Case Summary (BLD) | | | 7/12/2001 | | DONE |
|
|
|
|
Permanent Occupancy | | 3/14/1996 | 3/14/1996 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 3/14/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6335 issued 3-14-96 to Kenny Rogers Restaurant.
|
INSP - Final | 3/7/1996 | 3/7/1996 | 3/7/1996 | P | FAIL |
|
|
|
transfered from 338 for inspection health dept has not signed off as of yet cathy has the inspection card structural can sign-off when given the okay from cathy will notifiy perry dick
|
INSP - Temporary occupancy | | | 2/23/1996 | | PASS |
|
|
|
Temp. Occ. Cert. #3144 issued 2-23-96 to Kenny Rogers Restaurant.
|
INSP - Final | 2/22/1996 | 2/23/1996 | 2/22/1996 | A | PART |
|
|
|
ok for temp occ
|
INSP - Ceiling grid | 2/1/1996 | 2/1/1996 | 2/1/1996 | P | PASS |
|
|
|
02/01/96 333 - SCLG-OK SUSPENDED CEILING
|
INSP - Conference | 1/22/1996 | 1/22/1996 | 1/22/1996 | | PASS |
|
|
|
/ / 333 - approved duct shafts
|
INSP - Conference | 1/22/1996 | 1/22/1996 | 1/22/1996 | | PASS |
|
|
|
/ / 333 - approved duct shafts
|
INSP - Carpentry | 1/18/1996 | 1/18/1996 | 1/18/1996 | P | PASS |
|
|
|
01/18/96 333 - DRAFT STOP ok ì
|
INSP - Carpentry | 1/11/1996 | 1/11/1996 | 1/11/1996 | P | PASS |
|
|
|
01/11/96 333 - FRAM-OK FRAMING shafts and shear wall
|
INSP - Framing/Rough-in | 1/9/1996 | 1/10/1996 | 1/10/1996 | A | PASS |
|
|
|
01/09/96 333 - FRAME REINSPECT FRAM-OK FRAMING
|
INSP - Carpentry | 1/10/1996 | 1/10/1996 | 1/10/1996 | P | PASS |
|
|
|
01/10/96 333 - FIRE CHASE approval of detail givento K-2
|
INSP - Framing/Rough-in | 1/8/1996 | 1/9/1996 | 1/10/1996 | A | PART |
|
|
|
01/09/96 333 - shear walls ok to cover inside
|
INSP - Framing/Rough-in | 1/5/1996 | 1/8/1996 | 1/8/1996 | A | FAIL |
|
|
|
01/05/96 333 - OTH-OTHER AGENCIES NOT APPROVED submittals not recieved
|
INSP - Carpentry | 12/27/1995 | 12/28/1995 | 12/28/1995 | A | PART |
Carl Dependahl
|
|
|
12/28/95 340 - shear wall
|
INSP - Footings | 11/17/1995 | 11/20/1995 | 11/20/1995 | A | PASS |
|
|
|
|
Permit taken to Permit Desk | | | 11/17/1995 | | PASS |
|
|
|
|
Issue PAID IN FULL permit | | | 11/17/1995 | | I |
|
|
|
|
Inspection Record Card- Bld | | | 11/17/1995 | | |
|
|
|
|
(F) Reprint permit | | | 11/17/1995 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 11/16/1995 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 11/16/1995 | | 11/16/1995 | | PASS |
|
|
|
|
Routing - BUILDING | 11/16/1995 | | 11/16/1995 | | PASS |
|
|
|
|
Routing - PLUMBING | 11/1/1995 | | 11/1/1995 | | PASS |
|
|
|
|
Routing - BUILDING | 10/25/1995 | | 10/25/1995 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 10/20/1995 | | 10/23/1995 | | PASS |
|
|
|
|
Routing - FIRE | 10/19/1995 | | 10/18/1995 | | PASS |
|
|
|
|
Routing - PLANNING | 10/11/1995 | | 10/13/1995 | | PASS |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 10/11/1995 | | |
|
|
|
|
Plan Reviewer's activity | 10/10/1995 | | 10/10/1995 | | FAIL |
|
|
|
PARTICIAL PLAN REVIEW DONE NO STRUCTURAL CALCULATION AVAILABLE
|
Routing - PLUMBING | 9/22/1995 | | 10/3/1995 | | FAIL |
|
|
|
|
Routing - MECHANICAL | 10/3/1995 | | 10/3/1995 | | PASS |
|
|
|
FIELD VERIFICATION ONLY
|
Routing - PUBLIC WORKS | 9/18/1995 | | 9/22/1995 | | FAIL |
|
|
|
|
Routing - PLANNING | 9/13/1995 | | 9/19/1995 | | FAIL |
|
|
|
CONDITIONAL USE APPROVED DR NOT APPROVED
|
Routing - ELECTRICAL | 8/18/1995 | | 9/13/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/17/1995 | | 8/18/1995 | | FAIL |
|
|
|
|
Routing Off Site - A.C.H.D | 8/14/1995 | | 8/16/1995 | | PEND |
|
|
|
FEE HAVE NOT BEEN PAID
|
Routing Off Site - C.D.H | 8/15/1995 | | 8/15/1995 | | PASS |
|
|
|
|
Application received | | | 8/5/1995 | | PEND |
|
|
|
|
Routing - BUILDING | 10/26/1995 | | | | PEND |
|
|
|
|