INSP - Framing/Rough-in | 1/17/1996 | 1/17/1996 | 11/17/1996 | | PASS |
Bob Archibald
|
|
|
|
INSP - Permanent occupancy | | | 4/8/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6358 issued 4-8-96 to the Mooney Dental Clinic.
|
INSP - Final | 4/5/1996 | 4/5/1996 | 4/5/1996 | | PART |
Bob Archibald
|
|
|
ok for temp. occ. need elec. and p&z for final.
|
Permanent Occupancy | | 4/5/1996 | 4/5/1996 | | DONE |
|
|
|
|
INSP - Conference | 3/26/1996 | 3/26/1996 | 3/26/1996 | | PASS |
Bob Archibald
|
|
|
on final occ. requirements.needs landing at rear exit.
|
INSP - Conference | 2/22/1996 | 2/22/1996 | 2/26/1996 | P | PASS |
|
|
|
door at bath ok
|
INSP - Framing/Rough-in | 1/16/1996 | 1/16/1996 | 1/16/1996 | | FAIL |
Bob Archibald
|
|
|
NOT READY.
|
INSP - Footings | 11/28/1995 | 11/28/1995 | 11/28/1995 | | PASS |
Bob Archibald
|
|
|
PLACED W/OUT INSPECTION APPEARS OK
|
(F) Reprint permit | | | 11/22/1995 | | |
|
|
|
|
INSP - Foundation | 11/21/1995 | 11/21/1995 | 11/21/1995 | | PASS |
Bob Archibald
|
|
|
BASEMENT FOUNDATIONS.
|
INSP - Footings | 11/17/1995 | 11/17/1995 | 11/17/1995 | | PASS |
Bob Archibald
|
|
|
NOT READY IN A.M., MADE OK IN P.M..
|
Permit taken to Permit Desk | | | 11/16/1995 | | PASS |
|
|
|
PERMIT READY FOR ISSUE 11/16/95 - JCM
|
Routing Off Site - A.C.H.D | 11/16/1995 | | 11/16/1995 | | PASS |
|
|
|
A.C.H.D. IMPACT FEES PAID 11/16/95-CERT. #95-001610
|
Inspection Record Card- Bld | | | 11/16/1995 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/16/1995 | | |
|
|
|
|
Plan resubmittals received | | | 11/13/1995 | | PASS |
|
|
|
RESUBMITTED PLANS REVISIONS RECEIVED, 11/13/95, PLANS WERE REVIEWED AND APPROVED 11/14/95.
|
Plan resubmittals requested | | | 10/31/1995 | | NA |
|
|
|
RESUBMITTAL INFORMTION NOT COMPLETE, ADDITIONAL INFORMATION REQUESTED, LETTER SENT TO LARRY KNOPP'S OFFICE.
|
Plan resubmittals received | | | 10/27/1995 | | NA |
|
|
|
PLAN RESUBMITTALS RECEIVED 10/27/95 - NOT COMPLETE - LETTER SENT TO THE ARCHITECT REQUESTING ADDITIONAL REVISIONS 10/31/95.
|
Routing - FIRE | 10/16/1995 | | 10/26/1995 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 9/21/1995 | | 9/21/1995 | | PASS |
|
|
|
IMPACT FEES DO NOT APPEAR TO HAVE BEEN PAID AS OF 10/31/95.
|
Routing - ELECTRICAL | 9/19/1995 | | 9/19/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 8/21/1995 | | 9/18/1995 | | PASS |
|
|
|
No plan review, field verify.
|
Routing - PLUMBING | 8/26/1995 | | 8/28/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/11/1995 | | 8/21/1995 | | PASS |
|
|
|
|
Routing - PLANNING | 8/21/1995 | | 8/21/1995 | | PASS |
|
|
|
|
Application received | | | 8/11/1995 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/11/1995 | | PASS |
|
|
|
|