Case Summary (BLD) | | | 8/28/2008 | | DONE |
|
|
|
|
- INSP SPRINKLER ROUGH-IN/HYDR | 10/15/1996 | 10/15/1996 | 10/15/1996 | | PART |
|
|
|
/ / 405 - compare as built plans to reality, to compare with approved add one head due to partition obstruction between telecom and store room rack storage over 12 ft used one place, two store rooms had material sta within 10" of head.
|
- INSP SPRINKLER ROUGH-IN/HYDR | 9/18/1996 | 9/18/1996 | 9/18/1996 | | PASS |
|
|
|
/ / 405 - eric - tv fp..hydro on existing building system..afvised nee and ug hydro, also advised on theneed for approved plans for final
|
INSP - Permanent occupancy | | | 8/23/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6534 issued 8-23-96 to First Security Bank of Idaho Service Center.
|
INSP - Final | 8/21/1996 | 8/22/1996 | 8/22/1996 | P | PASS |
Jim Storey
|
|
|
08/22/96 301 - FNL -OK FINAL
|
Permanent Occupancy | | 8/22/1996 | 8/22/1996 | | DONE |
|
|
|
|
INSP - Final | 6/20/1996 | 6/20/1996 | 6/20/1996 | P | FAIL |
Jim Storey
|
|
|
06/20/96 301 - COF./TRUCK ENCLOSURE CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Final | 5/8/1996 | 5/9/1996 | 5/9/1996 | P | PASS |
Jim Storey
|
|
|
05/08/96 301 - TCO -TEMP C OF O ISSUED FOR 1,2,3 FLOORS. PENDING EMERG. POWER GEN. IN BLDG. EAST OF NEW STRUC. ELE.FIRE.STRUC TE
|
INSP - Final | 4/22/1996 | 4/22/1996 | 4/22/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - FNL -OK FINAL TCO -TEMP C OF
|
INSP - Conference | 4/4/1996 | 4/4/1996 | 4/4/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 -
|
INSP - Ceiling grid | 4/1/1996 | 4/1/1996 | 4/1/1996 | P | FAIL |
Jim Storey
|
|
|
04/01/96 301 -
|
INSP - Conference | 3/26/1996 | 3/26/1996 | 3/26/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 -
|
INSP - Ceiling grid | 2/21/1996 | 2/21/1996 | 2/21/1996 | P | CANC |
|
|
|
301 area.
|
INSP - Ceiling grid | 2/21/1996 | 2/21/1996 | 2/21/1996 | P | PASS |
Jim Storey
|
|
|
|
Issue PAID IN FULL permit | | | 12/22/1995 | | |
|
|
|
|
Permit taken to Permit Desk | | | 12/20/1995 | | PASS |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 12/20/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/20/1995 | | |
|
|
|
|
Routing - BUILDING | 12/5/1995 | | 12/20/1995 | | PASS |
|
|
|
Drawings approved after resubmittal (received 12-19-95) was approved.
|
Plan resubmittals received | 12/20/1995 | | 12/19/1995 | | |
|
|
|
|
Routing - FIRE | 11/20/1995 | | 12/4/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 11/15/1995 | | 11/20/1995 | | PASS |
|
|
|
no review
|
Routing - ELECTRICAL | 11/15/1995 | | 11/17/1995 | | PASS |
|
|
|
no review
|
Plan routing begun/TENANTS | | | 11/15/1995 | | |
|
|
|
Routing resumes after UBC plan check
|
Routing - BUILDING | 10/19/1995 | | 11/15/1995 | | FAIL |
|
|
|
UBC plan review completed. One (1) item requires a response from the Architect.
|
Routing - PUBLIC WORKS | 10/17/1995 | | 10/18/1995 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | 10/16/1995 | | 10/16/1995 | | |
|
|
|
Route to Public Works then back to Plan Check. After Plan Check route to Fire Department.
|
Application received | | | 10/13/1995 | | |
|
|
|
|
Routing - BUILDING | 12/5/1995 | | | | PEND |
|
|
|
|