Case Summary (BLD) | | | 11/10/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 7/12/2007 | | |
|
|
|
|
Permanent Occupancy | | 6/21/1996 | 6/21/1996 | | DONE |
|
|
|
|
INSP - Final | 6/20/1996 | 6/21/1996 | 6/21/1996 | A | PART |
Wes Worcester
|
|
|
FRI. LATE A.M. TEMPORARY OK, FINAL OK, ELELVATOR OK
|
INSP - Final | 6/21/1996 | 6/21/1996 | 6/21/1996 | | PART |
Wes Worcester
|
|
|
06/21/96 342 - FRI. LATE A.M.
|
INSP - Permanent occupancy | | | 6/21/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6453 issued 6-21-96 to the 1st Presbyterian Church (remodel & renovation)
|
INSP - Final | 6/7/1996 | 6/7/1996 | 6/7/1996 | P | PART |
Wes Worcester
|
|
|
06/07/96 342 -
|
INSP - Temporary occupancy | | | 6/7/1996 | | PASS |
|
|
|
Temp. Occ. Cert. #3229 issued 6-7-96 to the First Presbyterian Church.
|
INSP - Final | 6/5/1996 | 6/5/1996 | 6/5/1996 | P | NR |
Wes Worcester
|
|
|
06/05/96 342 - THIS IS THE ONE YOU DID THIS A.M.
|
INSP - Final | 5/30/1996 | 5/30/1996 | 5/30/1996 | | NR |
Wes Worcester
|
|
|
/ / 342 -
|
INSP - Final | 6/4/1996 | 6/4/1996 | 5/29/1996 | P | NR |
Wes Worcester
|
|
|
06/04/96 342 - 3 P.M. APPOINTMENT
|
INSP - Final | 5/30/1996 | 5/31/1996 | 5/25/1996 | P | NR |
Wes Worcester
|
|
|
05/31/96 342 - FRI. P.M.
|
INSP - Ceiling grid | 5/24/1996 | 5/24/1996 | 5/18/1996 | P | NH |
Wes Worcester
|
|
|
05/24/96 342 -
|
INSP - Ceiling grid | 5/15/1996 | 5/16/1996 | 5/11/1996 | P | CANC |
Wes Worcester
|
|
|
05/15/96 342 - This is for a suspended ceiling inspection. Wes sick
|
INSP - Conference | 5/10/1996 | 5/10/1996 | 5/4/1996 | P | PASS |
Wes Worcester
|
|
|
05/10/96 342 - met w/architect and he is to advise contractor of fix for
|
INSP - Carpentry | 4/8/1996 | 4/9/1996 | 4/9/1996 | A | PASS |
Wes Worcester
|
|
|
|
INSP - Footings | 4/1/1996 | 4/2/1996 | 3/30/1996 | A | PASS |
Wes Worcester
|
|
|
04/02/96 342 - EARLY A.M. PLEASE partial in basement
|
INSP - Footings | 3/20/1996 | 3/21/1996 | 3/21/1996 | A | PART |
Wes Worcester
|
|
|
LATE AM PLEASE 1st 8' and adjoining ftg
|
INSP - Footings | 3/18/1996 | 3/19/1996 | 3/15/1996 | A | PASS |
Wes Worcester
|
|
|
03/18/96 342 - EARLY TUES.A.M. FLOOR FOOTING....ELEVATOR PIT...... rebar ok. retaining wall awaiting engineering.
|
INSP - Ceiling grid | 3/14/1996 | 3/15/1996 | 3/11/1996 | A | PART |
Wes Worcester
|
|
|
03/15/96 342 - only two rooms ready, will look at remainder next week
|
INSP - Framing/Rough-in | 3/7/1996 | 3/8/1996 | 3/8/1996 | P | PART |
Wes Worcester
|
|
|
Lindsey corridor and a portion of all others ok after plumb insp
|
INSP - Foundation | 2/26/1996 | 2/27/1996 | 2/27/1996 | P | NR |
Wes Worcester
|
|
|
LATE PM. FND. WALL not ready, ck back 02/28 at 1 pm. Note they have changed elevator ftgs. and grade beam brng.
|
INSP - Carpentry | 2/15/1996 | 2/16/1996 | 2/16/1996 | A | NR |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 1/31/1996 | 1/31/1996 | 1/31/1996 | P | PART |
Wes Worcester
|
|
|
outside corridor
|
INSP - Framing/Rough-in | 1/26/1996 | 1/26/1996 | 1/26/1996 | P | PART |
Wes Worcester
|
|
|
corridor wall ok, and has been changed since conference when it was noted that there was not a continous membrane at wall
|
INSP - Flatwork | 1/24/1996 | 1/24/1996 | 1/24/1996 | P | CANC |
Wes Worcester
|
|
|
01/24/96 342 - no insp required
|
INSP - Carpentry | 1/24/1996 | 1/24/1996 | 1/24/1996 | | PASS |
Wes Worcester
|
|
|
/ / 342 - 1 hr wall is incorrect. Correcting
|
INSP - Foundation | 1/22/1996 | 1/23/1996 | 1/24/1996 | A | PASS |
Wes Worcester
|
|
|
01/23/96 342 - FND. STEM WALLS.
|
INSP - Footings | 1/19/1996 | 1/22/1996 | 1/22/1996 | A | PASS |
Wes Worcester
|
|
|
01/19/96 342 -
|
Telephone call | | | 1/3/1996 | | |
|
|
|
Called Terry Butler at 10:00 am Jan. 3, 1996. Ask him to call Sundance Construction and have them submitt a new Certificate of Value.
|
Plan Reviewer's Copy of Permit | | | 1/3/1996 | | |
|
|
|
|
Waiting for Cert. of Value | 1/3/1996 | | 1/3/1996 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/3/1996 | | |
|
|
|
|
Permit taken to Permit Desk | | | 1/3/1996 | | PASS |
|
|
|
|
Routing - BUILDING | 12/18/1995 | | 1/3/1996 | | PASS |
|
|
|
Drawings approved after Dec. 29, 1995 resubmittal was recieved.
|
Inspection Record Card- Bld | | | 1/3/1996 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 1/3/1996 | | |
|
|
|
|
Received Certificate of Value | 1/3/1996 | | 1/3/1996 | | |
|
|
|
|
Plan resubmittals received | 1/3/1996 | | 12/29/1995 | | |
|
|
|
|
Routing - FIRE | 12/11/1995 | | 12/18/1995 | | PASS |
|
|
|
|
Plan resubmittals requested | 12/8/1995 | | 12/8/1995 | | |
|
|
|
|
Routing - BUILDING | 11/7/1995 | | 12/8/1995 | | FAIL |
|
|
|
UBC plan review was started on 11-30-95. The preliminary review was completed 12-08-95. Eleven (11) items require a response from the Architect.
|
Routing - MECHANICAL | 10/24/1995 | | 11/6/1995 | | PASS |
|
|
|
No plan review, field verified.
|
Routing - PLUMBING | 10/23/1995 | | 10/27/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 10/19/1995 | | 10/23/1995 | | PASS |
|
|
|
|
Routing - PLANNING | 10/17/1995 | | 10/18/1995 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 10/17/1995 | | |
|
|
|
Planning, Public Works, Mechanical, Plumbing, Electrical then back to Plan Check. After Plan Check route to Fire Department.
|
Application received | | | 10/16/1995 | | |
|
|
|
|
Routing - BUILDING | 12/18/1995 | | | | |
|
|
|
|