVE BEEN RECEIVED AND APPROVED.
|
(F) Reprint permit | | | 11/29/1995 | | |
|
|
|
|
(F) Reprint permit | | | 11/15/1995 | | I |
|
|
|
|
Permit taken to Permit Desk | | | 11/2/1995 | | OK |
|
|
|
THIS PERMIT IS BEING ISSUED AS A PHASED PERMIT. THE PHASE I PORTION OF THIS PERMIT IS BEING RELEASED WITH THE APPROVAL OF THE BUILDING DIRECTOR WITH CONDITIONS.
|
Inspection Record Card- Bld | | | 11/2/1995 | | I |
|
|
|
|
Issue PAID IN FULL permit | | | 11/2/1995 | | I |
|
|
|
|
Routing - PLANNING | 10/10/1995 | | 10/16/1995 | | OK |
|
|
|
|
Plan resubmittals received | | | 10/12/1995 | | NA |
|
|
|
PLAN RESUBMITTALS RECIEVED 10/12/95 - REVIEWED RESUBMITTALS WITHOUT THE ORIGINAL PLANS AND SENT A LETTER TO THE ARCHITECT 10/26/95 REQUESTING ADDITIONAL CHANGES. THERE MAY BE MORE CHANGES REQUIRED AFTER REVIEW OF THE ORIGINAL PLANS.
|
Routing - PUBLIC WORKS | 10/5/1995 | | 10/9/1995 | | FAIL |
|
|
|
|
Routing - BUILDING | 9/20/1995 | | 10/4/1995 | | NA |
|
|
|
PRELIMINARY PLAN REVIEW COMPLETED - PLANS SENT TO JERRY THEIS, ARCHITECT, FOR REVISIONS.
|
Plan resubmittals requested | | | 10/4/1995 | | NA |
|
|
|
PRELIMINARY PLAN REVIEW COMPLETED AND CORRECTION LIST SENT TO ARCHITECT, JERRY THEIS, 10/04/95.
|
Plan Reviewer's activity | | | 9/29/1995 | | NA |
|
|
|
IT WAS DETERMINED THAT THE BUILDING WAS OVER AREA. ON 09/29/95 I CREATED AN ABBREVIATED PLAN CHECK REPORT INDICATING A LIST OF THE LARGER REQUIRED CHANGES AND FAXED MR. THEIS A COPY SO THAT HE COULD BEGIN WORKING ON THOSE ITEMS WHILE I COMPLETED A MORE COMPREHENSIVE CORRECTION LIST.
|
Telephone call | | | 9/28/1995 | | NA |
|
|
|
CALLED JERRY THEIS TO DISCUSS THE PROPOSED BUILDING. I DETERMINED THAT THE BUILDING WAS WELL OVER AREA AND I NEEDED TO KNOW IF ALL OF THE SUBMITTED INFORMATION WAS CORRECT.
|
Routing Off Site - A.C.H.D | 9/7/1995 | | 9/13/1995 | | PEND |
|
|
|
A.C.H.D. IMPACT FEES HAVE NOT BEEN PAID AS OF 10/04/95
|
Routing Off Site - C.D.H | 8/17/1995 | | 9/6/1995 | | OK |
|
|
|
|
Routing - PLANNING | 8/7/1995 | | 8/16/1995 | | NA |
|
|
|
DESIGN REVIEW NOT APPROVED - BOB BROWN HAS APPROVED THE CONDITIONAL USE 08/14/95.
|
Routing - PUBLIC WORKS | 8/4/1995 | | 8/7/1995 | | NA |
|
|
|
STILL NOT THE CORRECT PLANS. JJ
|
Routing - MECHANICAL | 8/3/1995 | | 8/4/1995 | | OK |
|
|
|
|
Routing - PLUMBING | 7/31/1995 | | 8/3/1995 | | OK |
|
|
|
|
Routing - ELECTRICAL | 7/18/1995 | | 7/28/1995 | | OK |
|
|
|
|
Routing - PUBLIC WORKS | 6/29/1995 | | 7/8/1995 | | NA |
|
|
|
SEWER PLANS NEED TO BE ADDED TO DRAINAGE PLANS. JJ
|
Application received | | | 6/28/1995 | | PEND |
|
|
|
|