Permanent Occupancy | | 6/18/1996 | 6/18/1996 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 6/18/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6448 issued 6-18-96 to Dr. Craig Smith.
|
INSP - Final | 6/17/1996 | 6/18/1996 | 6/17/1996 | A | PASS |
Wes Worcester
|
|
|
06/17/96 342 - FINAL FOR C/O.
|
INSP - Framing/Rough-in | 5/16/1996 | 5/17/1996 | 5/11/1996 | P | NR |
Wes Worcester
|
|
|
05/16/96 342 -
|
INSP - Carpentry | 5/10/1996 | 5/10/1996 | 5/4/1996 | P | PASS |
Wes Worcester
|
|
|
05/10/96 342 - 2:30 APT nailing of shr wall ok
|
INSP - Conference | 5/4/1996 | 5/4/1996 | 5/4/1996 | | PASS |
Wes Worcester
|
|
|
/ / 342 - discussed 1 hr property wall and it is to be rocked continuo
|
INSP - Temporary occupancy | | | 4/26/1996 | | PASS |
|
|
|
Temp. Occ. Cert. #3197 issued 4-26-96 to Dr. Smith's Dental Ofc. (the addn. only).
|
INSP - Temporary occupancy | 4/25/1996 | 4/26/1996 | 4/20/1996 | A | NR |
Wes Worcester
|
|
|
04/25/96 342 -
|
INSP - Conference | 4/20/1996 | 4/20/1996 | 4/20/1996 | | PART |
Wes Worcester
|
|
|
/ / 342 - handrails, guardrails, fire resistive const
|
INSP - Temporary occupancy | 4/24/1996 | 4/24/1996 | 4/19/1996 | P | NR |
Wes Worcester
|
|
|
04/24/96 342 -
|
INSP - Conference | 4/19/1996 | 4/19/1996 | 4/19/1996 | | CANC |
Wes Worcester
|
|
|
/ / 342 - first thing Thurs AM
|
INSP - Conference | 4/19/1996 | 4/19/1996 | 4/19/1996 | | FAIL |
Wes Worcester
|
|
|
/ / 342 - first thing in am ...NO SHOW
|
INSP - Ceiling grid | 4/11/1996 | 4/11/1996 | 4/11/1996 | P | PASS |
|
|
|
|
INSP - Framing/Rough-in | 3/11/1996 | 3/12/1996 | 3/12/1996 | A | PART |
Wes Worcester
|
|
|
upstairs only...cking on 1 hr ceiling and Oxygen storage rm 1 hr
|
INSP - Carpentry | 3/4/1996 | 3/5/1996 | 3/5/1996 | A | PART |
Wes Worcester
|
|
|
|
INSP - Footings | 2/27/1996 | 2/28/1996 | 2/28/1996 | A | PART |
Wes Worcester
|
|
|
RETAINING WALL REBAR special inspector on site
|
INSP - Wall cover | 2/21/1996 | 2/21/1996 | 2/21/1996 | P | PASS |
Wes Worcester
|
|
|
nailing 1 hr wall South side ok
|
INSP - Foundation | 2/15/1996 | 2/15/1996 | 2/15/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Foundation | 2/13/1996 | 2/14/1996 | 2/14/1996 | A | NR |
Wes Worcester
|
|
|
|
INSP - Foundation | 2/5/1996 | 2/5/1996 | 2/5/1996 | P | PASS |
|
|
|
02/05/96 338 - REBAR FDN -OK FOUNDATION
|
INSP - Foundation | 2/2/1996 | 2/5/1996 | 2/5/1996 | P | PART |
Wes Worcester
|
|
|
|
INSP - Footings | 1/31/1996 | 1/31/1996 | 1/31/1996 | P | PART |
Wes Worcester
|
|
|
front ftg
|
INSP - Foundation | 1/24/1996 | 1/24/1996 | 1/24/1996 | | PASS |
Wes Worcester
|
|
|
/ / 342 - moving stirrups on 2nd pier East wall, special inspector on
|
INSP - Foundation | 1/23/1996 | 1/24/1996 | 1/24/1996 | A | PASS |
Wes Worcester
|
|
|
01/24/96 342 - REBAR
|
INSP - Foundation | 1/17/1996 | 1/18/1996 | 1/20/1996 | A | NR |
Wes Worcester
|
|
|
01/18/96 342 - REBAR
|
INSP - Footings | 1/11/1996 | 1/11/1996 | 1/19/1996 | P | FAIL |
Jim Sly
|
|
|
75% Complete with re-bar Special Inspector to inspect befor pouring.
|
INSP - Footings | 1/17/1996 | 1/17/1996 | 1/17/1996 | | PASS |
Wes Worcester
|
|
|
/ / 342 -
|
INSP - Foundation | 1/17/1996 | 1/17/1996 | 1/17/1996 | P | PART |
Wes Worcester
|
|
|
01/17/96 342 - fnd.rebar in dirt. corrected while on site, special insp
|
INSP - Footings | 1/16/1996 | 1/16/1996 | 1/16/1996 | P | FAIL |
Wes Worcester
|
|
|
01/16/96 342 - rebar
|
INSP - Foundation | 1/11/1996 | 1/11/1996 | 1/11/1996 | | PART |
Wes Worcester
|
|
|
/ / 342 - special insp on site and will underpin adjacent bldg ftg and
|
INSP - Foundation | 1/10/1996 | 1/11/1996 | 1/11/1996 | A | NR |
Wes Worcester
|
|
|
01/10/96 342 - REBAR special inspector to be on site
|
INSP - Footings | 1/3/1996 | 1/4/1996 | 1/4/1996 | A | PASS |
Wes Worcester
|
|
|
01/04/96 342 - rebar dowels had improper cover, breaking ties and adjust arrived on site. Note to resubmit change in rebar placement from #5 to
|
Issue PAID IN FULL permit | | | 12/13/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/20/1995 | | |
|
|
|
|
Routing - BUILDING | 11/20/1995 | | 11/20/1995 | | PASS |
|
|
|
|
Permit taken to Permit Desk | | | 11/20/1995 | | PASS |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 11/20/1995 | | PASS |
|
|
|
|
Routing - FIRE | 11/16/1995 | | 11/17/1995 | | PASS |
|
|
|
|
Plan resubmittals received | | | 11/7/1995 | | PASS |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 10/24/1995 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 10/11/1995 | | 10/13/1995 | | PASS |
|
|
|
|
Routing - PLUMBING | 9/15/1995 | | 9/29/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 9/15/1995 | | 9/18/1995 | | PASS |
|
|
|
No plan review, field verified
|
Routing - ELECTRICAL | 9/14/1995 | | 9/14/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/1/1995 | | 9/12/1995 | | FAIL |
|
|
|
|
Routing - PLANNING | 8/28/1995 | | 8/31/1995 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 8/18/1995 | | 8/28/1995 | | PASS |
|
|
|
Impact fee certificate #95-001201 received 08-28-95 for $5,343.00.
|
Plan routing begun/NEW & ADDTN | | | 8/18/1995 | | PASS |
|
|
|
|
Received Certificate of Value | | | 8/16/1995 | | PASS |
|
|
|
|
Application received | | | 8/16/1995 | | PASS |
|
|
|
|
INSP - Foundation | 1/25/1996 | 1/26/1996 | 1/26/1995 | A | PART |
Wes Worcester
|
|
|
FND. REBAR, cautioned about over vibrating, pouring w/special insp on site
|
Routing - BUILDING | 10/17/1995 | | 1/24/1995 | | FAIL |
|
|
|
CORRECTIONS WRITTEN AND SENT 10/24/95
|